BESIX-MTH awards Nordhavn work to Bravida

Bravida Denmark, on behalf of the BESIX-MTH joint venture, will install plumbing, electricity, ventilation, road lighting and light signals for Copenhagen’s Nordhavn Tunnel.
By David Arminas February 5, 2024 Read time: 2 mins
Preparation work started last May on the 1.4km-long Nordhavn Tunnel which will be an extension of a 620m-long cut-and-cover tunnel that is part of the Nordhavnsvej project (image courtesy the Danish Road Directorate, Vejdirektoratet)

The BESIX-MTH joint venture has appointed Bravida Denmark for installation work on the Nordhavn Tunnel project in Copenhagen.

The project, worth more €26.7 million, includes a new stage from Svanemøllen to Nordhavn. Design and planning work is already underway, with production set to start in 2024 and expected completion in summer 2027.

Bravida's work includes installation of plumbing, electricity, ventilation, road lighting and light signals, said Nikolaj Bøhmer Jensen, a regional director at Bravida Denmark.

Bravida is a subcontractor to the joint-venture partnership BESIX-MTH and has worked in close collaboration since the project’s start, noted Michael Benedict Thulstrup, deputy project director at BESIX-MTH. The joint venture also is working closely with one of Denmark’s largest infrastructure contractors, MT Højgaard Danmark and together have worked on Stockholm’s E4 tunnel.

The Nordhavn Tunnel will offer more direct access to the urban development areas in both outer and inner Nordhavn. It will also improve access to harbour activities in the area and divert a significant portion of heavy traffic from Østerbro's road network.

Vejdirektoratet, the Danish Road Directorate, in collaboration with the city of Copenhagen and By & Havn, is overseeing the construction of the Nordhavn Tunnel. By & Havn is tasked with developing Ørestad and the port of Copenhagen  and runs the daily operations of the port through its subsidiary, Copenhagen Malmö Port.

Preparation work started last May on the 1.4km-long Nordhavn Tunnel which will be an extension of a 620m-long cut-and-cover tunnel that is part of the Nordhavnsvej project.

The Nordhavnsvej – or Northern Harbour Link - is a 3km-long four-lane two-tube bypass being built between Nordhavn and Helsingørmotorvejen (Elsinore Highway) in northern Copenhagen, Denmark. At €$323 million, the project was Copenhagen’s largest road infrastructure project in the past 50 years. The road runs through the heavily populated downtown district and improves the connection between the Helsingør motorway and the northern port area of the capital city.

Nordhavnsvej Consortium comprised E Pihl & Søn and Ed. Züblin is responsible for the construction and operation of the project, and includes five-year maintenance of the tunnel. Formwork design and installation was done by PERI Group.

Ramboll was the client’s general consultant responsible for all phases of the project, from planning, preliminary design and environmental impact assessment to tender design and supervision.

For more information on companies in this article

Related Content

  • Kronprinsesse Marys Bro bridges Roskilde Fjord
    January 10, 2019
    A BESIX joint venture is giving the royal treatment to the new Kronprinsesse Marys Bro across Roskilde Fjord, writes David Arminas It was announced in September 2016 that Belgian group BESIX, in a joint venture (RBAI) with Italian firm Rizzani de Eccher and Spanish company Acciona Infraestructuras, had been chosen for the €133 million project. The award, by client Vejdirektoratet (Danish Road Directorate), marked the entry of BESIX into the Scandinavian market. Vejdirektoratet praised the winning bid as
  • BESIX buying STRABAG’s Netherlands subsidiary
    February 1, 2021
    BESIX is buying STRABAG’s Netherlands-based subsidiary.
  • Denmark’s Roskilde Bridge officially opened
    October 1, 2019
    The official opening of Denmark’s new Roskilde Bridge has been carried out. The structure has been named Crown Princess Mary´s Bridge. The 1.3km structure is the first cantilevered bridge to be built in Denmark since 1970. Construction took 36 months and the work was completed three months ahead of schedule. The project posed some challenges to the engineers and designers as the construction work was subject to environmental restrictions. Because it lies close to a residential area and a summerhouse area,
  • Contracts are about to be signed for the Fehmarnbelt Fixed Link
    March 13, 2015
    Nearly eight years after Denmark and Germany agreed to construct a major undersea road and rail tunnel, the first contracts are about to be signed. David Arminas reports. Construction is due to start later this year on one of Europe’s most ambitious, as well as the world’s longest, road and rail tunnels, the 17.6km Fehmarnbelt Fixed Link between Germany and Denmark. Fehmarnbelt is expected to cost around US$7.5 billion and be five times the length of the Øresund tunnel between the Danish capital Copenhagen