BAM, Morgan Sindall start UK’s €112 million Oldbury viaduct job

A joint venture of BAM, Morgan Sindall and VolkerFitzpatrick has started refurbishing the Oldbury viaduct on the UK’s M5 motorway. The €112 million project will see repairs to a 3.5km stretch between junctions 1 and 2 of the motorway – one of the UK’s busiest routes – to the west of Birmingham city. Work is being done in three phases starting with the removal of the road surface on the southbound carriageway to investigate the condition of the concrete deck.
July 31, 2017 Read time: 2 mins
M5 junctions 1 and 2 in need of repair and waterproofing

A joint venture of 7456 BAM, 2567 Morgan Sindall and 2849 VolkerFitzpatrick has started refurbishing the Oldbury viaduct on the UK’s M5 motorway.

The €112 million project will see repairs to a 3.5km stretch between junctions 1 and 2 of the motorway – one of the UK’s busiest routes – to the west of Birmingham city.

Work is being done in three phases starting with the removal of the road surface on the southbound carriageway to investigate the condition of the concrete deck.

Damaged concrete will be repaired and a new waterproofing layer added prior to resurfacing. The process will then be repeated on the northbound carriageway, said Matt Atkinson, project director for the joint venture.

Various sections of the M5 through the West Midlands are elevated – viaducts – that were made of concrete in the late 1960’s. The Oldbury viaduct carries 120,000 vehicles a day, according to 8100 Highways England, the government agency responsible for major roads in England.

“This scheme is the largest concrete repair project ever undertaken in the UK,” the agency said. “To carry out concrete repair and joint replacement works safely, we will need to scaffold under most of the 2.9km long, 30m wide viaduct. All of our scaffolding will then be encapsulated in polythene to prevent the escape of water, dust and debris.”

For more information on companies in this article

Related Content

  • UV lining is highway drainage first for UK motorway upgrade
    December 19, 2017
    Drainage specialist Lanes Group is implementing the first project to extensively line highway drainage pipes as part of a Smart Motorway initiative in the UK. Lanes has been commissioned by the Carillion Kier Joint Venture working for Highways England to install ultra-violet – UV - liners during the M6 Junction 16-19 Smart Motorway scheme between Crewe and Knutsford, in county Cheshire. Lanes said that it is the first time that roadside drainage pipes will have been extensively lined, instead of being
  • M1 motorway safety benefits from transition barrier use
    December 3, 2013
    Temporary transition solutions for roadworks areas improve safety for personnel and drivers. A new temporary transition barrier system has been put to use successfully on the M1 motorway in the UK. Initial trials on the M1 have highlighted the potential cost savings and improved safety for road construction personnel and drivers on the approach to highway maintenance works. A spokesperson for BAM, Nuttall Morgan Sindall Joint Venture on the M1, junctions 39 to 42, said that the use of Asset Safe Taper syst
  • The power of water
    July 18, 2012
    The popularity of hydrodemolition is growing worldwide and was the specified solution for work on two vital Swedish links The hydrodemolition technique, which uses high pressure water jets to remove damaged concrete from various structures, is playing a crucial role in the major restoration of the vital Central Bridge and Söderled Tunnel in the centre of Sweden's capital Stockholm. The 1,550m dual two-lane rectangular box Söderled Tunnel and connecting dual two and three-lane Central Bridge are a vital 2.6k
  • Fast resurfacing work in UK by contractor Eurovia
    May 15, 2017
    In the UK the contractor Eurovia has recently carried out a challenging resurfacing job within a tight timescale. The firm had to contend with live traffic on a busy stretch of motorway, while carrying out the work close to shared intersections. The traffic was particularly heavy also during part of the job due to a holiday period and large numbers of tourist vehicles using the stretch of motorway.