Balfour works nights on Scotland’s Perth Transport Futures project

The Perth Transport Futures project has reached a milestone with the placing of steel beams to support the road bridge on Scotland’s A9 dual carriageway.
July 31, 2017 Read time: 2 mins
Up and in place for steel support beams on the Perth Transport Futures project

The Perth Transport Futures project has reached a milestone with the placing of steel beams to support the road bridge on Scotland’s A9 dual carriageway.

International construction group 1146 Balfour Beatty recently completed the work over three consecutive nights to position the three 103tonne beams.

Balfour Beatty is undertaking the work on behalf of Perth and Kinross Council under the Scape National Civil Engineering and Infrastructure Framework.

On completion, the project will see the creation of a new junction on the A9 dual carriageway, as well as a new link road. This will enable access to development land to the west of the city and support growth in Scotland’s third busiest region.

Hector Macaulay, Balfour Beatty’s Scotland regional managing director, said the company has engaged more than 50 local suppliers and subcontractors. Balfour Beatty sourced all of its steel from British manufacturers, with over half originating in Scotland.

<%$Linker:

2

 

External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal Perth Transport Futures Project false http://www.perthtransportfutures.co.uk/ false false%> has four phases and include development of the Cross Tay Link Road around Perth. Phase 1 has been developed by the council's roads infrastructure team and designed by consultants CH2M. It includes a grade-separated interchange between the A9 and the A85 roads as well as a bridge over the River Almond.

 

For more information on companies in this article

Related Content

  • Record breaking ABM bridge beams installed near Raith, Scotland
    September 30, 2016
    One of the largest mobile cranes in the UK, a 1,500tonne capacity unit, recently positioned nine 90tonne 42m pre-stressed bridge beams by ABM Precast Solutions. The massive W-beams were hoisted into place at Junction 5, the Raith Interchange, on Scotland’s M74 motorway – part of the M8-M73-M74 motorway improvements project.
  • VIDEO: Switzerland’s Astra Bridge concept to be tendered
    May 23, 2019
    Switzerland will soon tender for companies to build and supply a mobile system for physically shifting traffic away from road crews – the Astra Bridge concept. The federal highways agency - FEDRO - will be asking general contractors to submit bids starting this summer for the Astra Bridge system, according to the agency. The system, to be used on motorways, includes ramp sections at each end of what amounts to a train of elevated connected road sections. Vehicles run onto the top of the train which is
  • Dubuis’s cutting-edge crimping
    January 6, 2017
    France-based Dubuis is unveiling its new Neoelec in line BPL36 crimping tool at Intermat 2012.The company, bought by Stanley Black&Decker in 2006, has designed a crimper with 35kN force and 8mm stroke, weighing 2.1kg and capable of 4-185mm² hexagonal crimping.
  • Dubuis’s cutting-edge crimping
    February 6, 2012
    France-based Dubuis is unveiling its new Neoelec in line BPL36 crimping tool at Intermat 2012.The company, bought by Stanley Black&Decker in 2006, has designed a crimper with 35kN force and 8mm stroke, weighing 2.1kg and capable of 4-185mm² hexagonal crimping.