Tuen Mun to Chek Lap Kok tunnel connection

It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a Bouygues Construction subsidiary, is employing on this project The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories.
January 24, 2017 Read time: 3 mins
Main tunnel (photo courtesy Dragages)
It is not only the scale of the Tuen Mun to Chek Lap Kok tunnel that impressed delegates but the number of novel technologies that Dragages Hong Kong, a 979 Bouygues Construction subsidiary, is employing on this project

The 4.6 km tunnel running 60m below sea level is part of a strategic new route linking Hong Kong’s airport on Lantau Island and the New Territories.

Dragage’s contract includes reclamation of 16.5-hectares at the tunnel’s north end to accommodate the north portal and a ventilation building. Work started in 2013 on the nearly US$2.4 project and is due to run until 2018.

Bouygues’ tunnel technical director Bruno Combe told the conference that Dragage cut months from the construction schedule by changing the method of tunnel construction beneath the reclaimed area from cut-and-cover to bored. Since this section of the tunnel must accommodate three lanes of traffic in each of the twin tubes rather than two, Dragages used the world’s largest TBM, with a diameter of 17.6m – bigger than Bertha, the machine which creating the Alaskan Way Viaduct replacement tunnel in the US city of Seattle.

After initial larger sections of tunnel were completed, the 2592 Herrenknecht-made TBM was converted to a 14m-diameter machine to dig the southbound tunnel while another Herrenknecht 14m machine is creating the northbound one. The machines require frequent replacements of cutter tools as it makes its way through granite and decomposed granite before getting into softer materials.

Dragages is using its Mobydic system that employs sensors in the disc cutters to take measurements such as speed of rotation and temperature of the discs. As well as indicating disc wear, the information provides insight into the type of rock through which the TBM is churning.
Another Bouygues remote technology, Snake, uses an exploration arm equipped with a high-pressure jet to clean the tools making them ready for inspection and possible replacement. Perhaps the most impressive for delegates was the use of the Telemac, a heavy robotic arm to change cutter tools.

Human intervention is also required to change tools. Because tunnel pressures are high due to the water above it and the fractured rock - up to 6 bar - specialist tunnelling divers must do the work. They remain in pressurised containers on the surface and are shipped to the cutter head in pressurised shuttles. This avoids divers having to go through several compression and decompression cycles during a shift if needed. Apart from saving time, is also lowers health risks associated with the cycles.

Equally as challenging technically is construction of 56 cross-tunnel passages for which Dragages and Herrenknecht devised special 3.85m-diameter mini-TBMs, or pipejacking machines. When combined with launch frames, they can cope with the high pressures. To date the contractor has constructed six cross passages using this method.

For more information on companies in this article

Related Content

  • New Lokotrack's compact crushing
    February 6, 2012
    Metso is adding to its mobile Lokotrack crushing range with the new LT110C model. Designed for primary crushing, the LT110C is rugged in design but compact and features a Nordberg C110 jaw crusher, with a feed opening of 1100x850mm. Metso is offering two feeder variants and where large quantities of fines need to be scalped, a pan feeder and a separate two-deck scalper can be fitted. Depending on the feeder system selected, the Lokotrack LT110C can be equipped with either a standard 6m3 or an optional 9m3 f
  • Drilling's novel solutions
    July 23, 2012
    In the drilling and hydraulic attachment sectors too, firms are offering novel solutions for the customer. Atlas Copco continues to develop its comprehensive range of drilling solutions in the shape of its latest down-the-hole (DTH) and SmartRig variants, as well as adding new compact rigs and new consumables to the line-up. The firm's latest Roc L630 DTH rig benefits from a new feed as well as improved cooling. The new aluminium feed is said to improve hole straightness and hole quality. It also allows the
  • Highway project in Texas required demolition equipment
    May 1, 2018
    A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
  • Delayed Hong Kong tunnel cost climbing
    March 4, 2016
    Costs are climbing for a new road tunnel connection in Hong Kong. After a reassessment on the Tseung Kwan O-Lam Tin tunnel (Tseung-Lam tunnel) development project, the project cost increased from US$1.05 billion to $1.92 billion. The expected completion time has also been delayed from 2020 to 2021. The 4.2km tunnel will feature two lanes. The project is intended to reduce traffic congestion in Tseung Kwan O area during peak hours. Hong Kong’s Transport and Housing Bureau hopes to obtain approval from the Fi