Skip to main content

Rapid replacement of multiple bridges – the plan

The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years. Using traditional forms of procurement this programme would be like
December 14, 2017 Read time: 6 mins
New repair techniques are being used to speed bridge improvements
The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes


It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, 4907 PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years.

Using traditional forms of procurement this programme would be likely to take 10-15 years. PennDOT has speeded the whole process up by bundling all the bridges together and letting them under one US$899 million public private partnership (PPP or 3P) deal. What makes this 3P project unusual is the size of the bridges – they are all small, many of them in rural locations.

The authority calculates that whereas the design, construction and maintenance of the bridges over a 25-year period would normally cost around $2 million/bridge, this route cuts that figure to $1.4 million.

“A lot of that saving comes from the economies of scale that the private sector can bring to a bundled project like this,” according to PennDOT’s 3P director Mike Bonini, “including standardisation, the use of prefabricated elements and being able to mobilise construction units and move them from one bridge to another.”

PennDOT awarded the contract to Plenary Walsh Keystone Partners (PWKP) in 2015, having shortlisted four consortia drawn from bidders who came from around the world. The winning consortium comprises of Plenary Group and 8631 Walsh Investors who will finance and manage the concession, lead designer HDR, Walsh/Granite JV as lead contractor and Walsh Infrastructure Management which will provide maintenance.

Pennsylvania has the third-largest number of bridges of all the states in the US. Around 4,200 of its 25,000 bridges are structurally deficient. This does not mean that they are unsafe, rather that they need upgrading.

When selecting the 558 bridges that have gone into this package, PennDOT looked at over 2,000 structurally deficient bridges, selecting ones with similar characteristics. All the bridges are either single, or two-lane structures on smaller state highways. “The project goes to the heart of our mission to provide a sustainable transport system for all of Pennsylvania and the businesses that power the economy,” said Bonini.


PennDOT’s other bridges are being repaired under more traditional means, said Bonini. “The State still has the traditional highway and bridge delivery programme. We are working with each district office and planning partners to help to continue the number of bridges that have to be replaced every year.”

Once PWKP has replaced each bridge, it must maintain it for 25 years, although certain elements will become the responsibility of PennDOT sooner. The transport authority takes over snow ploughing, line-painting and debris pick-up immediately a structure is substantially complete; vegetation after a year; and the flexible pavement overlay goes back to the state after five years.

Pennsylvania’s P3 law came into play in 2012. The payment terms for the rapid replacement bridge programme involve PennDOT making a one-time mobilisation payment to PWKP at the start of the project, with milestone payments during the design and construction phases. Through the maintenance period, it will make availability payments, tied to certain performance metrics.

Steady progress


To get the ball rolling on the replacement programme, PennDOT selected batches of bridges in two regions for early completion, securing right-of-way and permitting approvals – processes that PWKP is carrying out for the bulk of the 558 bridges. As of mid-September 2017, 285 bridges had been replaced and were open to traffic, 102 were under construction, with a further 25 scheduled for construction before the turn of the year, leaving nearly 150 for next year.

The biggest challenge of the Rapid Bridge Replacement Programme is the organisation, said Bonini. “You could say this is more of a logistics project rather than a bridge-building exercise.”

PWKP is using project management software called e-Builder to help coordinate the design and construction activities. PennDOT has drafted in consultant support to its design team to help carry out the checking and approval activities required for each bridge. There will be around 15,000 submissions related to the design and approval process, and none of the deadlines linked to each submission has been missed, according to Bonini.

PWKP is employing 45 contractors to carry out the work alongside Walsh/Granite, with the programme divided into three regions – West, Central and East – each managed by operations and logistics personnel. “We have daily and weekly planning and coordination meetings in each region to keep the projects moving towards completion,” said PWKP spokesperson Rory McGlasson.  “We also have a co-located management team in Harrisburg to deal directly with PennDOT as issues arise so they are resolved in a timely manner.”


The 3P procurement route is allowing some innovative approaches to construction to be employed in Pennsylvania, among them the use of polyester polymer concrete (PCC) for the surfaces of the bridge decks.

“Typically we would not bid a bridge with the need to use polyester polymer concrete because of the cost,” said Bonini. “They have brought this to Pennsylvania and we are anxious to see how it works in the long term. We know the technology has been used in California and elsewhere but our climate is different: we get the benefit of all four seasons here. This gives us the ability to experiment and see if this PPC overlay works for us.”

Contractor Walsh/Granite is employing standardisation and prefabrication to help meet the rapid replacement schedule. Precast concrete elements such as box beams, girders and box culverts account for a large proportion of the bridge structures.

Walsh/Granite is also using new technologies on a limited basis, according to McGlasson. These include folded steel plate girder bridges and ‘bridge in a backpack’. Developed by the 1507 University of Maine, and named because the elements are easy to transport, the ‘bridge in a backpack’ concept sees lightweight carbon-fibre tube arches filled with concrete on site.

It has not all been plain-sailing to date, said Bonini, with ‘typical construction problems’ along the way. However, PWKP has a good system for sharing problems encountered so that they do not re-occur at other locations, he insists.

Though PennDOT has not employed this type of P3 deal for other packages of bridges, it is employing it on a programme to design and construct 29 compressed natural gas filling stations around the state. Northampton County in the Eastern part of Pennsylvania is also using the same model on a 28-bridge replacement programme for structures owned and maintained at county level.

“The project has received national recognition and other states are looking at the model to determine whether it would be effective for them to use to replace some of their structurally deficient bridges,” said Bonini.

For more information on companies in this article

Related Content

  • “Structurally deficient” US bridges need warning signs, says ARTBA
    April 10, 2015
    A US construction sector group wants warning signs to be posted on bridges designated “structurally deficient" and in need of repair by state engineers. More than 61,000 structurally deficient bridges remain in need of significant repair, according to the American Road & Transportation Builders Association (ARTBA), which analysed the US Department of Transport’s National Bridge Inventory database. However, by the end of 2014 there were more than 2,000 fewer structurally deficient structures than in 20
  • Kenya rehabilitates, widens, tolls Northern Corridor
    November 8, 2017
    A massive highway project in Kenya will boost transport for the country as well as its neighbours - Shem Oirere reports. Kenya has commenced the process of rehabilitating, expanding and tolling of 657km of East Africa’s Northern Corridor that is anchored on the Indian Ocean port of Mombasa and which links the gateway with landlocked countries of Uganda, Rwanda, Burundi and parts of eastern Democratic Republic of Congo (DRC).
  • The Fehmarnbelt Tunnel, another Danish connection
    June 20, 2017
    The Fehmarnbelt Tunnel between Denmark and Germany is both ambitious and innovative, explains Susanne Kalmar Pedersen, project director at design engineering firm Ramboll, adviser to the client Fehmarn A/S. The ambitious Fehmarnbelt Tunnel - one of Europe’s largest ongoing infrastructure projects - is a priority project within the EU’s Trans European Network (TEN-T) programme. It will link the German island of Fehmarn with the Danish island of Lolland. The tunnel is an 18km immersed combined road and rail l
  • Trimble’s innovation with new technology
    January 11, 2019
    Trimble is developing highly advanced technologies for the construction and quarrying sectors – Mike Woof writes Trimble is working on a number of highly innovative technologies that could revolutionise the construction and aggregates production sectors. Perhaps the most eye-catching of all of these innovations is for the autonomous compactor and dozer system Trimble is in the process of developing at present. Scott Crozier is general manager of Trimble’s general construction division. He said that whi