Work on St Petersburg bridge project

Contractor ICA Construction used two Aquajet robotic hydrodemolition machines at the top of a 120m-high bridge pylon located in the city of St Petersburg. The two Aquajet robotic water cutters were used to remove surplus concrete from around the inner steel structure of the bridge pylon. This link spans the River Neva and forms part of the Western High-Speed Diameter (WHSD) route in St Petersburg. The WHSD is a highly important route for the region and will provide a key connection between the Scandinavi
June 20, 2016 Read time: 4 mins
Using the Aquajet unit was safer as it reduced the personnel required at the top of the tower
Special equipment has been used to remove  concrete from the top of a bridge pylon

Contractor 2765 ICA Construction used two 2784 Aquajet robotic hydrodemolition machines at the top of a 120m-high bridge pylon located in the city of St Petersburg. The two Aquajet robotic water cutters were used to remove surplus concrete from around the inner steel structure of the bridge pylon. This link spans the River Neva and forms part of the Western High-Speed Diameter (WHSD) route in St Petersburg.

The WHSD is a highly important route for the region and will provide a key connection between the Scandinavian Peninsula, Continental Europe, Central Russia, and the Baltic States.

Turkish-Italian company ICA Construction is building an 11.57km section of the highway under a US$1.6 billion contract over a four-year construction schedule. This programme of works also includes building three major high-level bridges, together with low-level viaducts and smaller overbridges.

One of the crossings is the Petrovsky Fairway Bridge, a 560m cable-stayed structure that spans the River Neva and links two islands. The structure has been designed to cut the journey time from over one hour to between 10 and 15 minutes.

The Petrovsky Fairway Bridge is being built with two needle-shaped towers, each 120m-high. The deck is being supported by cables arranged in four planes. The cables supporting the deck units closest to the tower will be connected to the top of the tower, with those towards the mid span connected at a lower level. The length of the central span is 240m, and the bridge under-clearance is 25m.

On the northern pier ICA brought in the two Aquajet hydrodemolition robots to cut away surplus concrete from near the top of the pylon. The robot machines were rented by Termite, a hydrodemolition specialist that is a sister company to DUS, distributor for Sweden’s Aquajet Systems AS in Finland and Russia. The height of the concrete to be removed was 10m, so Termite assembled the Aqua Spine unit to the same length. The firm assembled the complete system on the ground, reducing the set up time.

The 10m-high Aqua Spine mast was lifted in place and bolted onto each side of the pylon. An Aqua Cutter 410A was used as the Power Control Unit to control the Aqua spine. ICA wanted to remove the concrete without causing any damage to the inner steel structure, and needed to save the vertical rebar to spend less time on recasting. Termite provided the two water cutters to ICA, together with operators and service backup, on a rental basis.

The diamter of the inner steel structure of the pylon varies between 3.5m and 4.4m. The wider sides of the pylon are covered by 55cm of concrete, while the narrow sides have a variable thickness of between 50cm and 75cm.

The concrete that had to be removed was at a height of 84.5-94.5m, and the full thickness that had to be removed was about 77m³. To carry out the work Termite placed the power pack at the bottom of the pylon and used a 120m long high-pressure hose to access the working area. The hose was fed upwards inside the pylon and then through a vent hole to the outside.

The water source was the Finnish Gulf and the firm used three-level filtration to prepare water for the plunger pump, the used water was fed back into the sea. A caisson wall filled with sand and crushed stone surrounds the pylon. This acted as a filtration and settling tank, so the water that was pumped back into the Gulf was almost entirely clean.

The advantages of this method for ICA, along with the clean cutting of the concrete, was that there was no need to have a large gang of jackhammer operators working high up on the pylon or any need to build any platforms or scaffolding.

For more information on companies in this article

Related Content

  • Quang Ninh agrees to SE's new draft for Bach Dang Bridge in Vietnam
    October 18, 2012
    Vietnam's Quang Ninh province has backed a new design proposed by Japanese developer SE Group for the 4.3km Bach Dang Bridge. The new design will change the original prestressed concrete bridge design to a steel cable-stayed bridge. The modification will lower the girder height, reduce the bridge length and alter the main span length. The altered draft is awaiting final approval from the authorities. SE Group has also requested to cut the expenses for the project to US $ 386 million from $ 483 million. The
  • Volvo machines help construct new Norwegian tunnels
    January 12, 2015
    Close to Larvik in Norway’s Vestfold County and around 80km south of Drammen, two tunnels are currently under construction as part of a state-funded infrastructure development programme. The project, which began earlier this year, comprises 7km of four lane highway – part of the E18 major route – linking the towns of Bommestad and Sky. This includes the new Larvik and Matineå tunnels, which will span 2.8 and 1.3km respectively. Worth €187 million, this project was awarded to Skanska Norway, the second la
  • CIFA celebrates with its K40H truck mounted boom pump
    February 28, 2018
    CIFA is celebrating its 90th year with a focus on the Francophone market, including Africa. A major part of celebrations will the official introduction into the French market of the K40H truck-mounted concrete boom pump. It is the largest of its type on three axels, according the company. The unit has as standard a five-section RZ folding system placing boom. The 4th and 5th boom sections are made of light and resistant CIFA Carbotech composite material. The other three sections are high-strength steel.
  • New concrete pumps from Liebherr
    June 9, 2022
    Liebherr Concrete Technology is now offering the THP 80-LP truck mounted concrete city pump for the North American market. The THP 80-LP is the smallest in Liebherr’s truck mounted pump product range.