Balfour works nights on Scotland’s Perth Transport Futures project

The Perth Transport Futures project has reached a milestone with the placing of steel beams to support the road bridge on Scotland’s A9 dual carriageway.
July 31, 2017 Read time: 2 mins
Up and in place for steel support beams on the Perth Transport Futures project

The Perth Transport Futures project has reached a milestone with the placing of steel beams to support the road bridge on Scotland’s A9 dual carriageway.

International construction group 1146 Balfour Beatty recently completed the work over three consecutive nights to position the three 103tonne beams.

Balfour Beatty is undertaking the work on behalf of Perth and Kinross Council under the Scape National Civil Engineering and Infrastructure Framework.

On completion, the project will see the creation of a new junction on the A9 dual carriageway, as well as a new link road. This will enable access to development land to the west of the city and support growth in Scotland’s third busiest region.

Hector Macaulay, Balfour Beatty’s Scotland regional managing director, said the company has engaged more than 50 local suppliers and subcontractors. Balfour Beatty sourced all of its steel from British manufacturers, with over half originating in Scotland.

<%$Linker:

2

 

External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Perth Transport Futures Project false http://www.perthtransportfutures.co.uk/ false false%> has four phases and include development of the Cross Tay Link Road around Perth. Phase 1 has been developed by the council's roads infrastructure team and designed by consultants CH2M. It includes a grade-separated interchange between the A9 and the A85 roads as well as a bridge over the River Almond.

 

For more information on companies in this article

Related Content

  • Concern over the state of US bridges
    April 1, 2019
    Bridge condition is a serious concern in the US, according to a new report from American Road & Transportation Builders Association (ARTBA).
  • Bridge building in miniature by Cimolai
    January 6, 2017
    Bespoke equipment supplier Cimolai Technology is exhibiting a model of the equipment it supplied for a Bulgarian bridge project. Construction of the bridge entailed lifting and positioning pre-cast sections weighing up to 260tonnes. Cimolai designed, built and supplied a bespoke cantilever lifting system to sit atop the centre pillar and simultaneously hoist the blocks from barges 42m below on the river Danube. The company said its European contracting customers are increasingly winning orders further afiel
  • Bridge building in miniature by Cimolai
    April 19, 2013
    Bespoke equipment supplier Cimolai Technology is exhibiting a model of the equipment it supplied for a Bulgarian bridge project. Construction of the bridge entailed lifting and positioning pre-cast sections weighing up to 260tonnes. Cimolai designed, built and supplied a bespoke cantilever lifting system to sit atop the centre pillar and simultaneously hoist the blocks from barges 42m below on the river Danube. The company said its European contracting customers are increasingly winning orders further afiel
  • Losing your car ain’t as hard as you would think
    April 29, 2015
    Thankfully it doesn’t happen too often, but forgetting where you parked your car can be an embarrassing moment, or several days, as one man in the UK recently found. Jason Matthews, 40, ran the Manchester City Marathon on April 19 in five hours and 11 minutes and then spent an additional several hours looking for his Saab 93 Sport. He said he couldn’t recall where he had parked the vehicle. He walked back around some of the 26-mile – nearly 42km - course, before driving around in a taxi for 40 minutes an