Balfour Beatty demolishes Scottish M8 bridge to create junction

Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
July 11, 2013 Read time: 2 mins
1146 Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland.

The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8. Materials removed during the demolition are being recycled, including the concrete which will be crushed and reused in the construction of the roads.

A recently completed 50m long, single span bridge provides a new access to the farm and forms part of the new grade separated junction that will provide the main access route to Heartlands, a US$968.15 million (£650mn) business, retail, residential and leisure destination, providing around 4,000 new jobs. Funded by 6192 The Royal Bank of Scotland, this will be the first entirely privately funded motorway junction in Scotland.

M8 Junction 4a is set to open in September 2013.

For more information on companies in this article

Related Content

  • IRF Geneva to support Qatar on its recycling strategy
    June 12, 2018
    IRF Geneva was at the Pavement Preservation and Recycling Summit (PPRS) 2018 in Nice The Pavement Preservation and Recycling Summit (PPRS) 2018 in Nice (26th – 28th March 2018) set the scene for the signature of an important Memorandum of Understanding (MoU) between between Ashghal, the Qatari Public Works Authority and the International Road Federation (Geneva). Ashghal’s participation in the summit was part of its endeavour to open opportunities for cooperation and investment in the road sector and recy
  • VIDEO of specialist contractor’s successful bridge demolition in Canada
    May 12, 2015
    Specialist contractor Priestly Demolition recently carried out a successful project in Ontario, Canada. The firm used its specialist skills to remove The Fountain Road Overpass, crossing Highway 401. A fleet of excavators equipped with demolition tools, including breakers and cutting equipment, was brought into to carry out the work using an overnight closure of the highway. Other machines including wheeled loaders and backhoe loaders were used to remove the broken out materials and to carry out other general duties.
  • Amey awarded Scottish strategic highways contract
    June 18, 2014
    Transport Scotland has awarded Amey a six-year contract to maintain and improve the motorways and trunk roads in South East Scotland. The commission, which is valued at over €115.3 million (£90 million), is subject to up to two one-year extensions and will see Amey deliver engineering design and operational delivery services for more than 885km (550 miles) of road. Under the Scottish Trunk Roads Unit South East (STRU SE) contract Amey will be responsible for managing and maintaining routes through Central
  • Long reach equipment simplifies demolition
    February 14, 2012
    Demolition is a highly specialised business, as the machinery required to carry out the work on high-rise demolition contracts can be very site specific. Today's high reach demolition rig is no longer simply a tracked excavator with a long boom, indeed some machines cannot be used as excavators at all. Likewise a machine that is dedicated to carrying a 2.5 or 3tonne shear or hammer will need to be built to take the stresses and strains of demolition life.