Balfour Beatty demolishes Scottish M8 bridge to create junction

Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
July 11, 2013 Read time: 2 mins
1146 Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland.

The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8. Materials removed during the demolition are being recycled, including the concrete which will be crushed and reused in the construction of the roads.

A recently completed 50m long, single span bridge provides a new access to the farm and forms part of the new grade separated junction that will provide the main access route to Heartlands, a US$968.15 million (£650mn) business, retail, residential and leisure destination, providing around 4,000 new jobs. Funded by 6192 The Royal Bank of Scotland, this will be the first entirely privately funded motorway junction in Scotland.

M8 Junction 4a is set to open in September 2013.

For more information on companies in this article

Related Content

  • Noise and crash barriers, high strength protection
    April 4, 2012
    HOLGATE INFRASTRUCTURE & Motorway Services has supplied vehicle restraint systems and noise attenuation panels to major highway upgrade projects in the UK. The firm has installed Vetex crash barriers and high performance aluminium noise barriers on the M50 Linton upgrade for Alu Griffiths and Amey. Holgate has also supplied the noise barrier package on the M74 Glasgow motorway extension.
  • £8 billion UK tunnel project to go ahead
    January 30, 2025
    The £8 billion UK Lower Thames Crossing tunnel project is to go ahead.
  • Fast-track demolition
    June 18, 2012
    Heavy hydraulic breakers and a six-tonne combi cutter from Atlas Copco is said to have played a key part in enabling Armac to complete the demolition of the former Catthorpe motorway interchange viaduct within the 36 hours prescribed by the Highways Agency. Bridge dismantling experts Armac deployed no fewer than 10 Atlas Copco hydraulic breakers – six HB 4200, two HB 5800 and two HB 7000 units – to dismantle the 5,500tonne, 85metre long structure. In addition, Armac also used an Atlas Copco CC 6000 hydrauli