Self-climbing formwork solution for bridge pylons

Harsco Infrastructure has provided self-climbing formwork (SCF), which is helping ensure quick and safe access during the construction of a 320m tall pylon for the world’s longest cable-stayed bridge.
February 27, 2012 Read time: 3 mins
Harsco Infrastructure’s self-climbing formwork is used on the 320m tall pylon of the Russky Island Bridge

Harsco Infrastructure has provided self-climbing formwork (SCF), which is helping ensure quick and safe access during the construction of a 320m tall pylon for the world’s longest cable-stayed bridge.

With its 1,100m central span the 3,100m Russky Island Bridge will ultimately be the world’s longest and tallest cable-stayed bridge. Traversing the Eastern Bosphorus, the US$490 million bridge will link the far east port of Vladivostok with Russky Island, which belongs to the Russian city.

Russian building contractor, SK MOST, is aiming for a record-breaking construction period
of just 43 months so that the bridge’s four-lane road is open in time for the 2868 Asia-Pacific Economic Cooperation summit at the end of 2012.

The 3234 Harsco solution provides a fully enclosed temporary working environment which protects against extreme weather conditions during construction of the pylon and its 70m tall approach piers, which together form part of the record-breaking bridge.    

SPECIFICATION
Russky Island Bridge


•Bridge deck width (steel structure): 21m

•Headroom under bridge: 70m

•Bridge length: 1,885.53m

•Total bridge length: 3,100m

•Largest span: 1,104m

•Height of bridge pylons: 320.9m

•Budget: €360 million
During the technical planning phase Harsco’s SCF team used its expertise to accelerate the construction schedule and ensure maximum safety, particularly for the two climbing units used on the pylon. This eliminated the need for any time-consuming conversion work and resulted in a formwork and platform solution that is said to be perfectly adapted to the tapering and inclined geometry of the pylon itself.


At the base, this calls for a ground plan of 7.8 x 13m with a 2m wall thickness, tapering to 7.1 x 7m with a 0.7m wall thickness at the top. The in-depth planning means that only a single work platform has to be removed from the SCF assembly, which is done during a pre-scheduled break in construction work. All other adjustments and climbing can be carried out safely and without holding up the site work unnecessarily.

To accommodate the tight construction schedule the system was specifically designed to allow adjustments to the SCF, and the 72 climbing cycles of 4.5m, to be performed quickly.

Rigid separation between the steelfixing levels and the shuttering and climbing operations means that once the steelfixing is completed, the formwork can be retracted and cleaned before the climbing shoes are fitted and the climbing rails raised and tied for the next pouring cycle. This allows the SCF platforms to be raised immediately after completion of the steelfixing and the formwork to be moved into its new position ready for the next pour. Once pouring is complete, the steelfixing for the next cycle can begin.

To protect men and materials from the severe climate, the self-climbing formwork is fully enclosed, complete with a modular, movable roof.

The exceptionally high load-bearing capacity of Harsco’s SCF brackets (150 kN vertically and 100 kN horizontally) is crucial to this project. The pylon’s special geometry, and continuous tapering, mean that only six of the 22 brackets employed actually climb vertically, with the others climbing at transverse and often changing angles of up to 5% from the vertical. Despite its high load-bearing capacity each SCF bracket requires just a single tie, with installation of the tie cones being a simple task. The cones only need to be positioned at the correct horizontal intervals, and unlike pairs of cones, they do not need to be set at a precisely measured angle.

Harsco is providing a formwork foreman and a number of technicians to support the project and ensure that the meticulously planned work processes are followed on site.

For more information on companies in this article

Related Content

  • Aquajet's new hybrid hydrodemolition robot
    February 27, 2012
    In what it says is a "a world first," Swedish specialist company Aquajet Systems has introduced a new diesel/electric-powered hybrid hydrodemolition robot offering a wide range of new features, including pollution-free operation in enclosed areas in electric-mode.
  • Efficient sheet piling for motorway projects
    January 11, 2019
    A UK-based steel sheet-piling contractor, Sheet Piling, is now using a TM 12/15 LR rig from the German ABI Group for motorway projects such as the widening of existing earthworks. This is said to be the world’s first long-reach telescopic leader rig, which is claimed will revolutionise sheet piling operations. The highly advanced vibratory installation rig features a maximum horizontal reach of 8.1m, measured from the centre of its cab’s body to the pile-driving position. This is said to be 3m further t
  • Romania’s important bridge project
    October 5, 2022
    Romania’s important Braila Bridge project will deliver a key crossing spanning the Danube River
  • Controversial Russian bridge opens
    May 16, 2018
    The first stage of a controversial Russian bridge project is now complete, with the link opening to use by cars. The Kerch Strait bridge spans the Black Sea, connecting Russia’s Taman Peninsula in Krasnodar with Crimea, the latter having been controversially annexed by Russia from Ukraine in 2014. The official opening of the 19km-long bridge was carried out by Russia’s president, Vladimir Putin, who drove across the link in a Kamaz truck to reach the city of Kerch. The US$2.7 billion bridge forms part of