Balfour Beatty demolishes Scottish M8 bridge to create junction

Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
July 11, 2013 Read time: 2 mins
1146 Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland.

The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8. Materials removed during the demolition are being recycled, including the concrete which will be crushed and reused in the construction of the roads.

A recently completed 50m long, single span bridge provides a new access to the farm and forms part of the new grade separated junction that will provide the main access route to Heartlands, a US$968.15 million (£650mn) business, retail, residential and leisure destination, providing around 4,000 new jobs. Funded by 6192 The Royal Bank of Scotland, this will be the first entirely privately funded motorway junction in Scotland.

M8 Junction 4a is set to open in September 2013.

For more information on companies in this article

Related Content

  • Volvo CE bridging the gap for new Indian transport links
    December 11, 2013
    The old Pakuria Bridge in Jharkhand, India, ran over a dry riverbed and railway line situated 20km from Calcutta. Now obsolete, the bridge has been brought to the ground in 60 days using Volvo construction equipment West Bengal in eastern India is the nation’s fourth most populous region, boasting more people than the whole of Germany. The state is bordered by Nepal, Bhutan, Bangladesh, and five other states of India with more than 91 million inhabitants spread over 34,267m².
  • Balfour Beatty sells its Infrastructure Partners business
    July 6, 2016
    UK-based contractor Balfour Beatty has exited from Balfour Beatty Infrastructure Partners (BBIP) which has rebranded as Basalt Infrastructure Partners. Basalt is now an independent fund management business that is 100% owned by the partners of the firm - Rob Gregor, Steven Lowry and Jeff Neil. “Basalt’s investment strategy will continue to focus on mid-market infrastructure assets in the energy, transport and utilities sectors in Western Europe and North America,” according to a Basalt statement.
  • Gilpin Demolition gets tough with A38 overpass in Devon, UK
    December 19, 2014
    There was no need for a day shift when Devon-based Gilpin Demolition took on a timely challenge - demolish an overpass bridge in 15 hours and reopen the A38 by the following morning.

    The 40m long and 8m high single carriageway bridge, made of 1,400 tonnes of steel and concrete, was an overpass near Rattery. By 8PM the A38 below had been closed and the bridge carriageways were barricaded, ready for Gilpin’s first crew to arrive and lay down 400tonnes of stone road protection on the A38.
  • Skanska Balfour Beatty install first M25 superspan gantry during motorway upgrade
    August 22, 2013
    The first superspan gantry has been installed over the M25 motorway near London, England. The structure near Junction 24 (Potters Bar, Hertfordshire) is part of the €219.92 million (£188 million) Managed Motorway scheme to upgrade the motorway between junctions 23 and 27. Weighing 36 tonnes and measuring 40m across, it is the first of five superspan gantries which will be installed during the project being carried out by Skanska Balfour Beatty, on behalf of the Highways Agency. The gantries will