Rapid replacement of multiple bridges – the plan

The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years. Using traditional forms of procurement this programme would be like
December 14, 2017 Read time: 6 mins
New repair techniques are being used to speed bridge improvements
The US State of Pennsylvania is saving itself $220 million over 10 years on a programme to replace 558 bridges with an unusual public private partnership approach - Kristina Smith writes


It is called the Rapid Bridge Replacement Programme with good reason. Pennsylvania’s Department of Transport, 4907 PennDOT, wants to see no less than 558 structurally deficient bridges replaced with newly designed and constructed ones, all within four years.

Using traditional forms of procurement this programme would be likely to take 10-15 years. PennDOT has speeded the whole process up by bundling all the bridges together and letting them under one US$899 million public private partnership (PPP or 3P) deal. What makes this 3P project unusual is the size of the bridges – they are all small, many of them in rural locations.

The authority calculates that whereas the design, construction and maintenance of the bridges over a 25-year period would normally cost around $2 million/bridge, this route cuts that figure to $1.4 million.

“A lot of that saving comes from the economies of scale that the private sector can bring to a bundled project like this,” according to PennDOT’s 3P director Mike Bonini, “including standardisation, the use of prefabricated elements and being able to mobilise construction units and move them from one bridge to another.”

PennDOT awarded the contract to Plenary Walsh Keystone Partners (PWKP) in 2015, having shortlisted four consortia drawn from bidders who came from around the world. The winning consortium comprises of Plenary Group and 8631 Walsh Investors who will finance and manage the concession, lead designer HDR, Walsh/Granite JV as lead contractor and Walsh Infrastructure Management which will provide maintenance.

Pennsylvania has the third-largest number of bridges of all the states in the US. Around 4,200 of its 25,000 bridges are structurally deficient. This does not mean that they are unsafe, rather that they need upgrading.

When selecting the 558 bridges that have gone into this package, PennDOT looked at over 2,000 structurally deficient bridges, selecting ones with similar characteristics. All the bridges are either single, or two-lane structures on smaller state highways. “The project goes to the heart of our mission to provide a sustainable transport system for all of Pennsylvania and the businesses that power the economy,” said Bonini.


PennDOT’s other bridges are being repaired under more traditional means, said Bonini. “The State still has the traditional highway and bridge delivery programme. We are working with each district office and planning partners to help to continue the number of bridges that have to be replaced every year.”

Once PWKP has replaced each bridge, it must maintain it for 25 years, although certain elements will become the responsibility of PennDOT sooner. The transport authority takes over snow ploughing, line-painting and debris pick-up immediately a structure is substantially complete; vegetation after a year; and the flexible pavement overlay goes back to the state after five years.

Pennsylvania’s P3 law came into play in 2012. The payment terms for the rapid replacement bridge programme involve PennDOT making a one-time mobilisation payment to PWKP at the start of the project, with milestone payments during the design and construction phases. Through the maintenance period, it will make availability payments, tied to certain performance metrics.

Steady progress


To get the ball rolling on the replacement programme, PennDOT selected batches of bridges in two regions for early completion, securing right-of-way and permitting approvals – processes that PWKP is carrying out for the bulk of the 558 bridges. As of mid-September 2017, 285 bridges had been replaced and were open to traffic, 102 were under construction, with a further 25 scheduled for construction before the turn of the year, leaving nearly 150 for next year.

The biggest challenge of the Rapid Bridge Replacement Programme is the organisation, said Bonini. “You could say this is more of a logistics project rather than a bridge-building exercise.”

PWKP is using project management software called e-Builder to help coordinate the design and construction activities. PennDOT has drafted in consultant support to its design team to help carry out the checking and approval activities required for each bridge. There will be around 15,000 submissions related to the design and approval process, and none of the deadlines linked to each submission has been missed, according to Bonini.

PWKP is employing 45 contractors to carry out the work alongside Walsh/Granite, with the programme divided into three regions – West, Central and East – each managed by operations and logistics personnel. “We have daily and weekly planning and coordination meetings in each region to keep the projects moving towards completion,” said PWKP spokesperson Rory McGlasson.  “We also have a co-located management team in Harrisburg to deal directly with PennDOT as issues arise so they are resolved in a timely manner.”


The 3P procurement route is allowing some innovative approaches to construction to be employed in Pennsylvania, among them the use of polyester polymer concrete (PCC) for the surfaces of the bridge decks.

“Typically we would not bid a bridge with the need to use polyester polymer concrete because of the cost,” said Bonini. “They have brought this to Pennsylvania and we are anxious to see how it works in the long term. We know the technology has been used in California and elsewhere but our climate is different: we get the benefit of all four seasons here. This gives us the ability to experiment and see if this PPC overlay works for us.”

Contractor Walsh/Granite is employing standardisation and prefabrication to help meet the rapid replacement schedule. Precast concrete elements such as box beams, girders and box culverts account for a large proportion of the bridge structures.

Walsh/Granite is also using new technologies on a limited basis, according to McGlasson. These include folded steel plate girder bridges and ‘bridge in a backpack’. Developed by the 1507 University of Maine, and named because the elements are easy to transport, the ‘bridge in a backpack’ concept sees lightweight carbon-fibre tube arches filled with concrete on site.

It has not all been plain-sailing to date, said Bonini, with ‘typical construction problems’ along the way. However, PWKP has a good system for sharing problems encountered so that they do not re-occur at other locations, he insists.

Though PennDOT has not employed this type of P3 deal for other packages of bridges, it is employing it on a programme to design and construct 29 compressed natural gas filling stations around the state. Northampton County in the Eastern part of Pennsylvania is also using the same model on a 28-bridge replacement programme for structures owned and maintained at county level.

“The project has received national recognition and other states are looking at the model to determine whether it would be effective for them to use to replace some of their structurally deficient bridges,” said Bonini.

For more information on companies in this article

Related Content

  • Attitude is key to sustainability, says Volvo CE’s Thomas Bitter
    June 27, 2018
    Whether you are in the global Volvo Ocean Race or working on-site locally, sustainability is about attitude as much as technology. David Arminas reports. Technology, sustainability and safety. We ignore these often related themes at our peril. This was the key point made by Volvo Group chief executive Martin Lundstedt during his brief opening presentation at the start of the Building Tomorrow Conference in Spain last October. The conference took place within the harbour of Alicante that was bustling wit
  • Automated testing is safer, cheaper and more thorough
    May 10, 2019
    New tests for cracking and rutting are easy to perform, use existing equipment and work well on mixes with different binders and recycled content - Kristina Smith writes Researchers at the Texas A&M Transportation Institute (TTI) have developed new tests for cracking and rutting, designed to be quick and easy to carry out, using existing laboratory equipment. The most advanced of these is the IDEAL Cracking Test (IDEAL-CT), which could be appearing in specifications in some of the US states in around six
  • Cats eyes from Clearview set the tone at Switch Island in the UK
    February 23, 2018
    Cats eyes, which light up in response to changing traffic lights, will be used for the first time in the UK at a motorway junction. Highways England, the government agency, is installing around 170 of the LED road studs at Switch Island, one of England’s busiest motorway junctions – used by over 90,000 vehicles every day. Installation is expected to take around a year to complete.
  • ACE/AECOM report: private sector and user-pay for English roads
    May 14, 2018
    It’s one minute to midnight for funding England’s roads, according to a timely new report, and the clock’s big hand is pointing to some form of user-pay solution, reports David Arminas Is there any way out of future user-pay funding for England’s highway infrastructure? The answer is a resounding ‘no’, according to the recently published report: Funding Roads for the Future. The brief 25-page document by the London-based Association for Consultancy and Engineering, ACE**, sums up the state of England’s ro