Astaldi begins drilling tunnels on Poland’s S7 dual carriageway

Italian contractor Astaldi has begun drilling two parallel tunnels as part of its S7 dual carriageway project in Poland. Each tunnel, between Naprawa and Skomielna Biala and under the Lubon Maly massif, will each be just over 2km long. Astaldi, based in Rome, won the three-year S7 dual carriageway project worth around €225 million in 2016 Work includes 38 bridges and viaducts and three motorway services. There will also be 25km of access roads and two junctions. The north-south S7, when complete
March 14, 2017 Read time: 2 mins
Italian contractor 1324 Astaldi has begun drilling two parallel tunnels as part of its S7 dual carriageway project in Poland.

Each tunnel, between Naprawa and Skomielna Biala and under the Lubon Maly massif, will each be just over 2km long.

Astaldi, based in Rome, won the three-year S7 dual carriageway project worth around €225 million in 2016

Work includes 38 bridges and viaducts and three motorway services. There will also be 25km of access roads and two junctions.

The north-south S7, when completed, will run 720km from Gdańsk on the Baltic coast through Elbląg, Warsaw, Radom, Kielce and Kraków to Rabka near Poland’s southern border with Slovakia. The vast majority of construction will be upgrading National Road 7 (DK 7).

The S7 is part of European route E77, in turn part of the inter-European road system, starting in north-eastern Russia and running 1,690km through the Baltic Sea states, into Poland and connecting with central Europe.

Astaldi’s highways division has been particularly active in Turkey – the Mount Bolu Tunnel, the Izmit Bay Bridge and, in Istanbul, the Third Bosphorus Bridge.

In 2015, Italian firm Salini Impregilo started construction of a 21.5km stretch of the S7 between the Jedrzejow and Checiny junctions under a deal worth nearly €144.67 million. Completion is set for the third quarter of of this year. Meanwhile, a consortium headed by Budimex won a contract worth nearly €318.28 million for the construction of a 9.7km section of the S7 between Ostroda Polnoc and Ostroda Poludnie.

In 2014, a Strabag consortium, picked up a €127.93 million contract for a 4.5km section of the S7 dual carriageway near Krakow, including construction of a bridge over the Vistula River.

For more information on companies in this article

Related Content

  • Ulma in Poland’s S7 tunnel
    October 22, 2020
    Construction of Poland’s longest road tunnel is progressing with an MK Formwork Carriage system from Spanish manufacturer Ulma.
  • Strabag to build 24km section of Poland’s S6 for €83 million
    November 2, 2015
    Publically listed Strabag has won the design and build contract to build a 24km section of Poland’s S6 for €83 million. The S6 expressway links the largest cities in northern Poland, Szczecin and Gdańsk. The publicly listed construction group Strabag will design and build the section between Goleniów and Koszalin for about €83 million. Construction of the 24 km dual carriageway asphalt road with two lanes of traffic in each direction will start this month with a scheduled finish of June 2019. The cont
  • Delay for Tvrdosin-Nizna R3 section in Slovakia
    June 22, 2023
    The NDS agency has not reported by how much the contracted cost of €62 million will rise.
  • Strabag closes in on Poland’s S8 Marki-Kobylka contract
    August 19, 2019
    Strabag has nudged into the lead for Poland’s retender of the dual lane S8 section between the Marki and Kobylka junctions, previously held by Salini-Impreglio. Five offers were on the table for the deal with Strabag offering €38 million, well above the €32 million that was budgeted for by GDDKiA, Poland’s road authority. Other bids came from a consortium headed by Warszawskie Przedsiebiorstwo Mostowe Mosty at nearly €40 million, a PORR and Unibep consortium offere at almost €59 million, a bid by I