Balfour and Vinci slide bridge over the M42

Workers slid the concrete shell of a 12,600-tonne bridge a record 165m to position it across the M42 motorway in the northern English county of Warwickshire.
By David Arminas January 6, 2023 Read time: 2 mins
Over the past six months, the 86m-long concrete structure was built on land next to the motorway and then slid across the road in a two-day operation (image courtesy of High Speed Two Ltd)

The joint venture of Balfour Beatty Vinci reports that it has completed over the M42 in England what it calls “the world-first box bridge slide”.

Workers slid the concrete shell of 12,600-tonne bridge a record 165m to position it across the M42 motorway in the county of Warwickshire. Around 450 people worked on the operation during the Christmas week, a quiet time on the roads. A section of the motorway section was closed for the 10-day operation.

The slide operation itself took only 48 hours at a speed of 4m per hour, explained Sasan Ghavami, Balfour Beatty Vinci's’s construction director for the project. “We’ve used innovative construction techniques and worked tirelessly throughout the Christmas period to move this 12,600-tonne bridge over the M42 – all done with the aim of keeping [traffic] disruption to an absolute minimum.”

Over the past six months, the giant 86m-long structure was constructed on land next to the motorway. It was developed by a design joint venture of Mott MacDonald and SYSTRA, working on behalf of Balfour Beatty Vinci. It has a base, three walls and top slab.

The sliding mechanism, designed by specialist civil and structural engineering company Freyssinet, allowed the box to be pushed into place over the motorway on a guiding raft over a distance of 165m. This construction method allowed it to be shifted into place in one movement, resulting in only two one-week closures of the motorway over a 12-month period, dramatically reducing disruption for road users.

On completion, the whole structure will total around 190m in length and will carry HS2 – High Speed 2 rail line - over the motorway.

For more information on companies in this article

Related Content

  • Sarens completes Nantes area A11 bridge lift
    December 27, 2023
    In France, Sarens used four Kamag SPMTs – self-propelled modular transporters – to move a bridge deck 70m and place it over the A11 at the autoroute’s Portes de Gesvres interchange.
  • Peri cantilever for Terfener Bridge
    May 17, 2021
    The Terfener Innbrücke reconstruction in the Inntal valley started in 2018 and is currently one of largest bridge construction projects in western Austria. In addition to providing planning services and onsite support, Peri has used its VBC Balanced Cantilever Carriage for the first time in Central Europe.
  • Brisbane's highway of distinction
    August 2, 2012
    A massive AU$2 billion update of the Gateway Motorway in Queensland is underway to improve an infrastructure stretched by population boom. Report and photographs by Adrian Greeman Just 20 years after the Australian city of Brisbane built its Gateway Motorway with a high slim signature bridge dominating the river skyline, the road is being completely revamped. Some 12km of urban route on the south of the Brisbane River is being expanded to take much increased traffic levels; the north is getting a completely
  • VIDEO: Balfour starts M3 bridge upgrade in UK following demolition
    November 23, 2016
    Balfour Beatty has started bridge work over the M3 motorway as part of a €205 million upgrade on highway connecting London to south coast ports. Balfour recently demolished the Woodlands Lane Bridge between junctions 2 and 3 near Windlesham on the M3 which runs from the capital to Southampton and Portsmouth. A new bridge is being constructed Balfour Beatty is working for the agency Highways England to reduce congestion this section of the M3 that handles more than 130,000 vehicle journeys every day.