Skip to main content

Ulma in Poland’s S7 tunnel

Construction of Poland’s longest road tunnel is progressing with an MK Formwork Carriage system from Spanish manufacturer Ulma.
October 22, 2020 Read time: 2 mins
After pouring each 6.25m section, the carriage was easily advanced with a hydraulic system (photo courtesy Ulma)

The S7 Expressway crosses Poland from Lubien´ to Rabka Zdrój, north to south, passing through the Voividato Malopolskie region. Three sections are under construction.

One of these sections goes through Lubon´ Maly mountain, for which a tunnel with two separate tubes is being built - a total length of over 4km. This phase has proven to be the most time-consuming and costly of the entire Expressway project. There are two independent tubes, approximately 2km each, designed for traffic to flow in a single direction.

The tunnel will feature two emergency passageways between the tubes and a ventilation room, as well as technical and service installations. In order to build it, 1,922m have been perforated for the left-hand tunnel and 1,919m for the right.  

Excavation began on the north side of the right-hand tube in March of 2017. Completion of the entire tunnel is expected by mid-2021.

Ulma’s Engineering Team designed an MK Formwork Carriage 15.5m wide and 10.7m long to pour the mine tunnel. With a single unit made from standard MK pieces, the carriage was adapted effortlessly to the tunnel’s complex geometry.

For the roof, a special panel was designed to be load-bearing during the pour and permit easy stripping without the need for hydraulic systems. TMK Formwork Panels provided an excellent finish, according to the manufacturer. The carriage boasts a high load-bearing capacity, working platforms, access stairways and other integrated safety features.

Due to the excavation clearance, the characteristics of the project and the variety of tasks that had to be performed simultaneously, the complete assembly of the carriage was carried out in sections, pre-assembled on the outside and moved inside the tunnel tubes.

After pouring each 6.25m section, the carriage was easily advanced with a hydraulic system that facilitated formwork placement and stripping, lowering, and levelling, as well as advance.

 

For more information on companies in this article

Related Content

  • Manitowoc and Grove brands launching new designs at bauma China 2014
    November 12, 2014
    The Manitowoc Group is introducing new Potain tower cranes and Grove rough terrain cranes to the Chinese market at bauma China 2014. The two new topless tower cranes come from Manitowoc’s Potain brand and are products of the firm’s Zhangjiagang plant in China. Earlier this year the facility also celebrated the delivery of its 5,000th crane since production began in 2006. Meanwhile from the Grove range of mobile cranes will be the latest RT890E rough-terrain crane. Both machines will be on the firm’s booth a
  • Manitowoc and Grove brands launching new designs at bauma China 2014
    January 6, 2017
    The Manitowoc Group is introducing new Potain tower cranes and Grove rough terrain cranes to the Chinese market at bauma China 2014. The two new topless tower cranes come from Manitowoc’s Potain brand and are products of the firm’s Zhangjiagang plant in China. Earlier this year the facility also celebrated the delivery of its 5,000th crane since production began in 2006. Meanwhile from the Grove range of mobile cranes will be the latest RT890E rough-terrain crane. Both machines will be on the firm’s booth a
  • Award winning bridge for North Carolina
    November 21, 2019
    A new bridge in the US state of North Carolina has won a key award for excellence – Mike Woof writes
  • Mullum Mullum Valley untouched by progress
    July 20, 2012
    Preserving the unspoiled Mullum Mullum Valley was the major consideration when deciding to build a traffic tunnel The answer to one of the major issues facing construction of the A$2.5 billion EastLink route in Australia was simple: construct a tunnel. While it was expensive, those involved realised they had little option but to go underground to protect the environmentally sensitive Mullum Mullum Valley, an untouched area of wood and bushland in Melbourne. EastLink, the 39km toll road project on the easter