Bertha readies for more Seattle SR99 Alaskan Way Viaduct tunnel work

Bertha, one of the world’s largest tunnelling machines will resume work underneath the US city of Seattle in November, nearly two years after breaking down. Bertha, at 17.4m diameter, began her journey in July 2013. She was boring a path to relocate a 3.2km stretch of the elevated State Route 99 Alaskan Way Viaduct, built between 1949 and 1953 and which carries around 100,000 vehicles daily. The elevated section will be moved underground allowing the creation of public space along Seattle’s downtown w
July 27, 2015 Read time: 3 mins
RSSBertha, one of the world’s largest tunnelling machines will resume work underneath the US city of Seattle in November, nearly two years after breaking down.

Bertha, at 17.4m diameter, began her journey in July 2013. She was boring a path to relocate a 3.2km stretch of the elevated State Route 99 Alaskan Way Viaduct, built between 1949 and 1953 and which carries around 100,000 vehicles daily.

The elevated section will be moved underground allowing the creation of public space along Seattle’s downtown waterfront. Options apart from a deep-bore tunnel included replacing it with a cut-and-cover tunnel, replacing it with another elevated highway or demolishing it and not replacing it.

But the construction schedule was severely disrupted in December 2013. After travelling around 305m, Bertha over heated and abruptly stopped. Contractor Seattle Tunnel Partners (STP) discovered damage to the machine’s seal system and contamination within the main bearing.

“Fully disassembling and assessing the machine was always the key to determining how long the repairs would take,” said Chris Dixon, STP project manager. “We want to reassemble the machine and resume tunnelling as quickly as possible, but we also want to ensure the repairs are done right.”

STP and 233 Hitachi are responsible for the repair effort, including the machine’s schedule. While the machine has been under repair, STP said it has continued essential work at the future tunnel portals, including construction of ramp and highway connections and the buildings that will house tunnel operations.

“The contractor’s schedule has changed, but the contract that governs their work remains the same,” said 914 Washington State Department of Transportation’s Todd Trepanier, the Alaskan Way Viaduct Replacement Programme administrator.

“The state is a paying customer in this transaction, and we’re intent on getting what we contracted for. We will continue to protect taxpayers and hold the contractor responsible for their work as they deliver this vital project.”

Bertha was made especially for the project by Japanese tunnelling machine specialist Hitachi Zosen. She was shipped in dismantle from Japan to Seattle in spring 2013 then reassembled in a pit nearly 25m deep to the west of Seattle’s athletics stadiums. Bertha’s owner, Seattle Tunnel Partners, the contracting team that’s building the tunnel, is responsible for ensuring she functions properly.

A report by the Seattle Times newspaper, the US$2 billion tunnel is the largest piece of the state’s $3.1 billion programme to replace the Alaskan Way Viaduct. Before tunnel boring started July 30, 2013, state officials said the tunnel would open by the end of 2015. The Times also noted that the front end of Bertha is still dismantled and laying along the downtown waterfront.

But STP said tunnelling will resume on November 23, with the machine emerging at the north end of downtown in late 2016. Traffic will start to use the double-deck four-lane, tolled Highway 99 tunnel from the neighbourhood of Sodo to that of South Lake Union within Seattle in early 2018, according to a revised schedule.

STP has already started some preparation work on the SR 99 southbound roadway inside the first stretch of bored tunnel (see pic).

For the story of Bertha, click on the website of Washington State Department of Transportation.

For more information on companies in this article

Related Content

  • Hitachi ZX135US-5 and ZX210LC-5 excavators work in Sjodalen valley
    July 7, 2016
    Norwegian contractor Skogen has started building a service road for a log-cabin development in Norway’s Sjodalen valley. More than 90 of the 120m2 cabins are being constructed to order and the project is scheduled to be completed within the next 12 months. The Vågå-based company was set up in 1982 by owner Ola Skogen and is firmly focused on general construction activities including groundworks and roads, as well as foundations, drainage and utilities for log cabins. The contractor’s medium excavat
  • How Florida paved the way for availability payments in the US
    November 21, 2014
    New financing models have been used to deliver key transport links in the US - * Patrick D Harder and Brandon J Davis Florida Department of Transportation’s (FDOT) public-private partnership (PPP) programme has made impressive progress, setting precedents for US transportation planning and funding. On March 26th 2014, FDOT opened 16km of new reversible express lanes as part of its US$1.8 billion I-595 Corridor Roadway Improvements Project. Just a few months later, on August 3rd 2014, FDOT opened twin tunnel
  • Australia: Consortium ready to abandon Melbourne’s East West Link
    March 10, 2015
    The East West Connect consortium is set to abandon Melbourne’s East West Link contract in return for a payment of between US$400 million and $535 million, according to media reports. But the Victoria state government is challenging the claim by East West Connect whose partners include Lend Lease, Acciona, Capella Capital and Bouygues. Instead, the government wants East West to payback around $153 million which the consortium allegedly received when the toll road contract was signed, reported the Herald Sun
  • GRAA focuses on winning project profile: Brisbane Airport Link, Northern Busway & Airport
    May 19, 2014
    The revolutionary AUD$4.8 billion Airport Link has delivered a landmark infrastructure project for Australia, tackling traffic congestion, enhancing the busway network and removing an infamous traffic bottleneck through an innovative and inspired design. The Airport Link in Brisbane, Australia included three separate projects – the Northern Busway (a 3km two-way dedicated busway), the Airport Roundabout Upgrade and the AirportlinkM7 (a 6.7km toll road including 5.2km of tunnel). Together, they represent the