Bangladesh’s Padma Bridge faces cost hike

The cost of the Padma Bridge Project in Bangladesh could rise by around US$173 million, according to a report by the Financial Express newspaper. A Planning Commission official said the money would be needed for compulsory purchase of nearly 2,6700 more hectares. Work started in 2014 and the project is likely to finish by the end of 2018.
September 25, 2017 Read time: 2 mins

The cost of the Padma Bridge Project in Bangladesh could rise by around US$173 million, according to a report by the Financial Express newspaper.

A Planning Commission official said the money would be needed for compulsory purchase of nearly 2,6700 more hectares. Work started in 2014 and the project is likely to finish by the end of 2018.

It will be the third cost hike for the two-level steel truss Padma Bridge across the Padma River. The bridge, nearly 6.2km long, will connect Louhajong, Munshiganj to Shariatpur and Madaripur, linking Bangladesh’s south-west region to the northern and eastern areas. The goal is to boost transportation between the underdeveloped south and the capital Dhaka along with the main port of Chittagong.

It will just over 18m wide, carrying a four-lane highway on the upper level and a single-track freight railway on a lower level.

2332 World Bank funding of around $1.2 billion was withdrawn in 2012 over allegations of corruption among 1043 Bangladeshi government officials and the procuremenet process. The project went ahead under government backed financing.

In 2014, China Major Bridge Engineering Company was chosen as construction contractor for the bridge which was designed by 1397 AECOM. The contract is a build-own-transfer deal in which China Major Bridge is investing $2 billion – around 70% of the project cost.

The UK’s 5180 Institution of Civil Engineers notes that the bridge is being built in one of the world’s most challenging environments including a high risk of earthquakes. The bridge’s piles are subject to extremely high riverbed scour and could lose substantial embedment.

To counter this, the AECOM design is the displacement-based approach for seismic resilience.

This includes seismic isolation between the superstructure girder and the pier-and-foundation system whereby principal bridge components can move relative to one another during an earthquake. This dissipates large forces.

Each pier has six steel tubular driven piles. Friction pendulum bearings are used to permit large relative displacements between the bridge superstructure and the bridge piers.

The design team led by AECOM included SMEC International, Northwest Hydraulic Consultants and ACE Consultants, with additional assistance from Aas-Jakobsenand HR Wallingford.

For more information on companies in this article

Related Content

  • Bangladesh: Cost of Padma Bridge project rises
    January 11, 2016
    The cost of building the Padma Bridge in Bangladesh will be nearly three times the US$2.61 billion estimated in 2011. Also on the rise is the cost of flood prevention work in the form of levee construction – called river training in Bangladesh. The addition of 1.3km of work at the Mawa end of the bridge means the total cost is now $1.2 billion, up from $1.1 billion. Apart from $200 from the $1 billion loan from India the project is not using any foreign financing, according to a report in the Daily S
  • World Bank cancel US$1.2bn Padma Bridge loan
    July 6, 2012
    A loan worth US$1.20billion for the Padma Multipurpose Bridge project has been cancelled by the World Bank (WB). The decision was said to have been taken as the Bank was not satisfied with the actions taken by the Bangladeshi government in regards to corruption allegations involving the bridge contract. A major engineering and construction company is alleged to have made improper payments to Bangladeshi government officials in order to secure the bridge contract. The World Bank loan, signed In April last y
  • Bangladesh bridge project for XCMG cranes
    March 7, 2018
    Six XCMG crawler cranes are working hard on the construction of the Padma Bridge in Bangladesh. This is a landmark project for Bangladesh, as the 6.15km structure will provide a new link between the south-west of the country and the northern and eastern regions. When the bridge is complete it will connect Louhajong, Munshiganj to Shariatpur and Madaripur. In addition to the main bridge section, there is an additional 3.8km approach bridge, which is also very important to the project. The Padma Bridge is
  • Cost soars for Bangladesh’s Karnaphuli River Tunnel
    April 14, 2015
    Amid concern over cost rises, Bangladesh has issued a request for expression of interest to engage a consultant for the proposed the Karnaphuli River Tunnel. The estimated cost to build the Karnaphuli Tunnel has risen by US$205 million, according to the government’s Bridge Authority. A report in the Financial Express newspaper said the original 2km tunnel proposal was prepared two years ago based on a feasibility study. According to Bridge Authority officials, the cost to build the 3.4km tunnel has ri