Ulma in Poland’s S7 tunnel

Construction of Poland’s longest road tunnel is progressing with an MK Formwork Carriage system from Spanish manufacturer Ulma.
October 22, 2020 Read time: 2 mins
After pouring each 6.25m section, the carriage was easily advanced with a hydraulic system (photo courtesy Ulma)

The S7 Expressway crosses Poland from Lubien´ to Rabka Zdrój, north to south, passing through the Voividato Malopolskie region. Three sections are under construction.

One of these sections goes through Lubon´ Maly mountain, for which a tunnel with two separate tubes is being built - a total length of over 4km. This phase has proven to be the most time-consuming and costly of the entire Expressway project. There are two independent tubes, approximately 2km each, designed for traffic to flow in a single direction.

The tunnel will feature two emergency passageways between the tubes and a ventilation room, as well as technical and service installations. In order to build it, 1,922m have been perforated for the left-hand tunnel and 1,919m for the right.  

Excavation began on the north side of the right-hand tube in March of 2017. Completion of the entire tunnel is expected by mid-2021.

Ulma’s Engineering Team designed an MK Formwork Carriage 15.5m wide and 10.7m long to pour the mine tunnel. With a single unit made from standard MK pieces, the carriage was adapted effortlessly to the tunnel’s complex geometry.

For the roof, a special panel was designed to be load-bearing during the pour and permit easy stripping without the need for hydraulic systems. TMK Formwork Panels provided an excellent finish, according to the manufacturer. The carriage boasts a high load-bearing capacity, working platforms, access stairways and other integrated safety features.

Due to the excavation clearance, the characteristics of the project and the variety of tasks that had to be performed simultaneously, the complete assembly of the carriage was carried out in sections, pre-assembled on the outside and moved inside the tunnel tubes.

After pouring each 6.25m section, the carriage was easily advanced with a hydraulic system that facilitated formwork placement and stripping, lowering, and levelling, as well as advance.

 

For more information on companies in this article

Related Content

  • Peri raises its game with hydraulic cylinder for UP Rosett props
    February 3, 2015
    Peri is highlighting several of its premier products this year, including the company’s panel wall formwork Maximo, its Gridflex grid slab formwork and the Peri UP Rosett Flex props. Intermat also marks the introduction of Maximo into the French market. The product makes the best use of manpower when on-site manpower is at a premium. The one-sided tie installation by only one person reduces the time needed to set up the formwork. Ties are installed from one side without spacer tubes and there is reduced
  • Peri raises its game with hydraulic cylinder for UP Rosett props
    January 6, 2017
    Peri is highlighting several of its premier products this year, including the company’s panel wall formwork Maximo, its Gridflex grid slab formwork and the Peri UP Rosett Flex props. Intermat also marks the introduction of Maximo into the French market. The product makes the best use of manpower when on-site manpower is at a premium. The one-sided tie installation by only one person reduces the time needed to set up the formwork. Ties are installed from one side without spacer tubes and there is reduced
  • Metrostav and Budimex among bidders for Poland’s S7 section
    April 25, 2017
    Poland’s highways directorate, GDDKiA, says 12 bids have been received for construction of the second section of the S7 dual carriageway. The 15km section will run from the Lesznowola junction to the Tarczyn Polnoc junction. Metrostav submitted the highest offer at €118 million, while the cheapest offer came from a consortium of Porr Polska Infrastructure and Porr Bau. Other bidders include others, Budimex, Intercor and Polaqua.
  • Bolivia’s new highway
    October 10, 2017
    Bolivia’s new highway will provide better access into mountain areas – Mauro Nogarin writes At the beginning of 2015, work began on the construction and paving for the Tupiza - Atocha - Uyuni highway project. The route is located in Bolivia’s Potosí department: it is 189m in length and forms part of the Southwest Basic Road Network (RVF) of Bolivia. The completion of this important route is requiring funding worth US$150 million, of which 72% is being delivered through loans from the European Investment