Balfour Beatty demolishes Scottish M8 bridge to create junction

Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
July 11, 2013 Read time: 2 mins
1146 Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland.

The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8. Materials removed during the demolition are being recycled, including the concrete which will be crushed and reused in the construction of the roads.

A recently completed 50m long, single span bridge provides a new access to the farm and forms part of the new grade separated junction that will provide the main access route to Heartlands, a US$968.15 million (£650mn) business, retail, residential and leisure destination, providing around 4,000 new jobs. Funded by 6192 The Royal Bank of Scotland, this will be the first entirely privately funded motorway junction in Scotland.

M8 Junction 4a is set to open in September 2013.

For more information on companies in this article

Related Content

  • THIS is a Paving Project– The I-15 CORE
    December 20, 2012
    Provo, Utah – The scope of the I-15 Corridor Expansion Project (I-15 CORE) in the state of Utah is nearly unprecedented because of the size of the project and the short completion deadline. Twenty-four miles (38.6 km) of removal and replacement of Interstate 15 between Lehi and Spanish Fork, widening the number of traveling lanes by two, for up to six lanes in each direction in 35 months. The new 364 lane miles (586 km) of concrete roadway will be slipformed 12 or 12.5 inches (305 or 318 mm) thick for a tot
  • Gubler gets down with a Kemroc EK 100 chain cutter
    May 1, 2018
    Boulders are usually removed from site by breaking them with a hammer and then using a backhoe to extract the rubble: a time-consuming process. Swiss construction company Gubler, however, used a Kemroc EK 100 chain cutter to cut down on processing time as well as wear and tear on company equipment. With an EK 100 chain cutter mounted on their 22tonne excavator, Gubler excavated the foundations, footings and service trenches in the typical local molasse rock. The project is a large residential complex and
  • Kuwait’s Sheikh Jaber al-Ahmad Al-Sabah Causeway opens
    August 27, 2019
    World Highways revisits the world’s fourth longest sea bridge - four years to construct and which has slashed travel time between Kuwait’s largest island and the capital city
  • Ageing Liberty Tunnels in US refurbished with hydrodemolition
    May 13, 2015
    Hydrodemolition surface preparation keeps Liberty Tunnel rehabilitation project on schedule in Pittsburgh. The Pennsylvania state Department of Transportation selected hydrodemolition surface preparation for the US$18.8 million rehabilitation of Pittsburgh’s Liberty Tunnels. Time was of the essence to complete the project on deadline without penalties and hydrodemolition was selected as it offered a fast and cost-effective method to prepare the tunnel walls for a new, shotcrete surface. This methods off