Balfour Beatty demolishes M8 bridge to create junction

A huge array of construction machinery from leading international equipment manufacturers was deployed by Balfour Beatty recently to demolish a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The Cowhill Bridge demolition was a major milestone for Ecosse Regeneration in the construction of Junction 4a. Ten excavators equipped with hydraulic breakers and munching attachments were used to remove
August 8, 2013 Read time: 2 mins
A huge array of construction machinery from leading international equipment manufacturers was deployed by 1146 Balfour Beatty recently to demolish a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland.

The Cowhill Bridge demolition was a major milestone for Ecosse Regeneration in the construction of Junction 4a. Ten excavators equipped with hydraulic breakers and munching attachments were used to remove the four-span composite construction bridge during a 10-hour night time closure of the M8. Materials removed during the demolition are being recycled.

A recently completed 50m long, single span bridge provides a new access to the farm and forms part of the new grade separated junction that will provide the main access route to Heartlands, a US$968.15 million (£650mn) business, retail, residential and leisure destination.

M8 Junction 4a is set to open in September 2013.

Click here to watch the Balfour Beatty demolition team in action.

For more information on companies in this article

Related Content

  • Balfour Beatty demolishes Scottish M8 bridge to create junction
    July 11, 2013
    Balfour Beatty has demolished a farm access bridge over the M8 motorway between junctions 4 and 5 to enable the completion of slip roads for the new Heartlands junction in West Lothian, Scotland. The demolition of Cowhill Bridge is a major milestone for Ecosse Regeneration in the construction of Junction 4a. Using ten excavators equipped with hydraulic breakers and munching attachments, the four span composite construction bridge was successfully removed during a recent 10-hour night time closure of the M8.
  • Busy UK motorway junction demolished in tight time frame – Mark Anthony reports
    October 18, 2012
    Military-style planning and overwhelming demolition firepower ensured that Armac Group avoided financial penalties and the wrath of drivers on one of the UK’s busiest motorway intersections. Demolition & Dismantling reports. 6 January is traditionally known for the visit of the three wise men to Bethlehem. However, on 6 January 2012, three wise demolition engineers from Armac Group was tasked with dismantling the monumental structure known as Catthorpe Viaduct: the main overbridge of the M6/M1/A14 interc
  • Balfour works nights on Scotland’s Perth Transport Futures project
    July 31, 2017
    The Perth Transport Futures project has reached a milestone with the placing of steel beams to support the road bridge on Scotland’s A9 dual carriageway.
  • Balfour Beatty lifts bridge into place over UK’s M54
    May 14, 2014
    In the UK, Balfour Beatty has lifted a new bridge into place over the M54 motorway as part of a €14.56 million (£12 million) project to connect a new high-tech business park to the road network and to provide access for the new Jaguar Land Rover plant. The bridge, which will serve the i54 business park in South Staffordshire, was delivered for Staffordshire County Council, Wolverhampton City Council and South Staffordshire Council, as part of the Midlands Highways Alliance framework.