Self-climbing formwork solution for bridge pylons

Harsco Infrastructure has provided self-climbing formwork (SCF), which is helping ensure quick and safe access during the construction of a 320m tall pylon for the world’s longest cable-stayed bridge.
February 27, 2012 Read time: 3 mins
Harsco Infrastructure’s self-climbing formwork is used on the 320m tall pylon of the Russky Island Bridge

Harsco Infrastructure has provided self-climbing formwork (SCF), which is helping ensure quick and safe access during the construction of a 320m tall pylon for the world’s longest cable-stayed bridge.

With its 1,100m central span the 3,100m Russky Island Bridge will ultimately be the world’s longest and tallest cable-stayed bridge. Traversing the Eastern Bosphorus, the US$490 million bridge will link the far east port of Vladivostok with Russky Island, which belongs to the Russian city.

Russian building contractor, SK MOST, is aiming for a record-breaking construction period
of just 43 months so that the bridge’s four-lane road is open in time for the 2868 Asia-Pacific Economic Cooperation summit at the end of 2012.

The 3234 Harsco solution provides a fully enclosed temporary working environment which protects against extreme weather conditions during construction of the pylon and its 70m tall approach piers, which together form part of the record-breaking bridge.    

SPECIFICATION
Russky Island Bridge


•Bridge deck width (steel structure): 21m

•Headroom under bridge: 70m

•Bridge length: 1,885.53m

•Total bridge length: 3,100m

•Largest span: 1,104m

•Height of bridge pylons: 320.9m

•Budget: €360 million
During the technical planning phase Harsco’s SCF team used its expertise to accelerate the construction schedule and ensure maximum safety, particularly for the two climbing units used on the pylon. This eliminated the need for any time-consuming conversion work and resulted in a formwork and platform solution that is said to be perfectly adapted to the tapering and inclined geometry of the pylon itself.


At the base, this calls for a ground plan of 7.8 x 13m with a 2m wall thickness, tapering to 7.1 x 7m with a 0.7m wall thickness at the top. The in-depth planning means that only a single work platform has to be removed from the SCF assembly, which is done during a pre-scheduled break in construction work. All other adjustments and climbing can be carried out safely and without holding up the site work unnecessarily.

To accommodate the tight construction schedule the system was specifically designed to allow adjustments to the SCF, and the 72 climbing cycles of 4.5m, to be performed quickly.

Rigid separation between the steelfixing levels and the shuttering and climbing operations means that once the steelfixing is completed, the formwork can be retracted and cleaned before the climbing shoes are fitted and the climbing rails raised and tied for the next pouring cycle. This allows the SCF platforms to be raised immediately after completion of the steelfixing and the formwork to be moved into its new position ready for the next pour. Once pouring is complete, the steelfixing for the next cycle can begin.

To protect men and materials from the severe climate, the self-climbing formwork is fully enclosed, complete with a modular, movable roof.

The exceptionally high load-bearing capacity of Harsco’s SCF brackets (150 kN vertically and 100 kN horizontally) is crucial to this project. The pylon’s special geometry, and continuous tapering, mean that only six of the 22 brackets employed actually climb vertically, with the others climbing at transverse and often changing angles of up to 5% from the vertical. Despite its high load-bearing capacity each SCF bracket requires just a single tie, with installation of the tie cones being a simple task. The cones only need to be positioned at the correct horizontal intervals, and unlike pairs of cones, they do not need to be set at a precisely measured angle.

Harsco is providing a formwork foreman and a number of technicians to support the project and ensure that the meticulously planned work processes are followed on site.

For more information on companies in this article

Related Content

  • Innovations in piling technology
    December 15, 2017
    The market for piling machines is seeing new technology come to market – Mike Woof writes UK firm BSP is now offering an improved range of piling systems, with its SL30 model and compact BH120. The SL30 can be used to drive Z piles in pairs and its hammer has a drop weight of 2.5tonnes, delivering an impact energy of 30kNm at up 84blows/minute. The SL piling hammer is designed for driving sheet piles and small bearing piles and is available with legs and inserts for use when freely suspended or with back
  • Clever approach to reducing bridge vibrations
    November 14, 2013
    Reducing vibrations on a bridge, supplying high-quality binders to emerging countries and helping small and medium players with warm mix, this month’s stories showcase some innovative bitumen technology solutions - Kristina Smith reports The Kessock Bridge in the Highlands of Scotland has become the third bridge in the UK to be resurfaced with Gussasphalt. A dense mastic asphalt containing Nynas Endura N5, a polymer modified binder, Gussasphalt has been designed to have a longer life than standard mastic as
  • Contracts for $1.9 billion Francis Scott Key bridge
    February 27, 2025
    Key contracts have been awarded for the $1.9 billion Francis Scott Key bridge.
  • China opens record-breaking bridge
    April 11, 2012
    China has opened the world's longest bridge over water, the 41.58km Jiaozhou Bay Bridge, which is said to have cost well over US$2 billion to build. It links the eastern port city of Qingdao to Huangdao Island across Jiaozhou Bay and is 4km longer than the previous longest bridge over water, the Lake Pontchartrain Causeway in Louisiana, USA. Opened in June, 2011 after four years of construction, the link is expected to carry some 30,000 vehicle/day and will reduce travel time by 30 minutes, although it is o