Progress delayed on Kenya's vital highway link

Kenya is investing in road developments , reports Shem Oirere. A multi-million dollar highway expansion project in Kenya's capital Nairobi may now be delayed for close to a year because of a huge underground network of water, electricity and communication pipes and cables that has slowed down construction works.
February 16, 2012 Read time: 4 mins
Construction work is underway at the Museum Hill portion of the project to upgrade a key highway link in Kenyan capital Nairobi

Kenya is investing in road developments, reports Shem Oirere

A multi-million dollar highway expansion project in Kenya's capital Nairobi may now be delayed for close to a year because of a huge underground network of water, electricity and communication pipes and cables that has slowed down construction works.

Design engineers have sought to slow the progress of the works on the US$300 million project to enable the relocation of the underground utility networks by Kenya's power utility firm, Kenya Power & Lighting Company (KPLC), water utility 1579 Nairobi Water and Sewerage Company (NWSC) and various telecommunication operators within the city of 4 million people.

The project has been split into three sections for ease of supervision and monitoring of construction works is being implemented by three Chinese companies; 1581 China Wu Yi, 1583 Synohydro and 1584 Sheng Li Engineering Construction Company. It involves expanding the highway from the current four lanes to eight and construction of modern flyovers, box culverts, interchanges, and standard pipe culverts. The highway, meant to be the first such modern highway in Eastern Africa, provides a vital link on the Trans-African Highway that connects Cairo in Egypt and Cape Town in South Africa. "There's a long way to go with the relocation of services but there is good progress," said Hari Ramesh of Consulting Engineering Services, one of the firms involved in the project, which was launched in April 2009.

"Most of the roads were two to four lanes and we are making them six to eight lanes, and a lot of these utilities were sitting on road reserves," Ramesh said.

in a notice carried by various daily newspapers in Nairobi both KPLC and the NWSC have assured they will hasten the re-location of the underground pipes and cables so as to enable the contractors proceed with construction according to the project's design.

The highway's design has equally presented serious challenges to the engineers who have identified the construction of an underpass and an overpass at the Museum Hill, Pangani and the Eastern Bypass junction as the most complex of the 50.4km long highway. The stretch of the road will have six lanes from the current four and a new forked flyover.

According to Kennedy Nyakuti, one of the project's design engineers, the construction works on this part of the stretch represent, "...the perfect engineer's nightmare." Design engineers have divided the 50.4km highway into three sections and each section will be worked by a different contractor of the three Chinese companies. The sections include Thika town-2720 Kenyatta University, Muthaiga roundabout- Uhuru Highway and Muthaiga Roundabout - Kenyatta University.

Works on the Muthaiga roundabout-Uhuru Highway involves $100 million arterial connections totaling 12.4km being constructed by China Wu Yi Company Limited. Specific works include expansion of the section of the highway from the current six lanes to eight, construction a four lane flyover. The contractor will also increase Murang'a road's lanes from the current four to six and build an underpass.

Section two of the highway project is on the 24km Thika town-Kenyatta University stretch being done by Shengli Engineering Construction Group Limited at a cost of $117.5 million. It includes the widening of the carriageway to six lanes, construction of a six lane flyover at Eastern Bypass and two underpasses.

The final stretch of the highway is the 14km Muthaiga roundabout-Kenyatta University section being constructed by Synohydro Corporation Limited at a cost of $107.5 million. This section is set to become the first high-speed superhighway in the city with between six to eight lanes "with limited access and exits" and involves the construction of an underpass, an interchange, flyovers and a subway.

The highway, a dual-carriageway road constructed to bitumen standard in the 1970s, carries around 70,000 vehicles/day, with one of the highest road accident incidents on the Kenyan road network. Over the past five years for example, the road has recorded 700 road accidents, with 227 of them being described by the Ministry of Transport as "fatal". The upgrade is necessary to improve safety and reduce the current congestion problem.

Financing for the project, which was initially slated for completion in July 2011, has been provided by the African Development Bank (AfDB). The bank has provided 63% of the total project costs while the 1638 Kenya Government has provided the remaining 37% with assistance from the 2719 Chinese Government. "This project financed to the tune of $190 million is the largest single operation ever financed by the concessionary arm of the 1586 African Development Bank, the African Development Fund," said Gilbert Mbesherubusa, the bank's Director for Infrastructure. The project has set other trends too. Recently Kenya floated the first ever Infrastructure Bond Programme as a source of long term financing for infrastructure development in eastern Africa's largest economy. Last year's infrastructure bond raised $552 million with $17.5 million going to the Nairobi-Thika Highway project.

Related Content

  • Bulgaria plans for operating road infrastructure
    February 21, 2012
    There is a lot of work to do on Bulgarian roads, but the government has plans to increase the length of highways built each year as Krasimir Krastanov reports. Bulgarian roads with a pavement make up 98.4% of all the country's roads, while 92.5% of them have an asphalt surface and 82.8% of them are able to carry 10tonnes/axle.
  • World Bank providing loan for key Kenyan roads
    October 9, 2012
    The World Bank is offering the Kenyan Government a loan worth nearly US$300 million to fund road projects. The lion’s share of the money will be used to construct a double decker road link in Kenyan capital Nairobi. The 30 year repayment loan will also feature a grace period of 10 years. The Kenyan Government will contribute a small sum to the project and will also be in charge of the tender process.
  • Winning formula for formwork
    July 19, 2012
    An unusual application of formwork took place recently in France, while formwork using one particular engineering construction kit was used for the first time in Poland. Guy Woodford reports An 80m long wild game underpass is an innovative feature of the Route Nationale 88 (RN 88) expansion in south-west France. For construction of the arched underpass tunnel, a PERI tunnel formwork carriage using VARIOKIT engineering construction kit was used. Thanks to the equipment’s easy handling, along with pre-assembl
  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)