Ulma in Poland’s S7 tunnel

Construction of Poland’s longest road tunnel is progressing with an MK Formwork Carriage system from Spanish manufacturer Ulma.
October 22, 2020 Read time: 2 mins
After pouring each 6.25m section, the carriage was easily advanced with a hydraulic system (photo courtesy Ulma)

The S7 Expressway crosses Poland from Lubien´ to Rabka Zdrój, north to south, passing through the Voividato Malopolskie region. Three sections are under construction.

One of these sections goes through Lubon´ Maly mountain, for which a tunnel with two separate tubes is being built - a total length of over 4km. This phase has proven to be the most time-consuming and costly of the entire Expressway project. There are two independent tubes, approximately 2km each, designed for traffic to flow in a single direction.

The tunnel will feature two emergency passageways between the tubes and a ventilation room, as well as technical and service installations. In order to build it, 1,922m have been perforated for the left-hand tunnel and 1,919m for the right.  

Excavation began on the north side of the right-hand tube in March of 2017. Completion of the entire tunnel is expected by mid-2021.

Ulma’s Engineering Team designed an MK Formwork Carriage 15.5m wide and 10.7m long to pour the mine tunnel. With a single unit made from standard MK pieces, the carriage was adapted effortlessly to the tunnel’s complex geometry.

For the roof, a special panel was designed to be load-bearing during the pour and permit easy stripping without the need for hydraulic systems. TMK Formwork Panels provided an excellent finish, according to the manufacturer. The carriage boasts a high load-bearing capacity, working platforms, access stairways and other integrated safety features.

Due to the excavation clearance, the characteristics of the project and the variety of tasks that had to be performed simultaneously, the complete assembly of the carriage was carried out in sections, pre-assembled on the outside and moved inside the tunnel tubes.

After pouring each 6.25m section, the carriage was easily advanced with a hydraulic system that facilitated formwork placement and stripping, lowering, and levelling, as well as advance.

 

For more information on companies in this article

Related Content

  • Auckland Harbour bridge celebrates 50 years
    February 22, 2012
    The bridge over Auckland Harbour celebrates its half century this year, and it has been given a major upgrade to ensure that safety is maintained in New Zealand's largest city. Mary Searle reports. Auckland is New Zealand's largest city, home to nearly a third of the entire country's population. It's a sprawling metropolis, and its 1.3 million people are spread over 637km² of city, suburbs and islands. The Auckland Harbour Bridge, which celebrates its 50th birthday in May, is a vital link in the city's road
  • Auckland Harbour bridge celebrates 50 years
    April 5, 2012
    The bridge over Auckland Harbour celebrates its half century this year, and it has been given a major upgrade to ensure that safety is maintained in New Zealand's largest city. Mary Searle reports. Auckland is New Zealand's largest city, home to nearly a third of the entire country's population. It's a sprawling metropolis, and its 1.3 million people are spread over 637km² of city, suburbs and islands. The Auckland Harbour Bridge, which celebrates its 50th birthday in May, is a vital link in the city's road
  • Cleveland to renovate Redcliffe Bridge
    March 19, 2021
    The iconic UK bascule bridge crossing Bristol city’s harbour was built in 1942.
  • Opening set for Bikos Tunnel section of R4
    June 5, 2023
    Opening of the first stage of Slovakia’s R4 Presov-Northern Bypass expressway, including the 1.1km-long twin-tube Bikos Tunnel, is set for this summer.