Tuen Mun to Chek Lap Kok Tunnel project

It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a Bouygues Construction subsidiary, is employing on this project. The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories. Dragage’s contract includes reclamation of 16.5-hectares at the tunnel’s north end to accommodate the north portal and a ventilation building. Wo
December 22, 2016 Read time: 3 mins
Pipe jackling method for cross-passages (Photo courtesy Dragages)

It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a Bouygues Construction subsidiary, is employing on this project.

The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories. Dragage’s contract includes reclamation of 16.5-hectares at the tunnel’s north end to accommodate the north portal and a ventilation building. Work started in 2013 on the nearly US$2.4 project and is due to run until 2018.

979 Bouygues’ tunnel technical director Bruno Combe told the conference that Dragage cut months from the construction schedule by changing the method of tunnel construction beneath the reclaimed area from cut-and-cover to bored. Since this section of the tunnel must accommodate three lanes of traffic in each of the twin tubes rather than two, Dragages used the world’s largest TBM, with a diameter of 17.6m – bigger than Bertha, the machine which creating the Alaskan Way Viaduct replacement tunnel in the US city of Seattle.

After initial larger sections of tunnel were completed, the Herrenknecht-made TBM was converted to a 14m-diameter machine to dig the southbound tunnel while another 2592 Herrenknecht 14m machine is creating the northbound one. The machines require frequent replacements of cutter tools as it makes its way through granite and decomposed granite before getting into softer materials.

Dragages is using its Mobydic system that employs sensors in the disc cutters to take measurements such as speed of rotation and temperature of the discs. As well as indicating disc wear, the information provides insight into the type of rock through which the TBM is churning.

Another Bouygues remote technology, Snake, uses an exploration arm equipped with a high-pressure jet to clean the tools making them ready for inspection and possible replacement. Perhaps the most impressive for delegates was the use of the Telemac, a heavy robotic arm to change cutter tools.

Human intervention is also required to change tools. Because tunnel pressures are high due to the water above it and the fractured rock - up to 6 bar - specialist tunnelling divers must do the work. They remain in pressurised containers on the surface and are shipped to the cutter head in pressurised shuttles. This avoids divers having to go through several compression and decompression cycles during a shift if needed. Apart from saving time, is also lowers health risks associated with the cycles.

Equally as challenging technically is construction of 56 cross-tunnel passages for which Dragages and Herrenknecht devised special 3.85m-diameter mini-TBMs, or pipe-jacking machines. When combined with launch frames, they can cope with the high pressures. To date the contractor has constructed six cross passages using this method.

For more information on companies in this article

Related Content

  • Building the Pfänder tunnes
    April 11, 2012
    The second tube of the Pfänder Tunnel, Bregenz, Austria, where the new main tunnel has been excavated using a tunnel boring machine (TBM), is being constructed by Alpine BeMo Tunnelling. Tubbings have been installed as the inner tunnel lining, and as part of concreting for the inner shell, the FQ 1 crosscut, suitable for vehicles, is being constructed using a tunnel formwork carriage designed and supplied by PERI.
  • Uprades for Glaskar and Damsgård tunnels
    July 10, 2023
    Norway’s Statens vegvesen will improve safety and communication systems in the Glaskar and Damsgård tunnels in Bergen.
  • Work commencing on key New Zealand tunnel link
    August 3, 2012
    New Zealand prime minister John Key led an official ground-breaking ceremony this week to allow the start of excavation work for two new 2.4km-long motorway tunnels beneath suburban Auckland. The Waterview Connection project is on schedule to begin its main construction phase next year, and the prime minister was on hand to turn the first soil for a 30m-deep trench which is needed to allow access for the tunnels’ southern approach trench in the west Auckland suburb of Owairaka.
  • Design underway for Hong Kong tunnel project
    December 12, 2012
    Work is moving ahead on the plans for a new tunnel link in Hong Kong, with the detailed design work now underway. The Central Kowloon Route (CKR) is now at the detailed design stage and Hong Kong’s Highways Department has launched the three-month phase two public engagement exercise, to collect public views on the design and construction plans. The route will be 4.7km long featuring three lanes in either direction and a 3.9km long tunnel section. Construction work is set to start in 2015 and will be comple