Pumps vital for Stockholm tunnel

A major tunnel project in the Swedish capital Stockholm will mean that roads in a residential area will be safe from workmen repairing power cables. The tunnel will not be visible when completed, but its importance to the city's development is considerable. It means 10km of high voltage cable cutting through a residential area will be replaced with cables laid through the new tunnel, providing sufficient land for some 3,000 badly-needed new homes in an area divided down the middle by Lake Mälaren and the Ba
July 20, 2012 Read time: 4 mins

A major tunnel project in the Swedish capital Stockholm will mean that roads in a residential area will be safe from workmen repairing power cables.

The tunnel will not be visible when completed, but its importance to the city's development is considerable. It means 10km of high voltage cable cutting through a residential area will be replaced with cables laid through the new tunnel, providing sufficient land for some 3,000 badly-needed new homes in an area divided down the middle by Lake Mälaren and the Baltic Sea.

A critical factor in allowing their construction is the use of seven submersible pumps installed deep in the bedrock below south Stockholm to keep the Skanstull-Solbergavoltage tunnel dry: a pump breakdown would have serious consequences.

"We are working on five parallel fronts at the moment, enabling us to maintain a pace of around 80-100m/ week," explains Peter Ahlgren, Blasting Supervisor for Oden Anläggningsentreprenad's tunnel project.

Work started in 2007 and blasting is scheduled for completion by April 2010 when power company Fortum starts installation of the power cables (start-up of power supply is estimated to be 2011). The main contractor is Oden and the contract amount is for SEK335 million (approximately E35 million/US$47.8 million). The total length of the main tunnel is 6.3km, with an additional 800m of approach tunnels. The depth varies from 30 to 60m.

Two of the five tunnel fronts are blasted from the middle outwards by work teams and accessed via a subterranean transport tunnel.

"Without functioning pumps we can't work and the project would be immediately and adversely affected. It is very important for the pumps to work properly if we are to keep up to the schedule," continues Peter Ahlgren.

Wear and tear on the pumps, which have to pump out 300litres of water/minute during drilling, is considerable. Water near the drilling rig is full of drill cuttings, and its effect can be compared with a sort of liquid sandpaper which rubs constantly on the internal parts of the pumps.

Per-Åke Jägren from pump supplier 219 Grindex, specialists in submersible pumps for tough environments, said: "We are using two models from our latest pump series. These are especially strong and hard wearing and built to withstand these kinds of conditions. They incorporate an entirely new design, where the abrasives in the water are kept away from the sensitive parts of the pump. Our pumps have really been put to the test in this tunnel project, and have demonstrated that they can meet everything expected of them. Our own tests show that these pumps last three times longer in hard wear and tear situations like these. What we are witnessing here confirms our tests."

Water is pumped up from the lowest parts of the tunnel pipe 50m up to ground level. Pumps work in stages using sediment tanks along the way. The water is pumped from the drilling rig to a pump pit, then to the next intermediate station, containing the system's large sediment tank. At this point most of the remaining drill cuttings are separated from the water and the water pumped on upwards is mostly clean (samples are taken regularly to ensure municipal water regulations are obeyed).

Several Grindex Major and Master pumps are used in the tunnelling work. A Major N-pump can deliver more than 35litres/second (over than 2m³/minute) in tough environments and work continuously without monitoring. The Master H pump is capable of a delivery head in excess of 45m.

The pump closest to the drilling rig, a Grindex Master, is the unit exposed most to the drill cuttings in the water.

For more information on companies in this article

Related Content

  • Peri’s formwork and shoring solution for the “East End Crossing”
    July 6, 2016
    Pylons almost 90m high are a striking feature of a new cable-stayed East End Crossing bridge over the Ohio River in Louisville, Kentucky state in the US The pylons are characterised by their complex shapes and massive legs and cross beams. Peri provided a comprehensive overall concept for its construction – consisting of a planning solution with perfectly matched formwork, climbing, shoring and scaffolding systems along with extensive on-site support. With a Peri solution, the construction crew were a
  • Stockholm bypass contract awarded
    March 4, 2016
    The contract to build a new highway bypass and interchange in Stockholm has been awarded by the Swedish transport authority, Trafikverket. The work will be carried out by Züblin Scandinavia, the Swedish subsidiary of Ed Züblin, in partnership with STRABAG subsidiary STRABAG Sverige. The work involves building a 950m long section of highway, including a complex interchange and is worth some €76 million. The works being carried out by Züblin in the district of Akalla north of Stockholm include sheeting and sh
  • IRF conference tackles transport green targets
    July 4, 2012
    The IRF's 2nd conference on roads and the environment addressed key transport targets, Mike Woof reports Reducing the impact of the road transport sector as a whole was the focus of the IRF's 2nd Roads & Environment Conference. Opening the event, Jean Beauverd, chairman of the IRF in Geneva said, "Evidence of global warming is now unequivocal. Even if we were to stabilise the effects of CO2 emissions, the effects would continue for decades. Eco-friendly processes have not yet reached the full acceptance tha
  • Piling accurately with Trimble’s new tool
    June 10, 2019
    Trimble is offering a new system that can help to boost the quality of drilling and piling work. The firm’s new Groundworks Machine Control System has been developed as a streamlined machine control solution for drilling and piling operations that helps optimise productivity and quality. The firm claims that this highly sophisticated system allows contractors to carry out drilling and piling operations more quickly, safely and accurately than using conventional methods. “Engineered for ease of use, Trim