Balfour and Vinci slide bridge over the M42

Workers slid the concrete shell of a 12,600-tonne bridge a record 165m to position it across the M42 motorway in the northern English county of Warwickshire.
By David Arminas January 6, 2023 Read time: 2 mins
Over the past six months, the 86m-long concrete structure was built on land next to the motorway and then slid across the road in a two-day operation (image courtesy of High Speed Two Ltd)

The joint venture of Balfour Beatty Vinci reports that it has completed over the M42 in England what it calls “the world-first box bridge slide”.

Workers slid the concrete shell of 12,600-tonne bridge a record 165m to position it across the M42 motorway in the county of Warwickshire. Around 450 people worked on the operation during the Christmas week, a quiet time on the roads. A section of the motorway section was closed for the 10-day operation.

The slide operation itself took only 48 hours at a speed of 4m per hour, explained Sasan Ghavami, Balfour Beatty Vinci's’s construction director for the project. “We’ve used innovative construction techniques and worked tirelessly throughout the Christmas period to move this 12,600-tonne bridge over the M42 – all done with the aim of keeping [traffic] disruption to an absolute minimum.”

Over the past six months, the giant 86m-long structure was constructed on land next to the motorway. It was developed by a design joint venture of Mott MacDonald and SYSTRA, working on behalf of Balfour Beatty Vinci. It has a base, three walls and top slab.

The sliding mechanism, designed by specialist civil and structural engineering company Freyssinet, allowed the box to be pushed into place over the motorway on a guiding raft over a distance of 165m. This construction method allowed it to be shifted into place in one movement, resulting in only two one-week closures of the motorway over a 12-month period, dramatically reducing disruption for road users.

On completion, the whole structure will total around 190m in length and will carry HS2 – High Speed 2 rail line - over the motorway.

For more information on companies in this article

Related Content

  • Bentley Systems award winners announced
    December 3, 2021
    Bentley Systems has announced the award winners for 2021.
  • Busy UK motorway junction demolished in tight time frame – Mark Anthony reports
    October 18, 2012
    Military-style planning and overwhelming demolition firepower ensured that Armac Group avoided financial penalties and the wrath of drivers on one of the UK’s busiest motorway intersections. Demolition & Dismantling reports. 6 January is traditionally known for the visit of the three wise men to Bethlehem. However, on 6 January 2012, three wise demolition engineers from Armac Group was tasked with dismantling the monumental structure known as Catthorpe Viaduct: the main overbridge of the M6/M1/A14 interc
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Final Lower Thames Crossing approval awaited
    November 7, 2022
    Work in the UK includes a twin bore tunnel under the River Thames east of London.