Balfour and Vinci slide bridge over the M42

Workers slid the concrete shell of a 12,600-tonne bridge a record 165m to position it across the M42 motorway in the northern English county of Warwickshire.
By David Arminas January 6, 2023 Read time: 2 mins
Over the past six months, the 86m-long concrete structure was built on land next to the motorway and then slid across the road in a two-day operation (image courtesy of High Speed Two Ltd)

The joint venture of Balfour Beatty Vinci reports that it has completed over the M42 in England what it calls “the world-first box bridge slide”.

Workers slid the concrete shell of 12,600-tonne bridge a record 165m to position it across the M42 motorway in the county of Warwickshire. Around 450 people worked on the operation during the Christmas week, a quiet time on the roads. A section of the motorway section was closed for the 10-day operation.

The slide operation itself took only 48 hours at a speed of 4m per hour, explained Sasan Ghavami, Balfour Beatty Vinci's’s construction director for the project. “We’ve used innovative construction techniques and worked tirelessly throughout the Christmas period to move this 12,600-tonne bridge over the M42 – all done with the aim of keeping [traffic] disruption to an absolute minimum.”

Over the past six months, the giant 86m-long structure was constructed on land next to the motorway. It was developed by a design joint venture of Mott MacDonald and SYSTRA, working on behalf of Balfour Beatty Vinci. It has a base, three walls and top slab.

The sliding mechanism, designed by specialist civil and structural engineering company Freyssinet, allowed the box to be pushed into place over the motorway on a guiding raft over a distance of 165m. This construction method allowed it to be shifted into place in one movement, resulting in only two one-week closures of the motorway over a 12-month period, dramatically reducing disruption for road users.

On completion, the whole structure will total around 190m in length and will carry HS2 – High Speed 2 rail line - over the motorway.

For more information on companies in this article

Related Content

  • The Preston Western Distributor
    September 7, 2023
    Costain, as main contractor for the Preston Western Distributor project, was involved from the earliest stages, thanks to the UK’s Early Contractor Involvement approach. The project was delivered on time and on budget to the benefit of the local environment, local businesses and the region’s workforce. David Arminas reports*
  • Act FAST when it comes to bridge maintenance, argues Cliff Weston
    February 27, 2017
    Deck waterproofing remains critical to a bridge’s structural integrity for its design life, explains Cliff Weston, director of Stirling Lloyd To properly maintain deck waterproofing there must be a willingness to look at solutions based on whole-life costing rather than just short-term initial costs. There are lessons to be learned from examples of prematurely failed infrastructure due to a focus on initial short-term costs.
  • New design consultant partnership
    July 7, 2017
    A new strategic design consultant partnership is now being formed between infrastructure group Balfour Beatty, Atkins, Mott MacDonald and WSP. The collaborative UK Strategic Design Consultant Partnership is said to offer a new level of openness, collaboration and innovation for the construction industry.
  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)