Sprayed tunnel waterproofing reduces build costs

Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.
February 10, 2012 Read time: 3 mins
Spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, means the final lining can be permanent sprayed concrete instead of cast in-situ concrete
Sprayed waterproofing: 'hot topic' Sprayed waterproofing is a hot industry topic, and a paper presented at the recent North American Tunnelling Conference not only discussed this method for achieving a dry tunnel but also how it can reduce build costs and construction time.

 In traditional SCL-SEM-NATM [Sprayed Concrete Lining-Sequential Excavation Method-New Austrian Tunnelling Method] tunnel construction, regardless of the thickness of concrete sprayed to form the primary lining, from a structural perspective this concrete is ignored, says 2314 Stirling Lloyd.

 According to the company, the full structural load is supported by the final or secondary lining. A sheet membrane is then tacked to various points of the primary concrete but it is not fully bonded. This compromises the choice for the final lining as it is exceptionally difficult to get sprayed concrete to bond to a sheet membrane system: the sprayed concrete tends to rebound off the membrane surface. This effect can be reduced by the use of lattice girders and reinforcing steel mesh to help support the sprayed concrete during application.

 However, this tends to have a detrimental effect on the quality of the final lining as achieving adequate compaction of sprayed concrete through a network of steel reinforcement is difficult, resulting in voids and failure to passivate the steel against corrosion from ground water when it is not adequately encapsulated.

 As a consequence the construction method currently favoured for final linings tends to be traditionally reinforced cast in-situ concrete. This is much slower than spraying concrete, claims Stirling Lloyd.

"The great design benefit of spray applied waterproofing, such as Stirling Lloyd's Integritank HF membrane, is that the final lining can be permanent sprayed concrete instead of cast in-situ concrete.

With no requirement for fibre reinforcement, traditional lattice girders and rebars, build speed is increased and cost reduced."

Colin Eddie from 2567 Morgan Sindall Underground Professional Services takes the view that, depending on the design of the tunnel, cost savings of up to 50% are achievable with a sprayed solution, when considering the waterproofing and final lining taken together.

 The most significant advance that a fully bonded sprayed membrane offers is the composite effect, between the primary and secondary sprayed concrete layers, says Stirling Lloyd.

 In construction which includes sprayed waterproofing, the primary and secondary concrete layers are both fully and intimately bonded to the membrane. Consequently, unlike when using sheet systems, both the concrete layers are acting together and therefore both the primary and secondary linings contribute to the load bearing capability of the tunnel.

 "Research carried out by Morgan Sindall, both in its Underground Professional Services division at Rugby, England and supported by further work at 2568 Warwick University to test this theory have shown that two concentric rings of sprayed concrete, bonded together by Stirling Lloyd's Integritank HF tunnel waterproofing membrane, behave in the same way as a monolithic ring of the same dimensions,"says Stirling Lloyd.

 "While earlier work had suggested that a mechanical key between the concentric rings is required by way of an uneven interface, the Warwick University work shows that this is not the case, and even with a smooth interface the full effect is achieved."

For more information on companies in this article

Related Content

  • Pre-stressed bridge decks use modular formwork system
    July 9, 2012
    Imaginative formwork, often using modular components, is helping to shape some challenging bridges worldwide. Patrick Smith reports Traffic volumes in and around Prague have swollen massively in recent years, pushing the existing road network to the limits of its capacity. To permanently ease congestion in the Czech capital's centre, a multi-lane orbital motorway is under construction as a high capacity bypass for central Prague and to link up all the motorways and other major highways radiating from the ci
  • Peri has Polish bridge covered
    February 6, 2012
    A new bridge is being constructed across the Vistula River near Grudzi?dz, Poland, and for the foreland bridge from south-east direction, a so-called incremental launching method is being used. Two lanes, each some 556m long, are being constructed in 25 concreting cycles with standard lengths of 24m, while the formwork is 25m long and is positioned behind the bridge abutments.
  • PERI fills gap in Greek market
    February 19, 2013
    A team of Greek and German PERI engineers have developed a comprehensive formwork and scaffolding solution for the T4 bridge on the A7 motorway in Greece. The 160km long A7 connects Kalamata in the south to Corinth in the northwest of the Peloponnese peninsula. On one stretch of the motorway a 390m long arched bridge – known as T4 – is being used to close the gap between Paradisia and Tsakona. Set for completion in early 2014, two-thirds of the 22m wide bridge superstructure will be suspended on a steel arc
  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.