Balfour Beatty demolishes M8 bridge to create junction

A huge array of construction machinery from leading international equipment manufacturers was deployed by Balfour Beatty recently to demolish a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The Cowhill Bridge demolition was a major milestone for Ecosse Regeneration in the construction of Junction 4a. Ten excavators equipped with hydraulic breakers and munching attachments were used to remove
August 8, 2013 Read time: 2 mins
A huge array of construction machinery from leading international equipment manufacturers was deployed by 1146 Balfour Beatty recently to demolish a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland.

The Cowhill Bridge demolition was a major milestone for Ecosse Regeneration in the construction of Junction 4a. Ten excavators equipped with hydraulic breakers and munching attachments were used to remove the four-span composite construction bridge during a 10-hour night time closure of the M8. Materials removed during the demolition are being recycled.

A recently completed 50m long, single span bridge provides a new access to the farm and forms part of the new grade separated junction that will provide the main access route to Heartlands, a US$968.15 million (£650mn) business, retail, residential and leisure destination.

M8 Junction 4a is set to open in September 2013.

Click here to watch the Balfour Beatty demolition team in action.

For more information on companies in this article

Related Content

  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Bridge improvements reduce flood threat
    February 16, 2012
    The impact of the new Eden Bridge over the River Eden on its flood plain is a key issue to the construction of the Carlisle Northern Development Route (CNDR).
  • Bridge improvements reduce flood threat
    April 4, 2012
    The impact of the new Eden Bridge over the River Eden on its flood plain is a key issue to the construction of the Carlisle Northern Development Route (CNDR).