Breakthrough on Slovakia’s D1 tunnel near Zilina

Workers in Slovakia have broken through the first of two passages in a tunnel near Zilina as part of an 11km D1 highway project. Breakthrough of the second passage of the tunnel on the section Hricovske Podhradie-Lietavska Lucka will likely be in January. Around 80m are still to be bored, according to a report in the Slovak Spectator on-line newspaper. Zilina is in northwestern Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders. Juraj Valent, head of the Na
December 12, 2016 Read time: 2 mins
Workers in Slovakia have broken through the first of two passages in a tunnel near Zilina as part of an 11km D1 highway project.

Breakthrough of the second passage of the tunnel on the section Hricovske Podhradie-Lietavska Lucka will likely be in January. Around 80m are still to be bored, according to a report in the Slovak Spectator on-line newspaper.

Zilina is in northwestern Slovakia, around 200km from the capital Bratislava and close to the Czech and Polish borders.

Juraj Valent, head of the National Highway Company (NDS), said the section with its two tunnels and 11 bridges is scheduled for completion by October 2018. Cost is around €427 million, with money coming from the central government and the European Union.

Slovakia’s D1 motorway runs from the western border with the Czech Republic to the eastern border with the Ukraine, a 100km frontier amid remote forested areas. The government has been building and renovating the route since 1985 when a cross-country route was planned in earnest. The D1 also forms part of the European routes E50, E58, E75 E571.

Related Content

  • Delay for Tvrdosin-Nizna R3 section in Slovakia
    June 22, 2023
    The NDS agency has not reported by how much the contracted cost of €62 million will rise.
  • Slovakia concerned over tenders for D1 Presov and D3 Cadca bypasses
    September 14, 2016
    The Slovakian government is examining bids for two tenders for motorway stretches D1 because of their higher-than-expected costs. The deal involves the Presov West - Presov South stretch and the D3 Cadca, Bukov - Svrcinovec section, according to a report in Pravda. Both projects are bypasses of Cadca, near the border with Poland and the Czech Republic, and Presov in eastern Slovakia. The newly appointed transport minister, Arpad Ersek, review the tenders, the Pravda report said. The Slovak Insti
  • Slovakia’s troubled D1 highway
    February 20, 2012
    Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.
  • Slovakia’s D1 motorway Korbelka tunnel could cost €278mn
    August 19, 2016
    The D1 motorway tunnel Korbelka in Slovakia is estimated to now cost €278 million, according to a report in Pravda Slovakia. But the chosen 6km route is a safer option than another route alongside the Vah River that would have taken in a potential landslide area. Because of the slide risk, a further €202 million would be needed to shore up the hillside. More work will have to be done to finalise the route, meaning work would not start until likely 2019, according to the report. Slovakia's Transport