Bertha readies for more Seattle SR99 Alaskan Way Viaduct tunnel work

Bertha, one of the world’s largest tunnelling machines will resume work underneath the US city of Seattle in November, nearly two years after breaking down. Bertha, at 17.4m diameter, began her journey in July 2013. She was boring a path to relocate a 3.2km stretch of the elevated State Route 99 Alaskan Way Viaduct, built between 1949 and 1953 and which carries around 100,000 vehicles daily. The elevated section will be moved underground allowing the creation of public space along Seattle’s downtown w
July 27, 2015 Read time: 3 mins
RSSBertha, one of the world’s largest tunnelling machines will resume work underneath the US city of Seattle in November, nearly two years after breaking down.

Bertha, at 17.4m diameter, began her journey in July 2013. She was boring a path to relocate a 3.2km stretch of the elevated State Route 99 Alaskan Way Viaduct, built between 1949 and 1953 and which carries around 100,000 vehicles daily.

The elevated section will be moved underground allowing the creation of public space along Seattle’s downtown waterfront. Options apart from a deep-bore tunnel included replacing it with a cut-and-cover tunnel, replacing it with another elevated highway or demolishing it and not replacing it.

But the construction schedule was severely disrupted in December 2013. After travelling around 305m, Bertha over heated and abruptly stopped. Contractor Seattle Tunnel Partners (STP) discovered damage to the machine’s seal system and contamination within the main bearing.

“Fully disassembling and assessing the machine was always the key to determining how long the repairs would take,” said Chris Dixon, STP project manager. “We want to reassemble the machine and resume tunnelling as quickly as possible, but we also want to ensure the repairs are done right.”

STP and 233 Hitachi are responsible for the repair effort, including the machine’s schedule. While the machine has been under repair, STP said it has continued essential work at the future tunnel portals, including construction of ramp and highway connections and the buildings that will house tunnel operations.

“The contractor’s schedule has changed, but the contract that governs their work remains the same,” said 914 Washington State Department of Transportation’s Todd Trepanier, the Alaskan Way Viaduct Replacement Programme administrator.

“The state is a paying customer in this transaction, and we’re intent on getting what we contracted for. We will continue to protect taxpayers and hold the contractor responsible for their work as they deliver this vital project.”

Bertha was made especially for the project by Japanese tunnelling machine specialist Hitachi Zosen. She was shipped in dismantle from Japan to Seattle in spring 2013 then reassembled in a pit nearly 25m deep to the west of Seattle’s athletics stadiums. Bertha’s owner, Seattle Tunnel Partners, the contracting team that’s building the tunnel, is responsible for ensuring she functions properly.

A report by the Seattle Times newspaper, the US$2 billion tunnel is the largest piece of the state’s $3.1 billion programme to replace the Alaskan Way Viaduct. Before tunnel boring started July 30, 2013, state officials said the tunnel would open by the end of 2015. The Times also noted that the front end of Bertha is still dismantled and laying along the downtown waterfront.

But STP said tunnelling will resume on November 23, with the machine emerging at the north end of downtown in late 2016. Traffic will start to use the double-deck four-lane, tolled Highway 99 tunnel from the neighbourhood of Sodo to that of South Lake Union within Seattle in early 2018, according to a revised schedule.

STP has already started some preparation work on the SR 99 southbound roadway inside the first stretch of bored tunnel (see pic).

For the story of Bertha, click on the website of Washington State Department of Transportation.

For more information on companies in this article

Related Content

  • Italian highway bridge and tunnel link
    February 21, 2022
    A major Italian highway bridge and tunnel link is under construction.
  • ARTBA calls for more bridge repairs in US
    February 18, 2016
    The American Road & Transportation Builders Association (ARTBA) is calling for more bridge repairs in the US. There are still too many structurally deficient bridges in the US according to a recent analysis. This report states that while there were 2,574 fewer structurally deficient bridges in 2015 compared to the number in 2014, there are still 58,500 on the structurally deficient list. Worse still, at the current pace of bridge investment it will take at least 21 years before these bridges are all replace
  • Final touches for Seattle’s SR520 floating bridge
    November 21, 2017
    Construction crews in the US state of Washington are finishing bicycle trails and pedestrian paths leading up to the award-winning SR 520 floating bridge. The Evergreen Point Floating Bridge - officially now the Governor Albert D. Rosellini Bridge - carries Washington State Route 520 across Lake Washington in Seattle. The 2.35km-long floating span is the longest floating bridge in the world and at 35m the world's widest. It opened in April last year as a replacement for the original 50-year-old four-lane
  • Switzerland’s new tunnel bore being built
    April 19, 2018
    A major new road tunnel project is being constructed in Switzerland – Mike Woof writes Construction work is now underway in Switzerland for the new Belchen Tunnel bore, a project that has resulted from the country’s long-term infrastructure planning. The building of this latest tunnel is important for Switzerland economically as it will deliver an upgraded link for a major transport infrastructure connection. When it is complete, the tunnel will form part of the vital A2 route between Basel, in the north