RMD’s Hong Kong highway project

RMD Kwikform has supplied its 80kN Rapidshor shoring for the widening of the Tolo Highway, running between the Island House Interchange and Tai Hang in Hong Kong. The project, overseen by main contractor Gammon Construction and set to be completed by the end of 2013, will widen the Tolo Highway from a two to four-lane carriageway in each direction, alleviating traffic congestion. “We were approached by [project] sub-contractors, United Soundfair and Richwell Engineering to supply shoring and formwork suppor
June 13, 2012 Read time: 2 mins
319 RMD Kwikform has supplied its 80kN Rapidshor shoring for the widening of the Tolo Highway, running between the Island House Interchange and Tai Hang in Hong Kong.

The project, overseen by main contractor 1526 Gammon Construction and set to be completed by the end of 2013, will widen the Tolo Highway from a two to four-lane carriageway in each direction, alleviating traffic congestion.

“We were approached by [project] sub-contractors, United Soundfair and Richwell Engineering to supply shoring and formwork support,” says Noel Kennedy, general manager for RMD Kwikform Hong Kong.

“The scale of the site and project required the use of our 80kN capacity Rapidshor shoring, to ensure safety and the continuous traffic flow needed, whilst the widening took place. Due to the location of the site, we also needed to engineer a solution using Rapidshor to support the overhead works spanning the slip roads at interchanges, whilst maintaining a safe access route for traffic.

“In addition to the main Rapidshor shoring, we also utilised our Megashor heavy duty shoring to provide extra support to a variety of the bridge deck structures, some up to a height of 25metres,  with SuperSlim and GTX Beams used to create the soffit.”

Kennedy says the Tolo Highways project is one of many that have benefitted from the use of Rapidshor, which is one of the more widely used systems in Hong Kong. RMD Kwikform says it’s popular with sub-contractors, as it allows them to use less labour, due to the heavy leg load capacity.

For more information on companies in this article

Related Content

  • Advanced method for South Africa bridge construction
    May 16, 2016
    A sophisticated construction method has been used for the first time in South Africa for a suspended bridge project This novel method of bridge construction was used on a major road upgrade project for the South African National Roads Agency Limited (SANRAL). Main contractor Lonerock Construction, and subcontractor Tzandeboo Construction, used RMD Kwikform’s Megatruss system to construct a 60m-long bridge while suspended mid-air over the live N4 highway. Lonerock Construction’s US$8.5 million (R132
  • Bridge engineering worldwide
    July 1, 2013
    Guy Woodford looks at vital bridge construction, repair and inspection projects in China, Europe, North America and Australia The Heron Road Bridge in Ottawa, Ontario in Canada is a vital link within the City’s transport network, as it crosses the Rideau River, which divides the east and west parts of the City. Constructed in 1966-1967, the Heron Road Bridge is approximately 275m long and includes six lanes.
  • RMD launches R800 panel girder
    July 19, 2022
    RMD Kwikform has launched its heavy-duty R800 modular panel girder system which the company says is the only CE-marked girder system on the market.
  • Advanced method for South Africa bridge construction
    May 16, 2016
    A sophisticated construction method has been used for the first time in South Africa for a suspended bridge project This novel method of bridge construction was used on a major road upgrade project for the South African National Roads Agency Limited (SANRAL). Main contractor Lonerock Construction, and subcontractor Tzandeboo Construction, used RMD Kwikform’s Megatruss system to construct a 60m-long bridge while suspended mid-air over the live N4 highway. Lonerock Construction’s US$8.5 million (R132