Australian project, costs spiral

Costs are spiralling for a major Australian project.
By MJ Woof October 5, 2020 Read time: 1 min
Melbourne’s West Gate project looks set to be hit by further cost increases and delays – image © courtesy of Worakit Sirijinda, Dreamstime.com
There is serious concern in Australia over the spiraling costs of a major transport project in Melbourne, Victoria. The West Gate Tunnel project now looks likely to cost an additional US$2.12 billion (A$3 billion). This will bring the final pricetag to $4.73 billion (A$6.7 billion).

However, the spike in the cost has been caused by unforeseen circumstances, namely, the discovery of contaminated soil and problems with moving utilities. The volume of the contaminated soil is such that it cannot be moved to existing landfill areas, further increasing the problems and costs.

The project has already been hit by other delays and issues that have put up its pricetag, with a growing awareness of further problems to come. The project now looks likely to take a further 10 months to complete, with tunneling work having already been pushed back.

Another problem is the legal wrangle between Transurban and construction firms working on the project, John Holland and CPB Contractors.

For more information on companies in this article

Related Content

  • CPB Contractors closes deal for Melbourne’s West Gate Tunnel
    December 13, 2017
    CPB Contractors has achieved contractual close on Melbourne’s planned 5km West Gate Tunnel, originally called the Western Distributor. The road will link the West Gate Freeway at Yarraville, a suburb of Melbourne, with the tolled CityLink road network at Docklands via a tunnel beneath Yarraville.
  • South Australia road corridor plan
    February 24, 2022
    South Australia has plans for a major road corridor project.
  • West Gate Tunnel delays
    May 13, 2020
    Australia’s West Gate Tunnel project will be delayed
  • New Australia road tunnel project planned
    April 12, 2017
    A new road tunnel project is planned for the city of Melbourne in Australia. Construction is set to commence in 2018 and will take until 2022 to complete. The work will be carried out by a joint venture comprising CPB Contractors, the Australian subsidiary of German contractor Hochtief, and engineering firm John Holland. The new West Gate Road Tunnel project will help cut congestion in the city at peak periods. In addition to the tunnel construction the project also includes widening the existing West Gate