Skip to main content

RMD Kwikform: the role of temporary works in the age of BIM

Formwork and shoring are no longer isolated services that stand outside the design process of infrastructure projects, as Simon Dowd* explained In recent years, the roles of suppliers have changed as client and main contractors require more visibility and data from their construction sites. Due to the requirements of BIM - building information modelling - and the adoption of digital processes, it is no longer the role of a temporary works business to simply provide formwork and shoring. Simon Dowd said
April 19, 2018 Read time: 4 mins
Formwork and shoring are no longer isolated services that stand outside the design process of infrastructure projects, as Simon Dowd* explained


In recent years, the roles of suppliers have changed as client and main contractors require more visibility and data from their construction sites. Due to the requirements of BIM - building information modelling - and the adoption of digital processes, it is no longer the role of a temporary works business to simply provide formwork and shoring.

Simon Dowd said, “At 319 RMD Kwikform, it is now our responsibility to interact with the entire supply chain to support the overall method of construction, including its design and processes.”

He continued, “We recognised some years back that the industry would move away from 2D drawings. It has been a slow trend. But as we work closer with customers, particularly on larger infrastructure projects, it’s clear that 3D drawings should now be standard practice. We quickly learned that in order to service our customers - and by extension their clients - better, we must evolve and work smarter alongside them.”

RMD Kwikform has since evolved its 3D capabilities and designed solutions to automate highly realistic rendered 3D models, using an in-house developed visualisation tool, LocusEye. These models can be viewed on a PC, iPad or mobile phone, providing customers with a realistic model of how any solution looks on site. Flexible in functionality, LocusEye allows for changes to be made instantly and for solutions to be re-examined.

The industry needs smart solutions. With the growing adoption of BIM and the mandatory use of it in major projects, our customers are now demanding IFC BIM compliant models of our temporary works solutions.

Dowd said, “In response to our customer’s needs, we’re now building, automating and converting 3D AutoCAD models into IFC BIM compliant models. Through this system, on-site clashes can be detected, plus data can be captured to better manage equipment and plan construction phasing.”

LocusEye has already been used across a number of national and international projects. These include the UK’s Mersey Gateway and University College London Hospital, Australia’s Ventilation Facility and a number of access towers in Saudi Arabia.

Dowd said, “Some of the feedback we’ve already had is around the responsiveness of the models and how easy they are to interrogate. However, more importantly we’ve seen how much a positive impact this has had in allowing main contractors to visualise the overall management, build ability and future planning of the site.”

He continued, “Any construction site needs to be flexible; it’s just the nature of the job, the site demands change. With BIM compliant models and through LocusEye, our customers see what impact said change will have on a site.” How does this change and affect planned phasing; how does it impact delivery of equipment? He explained, “As the models are already embedded into the BIM model, our customers are able to manipulate processes, change phasing, and target specific elements of any model. This puts the control back in the contractor’s hands and grants complete visibility.”

“With BIM compliant packages and the added advantage of LocusEye, customers use their own tacit knowledge to look at practicalities for delivery, erection and dismantling of kit. They can see where access and egress can be placed and how the temporary works solution accommodates for other works on site.”

He concluded, “It’s all about the better management of the site in order to ensure even safer working practices, and ultimately reduce time and costs.”

*Simon Dowd is major projects manager at RMD Kwikform.

For more information on companies in this article

Related Content

  • LeeBoy’s strong future, through Tier 4 Final investment
    February 22, 2019
    LeeBoy is seeing strong sales for its road machines at the moment, particularly in the US. And the firm’s early investment in fitting Tier 4 Final compliant engines has played a significant role Christopher Barnard is CEO of LeeBoy and commented, “The US has been strong. Demand is there and the infrastructure spending is there. It’s a good market. In our segment for commercial paving we’re doing very well.” The paver range is selling well and the firm’s 8520 model is a particularly strong seller. Barnard
  • LeeBoy’s strong future, through Tier 4 Final investment
    March 20, 2019
    LeeBoy is seeing strong sales for its road machines at the moment, particularly in the US. And the firm’s early investment in fitting Tier 4 Final compliant engines has played a significant role Christopher Barnard is CEO of LeeBoy and commented, “The US has been strong. Demand is there and the infrastructure spending is there. It’s a good market. In our segment for commercial paving we’re doing very well.” The paver range is selling well and the firm’s 8520 model is a particularly strong seller. Barnard
  • RMD’s Hong Kong highway project
    June 13, 2012
    RMD Kwikform has supplied its 80kN Rapidshor shoring for the widening of the Tolo Highway, running between the Island House Interchange and Tai Hang in Hong Kong. The project, overseen by main contractor Gammon Construction and set to be completed by the end of 2013, will widen the Tolo Highway from a two to four-lane carriageway in each direction, alleviating traffic congestion. “We were approached by [project] sub-contractors, United Soundfair and Richwell Engineering to supply shoring and formwork suppor
  • Sandvik’s DT1131i jumbo and iSURE software in Iceland and Norway
    August 14, 2019
    Sandvik’s DT1131i three-boom, electro-hydraulic jumbo, iSURE tunnel management software and the latest drill bit hardware were recently put to the test in Iceland and Norway* Czech contractor Metrostav recently achieved 105m of tunnel excavation in a record-breaking six days. But it will be consistent performance and progress that will see Iceland’s Dyrafjordurgong Tunnel in the remote Westfjords region open on time and on budget. The 5.3km Dyrafjordurgong Tunnel is costing around €69 million and due