Tuen Mun to Chek Lap Kok Tunnel project

It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a Bouygues Construction subsidiary, is employing on this project. The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories. Dragage’s contract includes reclamation of 16.5-hectares at the tunnel’s north end to accommodate the north portal and a ventilation building. Wo
December 22, 2016 Read time: 3 mins
Pipe jackling method for cross-passages (Photo courtesy Dragages)

It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a Bouygues Construction subsidiary, is employing on this project.

The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories. Dragage’s contract includes reclamation of 16.5-hectares at the tunnel’s north end to accommodate the north portal and a ventilation building. Work started in 2013 on the nearly US$2.4 project and is due to run until 2018.

979 Bouygues’ tunnel technical director Bruno Combe told the conference that Dragage cut months from the construction schedule by changing the method of tunnel construction beneath the reclaimed area from cut-and-cover to bored. Since this section of the tunnel must accommodate three lanes of traffic in each of the twin tubes rather than two, Dragages used the world’s largest TBM, with a diameter of 17.6m – bigger than Bertha, the machine which creating the Alaskan Way Viaduct replacement tunnel in the US city of Seattle.

After initial larger sections of tunnel were completed, the Herrenknecht-made TBM was converted to a 14m-diameter machine to dig the southbound tunnel while another 2592 Herrenknecht 14m machine is creating the northbound one. The machines require frequent replacements of cutter tools as it makes its way through granite and decomposed granite before getting into softer materials.

Dragages is using its Mobydic system that employs sensors in the disc cutters to take measurements such as speed of rotation and temperature of the discs. As well as indicating disc wear, the information provides insight into the type of rock through which the TBM is churning.

Another Bouygues remote technology, Snake, uses an exploration arm equipped with a high-pressure jet to clean the tools making them ready for inspection and possible replacement. Perhaps the most impressive for delegates was the use of the Telemac, a heavy robotic arm to change cutter tools.

Human intervention is also required to change tools. Because tunnel pressures are high due to the water above it and the fractured rock - up to 6 bar - specialist tunnelling divers must do the work. They remain in pressurised containers on the surface and are shipped to the cutter head in pressurised shuttles. This avoids divers having to go through several compression and decompression cycles during a shift if needed. Apart from saving time, is also lowers health risks associated with the cycles.

Equally as challenging technically is construction of 56 cross-tunnel passages for which Dragages and Herrenknecht devised special 3.85m-diameter mini-TBMs, or pipe-jacking machines. When combined with launch frames, they can cope with the high pressures. To date the contractor has constructed six cross passages using this method.

For more information on companies in this article

Related Content

  • Brisbane’s new airport link is an engineering success
    April 12, 2013
    Financial troubles for Brisbane's new Airport Link overshadow its construction success – Adrian Greeman writes. Political argument and legal dispute is likely to rage for some time yet over the bankruptcy of Australian road operator BrisConnect, which went into receivership this February with A$3 billion in debt. Toll paying users for its new Airport Link have been less than half the predicted numbers since it opened in July last summer. But if its nancial engineering is being questioned, the same is not t
  • Bertha readies for more Seattle SR99 Alaskan Way Viaduct tunnel work
    July 27, 2015
    Bertha, one of the world’s largest tunnelling machines will resume work underneath the US city of Seattle in November, nearly two years after breaking down. Bertha, at 17.4m diameter, began her journey in July 2013. She was boring a path to relocate a 3.2km stretch of the elevated State Route 99 Alaskan Way Viaduct, built between 1949 and 1953 and which carries around 100,000 vehicles daily. The elevated section will be moved underground allowing the creation of public space along Seattle’s downtown w
  • Take a breather with Herrenknecht’s ventilation shaft boring machine
    February 10, 2016
    For fast underground construction of slot holes with small diameters within highway tunnels, Herrenknecht is highlighting its Boxhole Boring Machine. The BBM is for slot holes, or boreholes, such as ventilation shafts, either inclined or vertical, with diameters of up to 1.5m and lengths of up to 60m. The machines are designed for stable rock with compressive strengths of 180 Megapascal or more. Herrenknecht, based in Schwanau, southwest Germany, uses pipe jacking technology for its BBM. A drilling un
  • Take a breather with Herrenknecht’s ventilation shaft boring machine
    January 6, 2017
    For fast underground construction of slot holes with small diameters within highway tunnels, Herrenknecht is highlighting its Boxhole Boring Machine. The BBM is for slot holes, or boreholes, such as ventilation shafts, either inclined or vertical, with diameters of up to 1.5m and lengths of up to 60m. The machines are designed for stable rock with compressive strengths of 180 Megapascal or more. Herrenknecht, based in Schwanau, southwest Germany, uses pipe jacking technology for its BBM. A drilling un