BAM, Morgan Sindall start UK’s €112 million Oldbury viaduct job

A joint venture of BAM, Morgan Sindall and VolkerFitzpatrick has started refurbishing the Oldbury viaduct on the UK’s M5 motorway. The €112 million project will see repairs to a 3.5km stretch between junctions 1 and 2 of the motorway – one of the UK’s busiest routes – to the west of Birmingham city. Work is being done in three phases starting with the removal of the road surface on the southbound carriageway to investigate the condition of the concrete deck.
July 31, 2017 Read time: 2 mins
M5 junctions 1 and 2 in need of repair and waterproofing

A joint venture of 7456 BAM, 2567 Morgan Sindall and 2849 VolkerFitzpatrick has started refurbishing the Oldbury viaduct on the UK’s M5 motorway.

The €112 million project will see repairs to a 3.5km stretch between junctions 1 and 2 of the motorway – one of the UK’s busiest routes – to the west of Birmingham city.

Work is being done in three phases starting with the removal of the road surface on the southbound carriageway to investigate the condition of the concrete deck.

Damaged concrete will be repaired and a new waterproofing layer added prior to resurfacing. The process will then be repeated on the northbound carriageway, said Matt Atkinson, project director for the joint venture.

Various sections of the M5 through the West Midlands are elevated – viaducts – that were made of concrete in the late 1960’s. The Oldbury viaduct carries 120,000 vehicles a day, according to 8100 Highways England, the government agency responsible for major roads in England.

“This scheme is the largest concrete repair project ever undertaken in the UK,” the agency said. “To carry out concrete repair and joint replacement works safely, we will need to scaffold under most of the 2.9km long, 30m wide viaduct. All of our scaffolding will then be encapsulated in polythene to prevent the escape of water, dust and debris.”

For more information on companies in this article

Related Content

  • Balfour Beatty in 10-year extension to Exeter-Bere Regis road deal
    May 8, 2015
    A Balfour Beatty joint venture with South West Highways has been awarded a €55 million 10-year extension to its contract for operations and maintenance on the 102km A30/A35 main Exeter to Bere Regis road. The contract is on behalf of Connect Roads for ultimate customer Highways England, the newly named government roads agency. The joint venture – SWHBBIS - was appointed as the operations and maintenance contractor for this stretch of the trunk road in 1996. In 2006, the joint venture was re-appointed
  • New bridge refurbishment solutions now available
    July 15, 2015
    An array of new bridge refurbishment and repair solutions are available – Mike Woof writes Around the world there are many bridges requiring repairs or refurbishment, and there is a ready market for novel solutions to upgrade existing structures. New developments offer quicker and more efficient ways to improve bridge surfaces and structural performance and add new life to ageing designs. Spancrete is broadening the availability of its novel precast building solutions worldwide by offering these to th
  • Eliminating leaks on Prague bridge
    July 17, 2012
    Stirling Lloyd's Eliminator waterproofing system, found on the decks of many of the world best known highway bridges, is being used in a €8.7 million refurbishment project on the famous 650-year-old Charles Bridge in the Czech capital Prague. Work on the tourist attraction includes repairs to the upper bridge section, replacement of the old concrete deck, installation of the new waterproofing system, replacing stones in sills where required, new drainage and repair to the structures pillars. It will repair
  • Eliminating leaks on Prague bridge
    July 17, 2012
    Stirling Lloyd's Eliminator waterproofing system, found on the decks of many of the world best known highway bridges, is being used in a €8.7 million refurbishment project on the famous 650-year-old Charles Bridge in the Czech capital Prague. Work on the tourist attraction includes repairs to the upper bridge section, replacement of the old concrete deck, installation of the new waterproofing system, replacing stones in sills where required, new drainage and repair to the structures pillars. It will repair