Skip to main content

Simex machine helps deliver new tunnel lining

In Italy an MP1000 cutting system from Simex has been used to help resurface the walls of a highway tunnel. The SS51 State Road crosses through the Dolomites in the north-eastern Alpine Region of Italy. The SS51 starts in San Vendemiano in the province of Treviso and ends in Dobbiaco in the province of Bolzano and is a key road because it connects Cadore and the main towns in the area of Cortina d'Ampezzo. This 134.4 km road has expansion work and upgrades to improve safety and boost capacity.
December 3, 2014 Read time: 4 mins

 In Italy an MP1000 cutting system from Simex has been used to help resurface the walls of a highway tunnel. The SS51 State Road crosses through the Dolomites in the north-eastern Alpine Region of Italy. The SS51 starts in San Vendemiano in the province of Treviso and ends in Dobbiaco in the province of Bolzano and is a key road because it connects Cadore and the main towns in the area of Cortina d'Ampezzo. This 134.4 km road has expansion work and upgrades to improve safety and boost capacity.

One the most important sections is the 1.34km Caralte tunnel near Pieve di Cadore, which has a road surface 7.2m wide and includes 1.3m wide pedestrian walkways. Along with the ponte Cadore, this single-tube tunnel is part of an important bypass that avoids motorists from having to pass through the town of Perarolo di Cadore and the section of road known as la Cavallera with its many hairpin turns. But, completed in 1985, the concrete lining of the tunnel had started to deteriorate.

The ANAS road infrastructure authority of the Venice district decided to restore the tunnel walls by means of waterproofing and ceiling reinforcement. The project consisted of injecting polyurethane resins to close the cracks and prevent water from reaching the lining, removing 30mm of the degraded layer by scarification and then applying a special fibre-reinforced grout. The tunnel ceiling was also fittted with four L-shaped elements at spaced intervals to prevent detachment of the concrete over time. The rehabilitation works of the Cadore Tunnel were assigned to a temporary consortium made up of Cadore Asfalti Srl of Perarolo di Cadore and Esposito Mario of Trento.

A critical aspect of the job came from the time restraints of closures for the restoration works. Even partial closure would lead to detours along the long and winding roads. High productivity as well as precise profiling were crucial and in all, the project required a total of 24,300m2 of scarified surface.

Contractor Grotti carried out the scarification using a GTF 200 RC and a special Simex MP 1000 planer. The GTF 200 RC is a machine constructed by Grotti based on a tracked excavator but with features such as a telescopic boom that can follow the profile of the tunnel from the ceiling along the side walls; a hydraulic circuit designed to power the Simex attachments; and a remote control allowing the operator to work at a distance. Grotti was subcontracted by Cadore Asfalti. The extension of the boom right up to the 6.6m high tunnel ceiling and the fact that the boom could be retracted to follow the profile along the side walls allowed the work to be carried out. The Simex MP 1000 planer featured a drum equipped with 134 teeth, providing a surface ready for the application of the fibre-reinforced grout.

Injected resins were used to close the cracks and seal the joints. This entailed the use of single-component hydroreactive and expanding polyurethane resin from the MasterBuilder line produced by BASF. The MasterRoc MP 355 1K DW material is free of solvents and can react with water by forming a porous foam with expansion capacity 20-25 times its own volume.

This was injected in proximity to the cracks by boring 10-15mm diameter holes. Injection was carried out using polyamide truncated cone-shaped packers, and in some more critical areas, in steel as well. Both models were certified to withstand an injection pressure of 250bar and to ensure a seal. In some areas the procedure involved filling actual cavities formed behind the lining. In total, over 30,000 boreholes and injections were carried out, sealing the tunnel effectively.

Related Content

  • Improving the UK’s road markings efficiently
    June 30, 2014
    According to a recently published report, based on the findings of the Road Safety Markings Association (RSMA), the condition of road markings on the UK’s roads is so poor they require immediate remedial action. This comprehensive survey covered 7,000km of the roads in England, Wales, Scotland and Northern Ireland. It revealed that 47% of markings on all roads (and as much as 52% on motorways) in England are in need of immediate replacement or should be scheduled for replacement in order to ensure they meet
  • Asphalt paving improves road safety
    March 14, 2012
    A special emulsion is being used at the largest gold mine in South America for slurry surfacing on its compacted, unpaved roads. The result is said to be greatly curtailed particulate emissions and enhanced visibility which makes roads safer and reduces regional haze.
  • Durable surface solution
    February 22, 2012
    Innovative spray pavers from Vögele have been used in Germany to rehabilitate a section of the A99 autobahn near Munich. In all, four SUPER 1800-2 pavers fitted with SprayJet Module were used to pave a thin, noise-reducing asphalt. overlay on spray seal on the A99 to the west of the Allach Tunnel. For pavement rehabilitation, this stretch of the busy orbital motorway near Munich could only be closed to traffic at night. The traffic volume on the A99 orbital motorway near Munich is 100,000-120,000 vehicles/d
  • UltraScape makes a point at the Juuliku Road junction in Tallinn
    February 23, 2018
    Instarmac’s UltraScape Flowpoint grouting has been installed at three new roundabouts and road edges in the Estonian capital Tallinin. Instarmac’s Estonian partner RoadService laid the Flowpoint at the Juuliku Road junction at Tallinn Roundabout. Construction of Juuliku Road Junction and Road Section involved reconstructing areas of the existing road network as well as introducing a 3.4km connection road, two bridges and viaducts and a two-level interchange. An additional three roundabouts were built wit