Tunnel inspections reveal safety compliance need

Results show the state of Europe's tunnel infrastructure at its 'most sublime and most depressing quality' as Patrick Smith reports. EuroTAP [European Tunnel Assessment Programme] 2010 has unveiled the results of inspections conducted earlier this year in 26 major tunnels in 13 European countries. The on site inspections, carried out between 12 April and 20 May, 2010, are said to indicate that an "alarming number of operational tunnels across Europe will not be ready to comply with EU tunnel safety rules wh
May 9, 2012 Read time: 4 mins
The double-deck Duplex A86 tunnel near Paris, opened in 2009, gained a glowing report. (EuroTAP, Jan Potente, photographer)

Results show the state of Europe's tunnel infrastructure at its 'most sublime and most depressing quality' as Patrick Smith reports.

2436 EuroTAP [European Tunnel Assessment Programme] 2010 has unveiled the results of inspections conducted earlier this year in 26 major tunnels in 13 European countries. The on site inspections, carried out between 12 April and 20 May, 2010, are said to indicate that an "alarming number of operational tunnels across Europe will not be ready to comply with EU tunnel safety rules when they come into effect in 2014." Of the tunnels (four in Spain, three in Germany, Italy, Austria and Switzerland, two in France and Norway, one in Belgium, Croatia, the Netherlands, Slovenia, the Czech Republic, and for the first time in the history of EuroTAP, in Iceland), overall one was rated as poor, three as very poor, two as acceptable, four as good and 16 tunnels scored very good.

The EU Tunnel Directive setting the minimum safety requirements for tunnels in the trans-European road networks was adopted in 2004.

EuroTAP says that despite significant progress made by many tunnel operators, practically 40% of tunnels tested in EuroTAP 2010 did not score top marks.

"We can see indications that some Member States will have an obvious problem to comply with the deadlines set by the EU Tunnel Directive by 2014 and 2019 respectively," said Wil Botman, director general of the FIA [7115 Fédération Internationale de l’Automobile, the organisation of the world's leading motoring organisations] European Bureau. "It is necessary to speed up the process of refurbishment of tunnels already in operation in order to meet requirements of the Directive and to improve the safety of all motorists." EuroTAP claims that inadequate breathing equipment for fire fighters, a major shortcoming in half of all tunnels would make rescues in thick smoke impossible. Similarly, the frequently noted lack of tunnel loudspeakers makes warnings about accidents to drivers entering or already in the tunnel impossible. Missing hydrants and information displays at portals, no barriers to close the tunnel, dark tunnel walls and insufficient escape route signs were among the most common deficiencies, while 19% of tunnels lack appropriate lighting and in-tunnel traffic radio reception, conditions all motorists expect to function.

With motorisation across Europe expected to increase and not just in peak holiday periods, roads and tunnels will have to bear increasing daily volumes of vehicles and increased risks of accidents.

"This year's results show the state of Europe's tunnel infrastructure at its most sublime and most depressing quality. In last place out of the 26 tested tunnels is Iceland's [sub-sea] Hvalfjörður Tunnel. For this EU candidate country, EuroTAP can serve as a benchmark in its efforts to become an EU member and comply with EU legislation," says EuroTAP.

The Hvalfjördur Tunnel, on the south-west coast of Iceland, opened in 1998, reduced the travel distance between the capital Reykjavík and other localities by over 40km.

Plans for the future include (2010) improved markings for lay-bys; additional fire extinguishers and batteries for the uninterruptible power supply system to be supplemented/replaced. Next year additional video cameras and transmission via optical fibres; additional emergency phones with fire extinguishers and improved markings are planned, while in 2012 escape route signs in the tunnel and new cabling for evacuation lighting will be fitted.

Between 2012 and 2014 the installation of an automatic video surveillance system; an automatic extinguishing system in the transformer stations and certified cables for power supply and control are scheduled.

With traffic in the tunnel increasing by approximately 10-12%/year 2004-2007, it was felt a new tunnel was necessary in 2014-2015 but following the financial crisis in 2008, there has been no growth in traffic.

"All geological research and primary design for the new tunnel was ready in July, 2008 but now it is not on the plan in the public sector for the next 8-10 years," said Gylfi Thordarson, managing director of the tunnel operators Spölur ehf.

At the other end of the test results scale stands the state-of-the-art A86 Duplex Tunnel, part of a ring road around Paris. This exemplary and innovative double-deck tunnel with cross-connections and additional escape and rescue routes every 200m, offers the full range of safety features that other operators should target.

For more information on companies in this article

Related Content

  • How safe is safe?
    February 7, 2024
    When it comes to vehicle restraint systems, just how safe it safe? Attendees to the 3rd International Conference on Road Safety, put on by the ERF - European Union Road Federation – found out, reports David Arminas.
  • IRF calls for action on road traffic noise
    July 12, 2012
    IRF BPC calls for more effective implementation of Noise Reduction Maps According to the European Union Directive 2002/49/EC relating to the assessment and management of environmental noise (END), the Member States of the European Union have committed to abide by a strict timetable of milestones and deliverables, all aimed at reducing current levels of noise and improving the life of Europe's citizens. As part of this overall strategy, European leaders were required to submit national noise action plans by
  • Sri Lanka is suffering a worrying increase in road accidents and road related fatalities
    April 19, 2012
    The latest data from Sri Lanka reveals a massive rise in road accidents and the deaths. Finding the root cause is not straightforward however and may be many complex causes for this scenario. Key factors have been identified by local experts however and these include reckless driving without adequate road discipline, the absence of an effective procedure for issuing driving licenses and a lack of any training procedures for drivers as well as other road users. Other key problems include deficiencies in the
  • New Zealand’s Waterview project is moving closer to completion
    December 13, 2016
    New Zealand’s biggest road project is less than a year away from completion, and a lot of progress has been made since World Highways last looked at the project two years ago - Mary Searle Bell reports New Zealand’s Waterview project is moving closer to completion and will be the largest road project in the country. The NZ$2 billion Western Ring Route will see the creation of an alternative motorway to State Highway 1, which runs through the centre of Auckland. The 47km-long motorway will allow a large p