Skip to main content

Progress delayed on Kenya's vital highway link

Kenya is investing in road developments , reports Shem Oirere. A multi-million dollar highway expansion project in Kenya's capital Nairobi may now be delayed for close to a year because of a huge underground network of water, electricity and communication pipes and cables that has slowed down construction works.
February 16, 2012 Read time: 4 mins
Construction work is underway at the Museum Hill portion of the project to upgrade a key highway link in Kenyan capital Nairobi

Kenya is investing in road developments, reports Shem Oirere

A multi-million dollar highway expansion project in Kenya's capital Nairobi may now be delayed for close to a year because of a huge underground network of water, electricity and communication pipes and cables that has slowed down construction works.

Design engineers have sought to slow the progress of the works on the US$300 million project to enable the relocation of the underground utility networks by Kenya's power utility firm, Kenya Power & Lighting Company (KPLC), water utility 1579 Nairobi Water and Sewerage Company (NWSC) and various telecommunication operators within the city of 4 million people.

The project has been split into three sections for ease of supervision and monitoring of construction works is being implemented by three Chinese companies; 1581 China Wu Yi, 1583 Synohydro and 1584 Sheng Li Engineering Construction Company. It involves expanding the highway from the current four lanes to eight and construction of modern flyovers, box culverts, interchanges, and standard pipe culverts. The highway, meant to be the first such modern highway in Eastern Africa, provides a vital link on the Trans-African Highway that connects Cairo in Egypt and Cape Town in South Africa. "There's a long way to go with the relocation of services but there is good progress," said Hari Ramesh of Consulting Engineering Services, one of the firms involved in the project, which was launched in April 2009.

"Most of the roads were two to four lanes and we are making them six to eight lanes, and a lot of these utilities were sitting on road reserves," Ramesh said.

in a notice carried by various daily newspapers in Nairobi both KPLC and the NWSC have assured they will hasten the re-location of the underground pipes and cables so as to enable the contractors proceed with construction according to the project's design.

The highway's design has equally presented serious challenges to the engineers who have identified the construction of an underpass and an overpass at the Museum Hill, Pangani and the Eastern Bypass junction as the most complex of the 50.4km long highway. The stretch of the road will have six lanes from the current four and a new forked flyover.

According to Kennedy Nyakuti, one of the project's design engineers, the construction works on this part of the stretch represent, "...the perfect engineer's nightmare." Design engineers have divided the 50.4km highway into three sections and each section will be worked by a different contractor of the three Chinese companies. The sections include Thika town-2720 Kenyatta University, Muthaiga roundabout- Uhuru Highway and Muthaiga Roundabout - Kenyatta University.

Works on the Muthaiga roundabout-Uhuru Highway involves $100 million arterial connections totaling 12.4km being constructed by China Wu Yi Company Limited. Specific works include expansion of the section of the highway from the current six lanes to eight, construction a four lane flyover. The contractor will also increase Murang'a road's lanes from the current four to six and build an underpass.

Section two of the highway project is on the 24km Thika town-Kenyatta University stretch being done by Shengli Engineering Construction Group Limited at a cost of $117.5 million. It includes the widening of the carriageway to six lanes, construction of a six lane flyover at Eastern Bypass and two underpasses.

The final stretch of the highway is the 14km Muthaiga roundabout-Kenyatta University section being constructed by Synohydro Corporation Limited at a cost of $107.5 million. This section is set to become the first high-speed superhighway in the city with between six to eight lanes "with limited access and exits" and involves the construction of an underpass, an interchange, flyovers and a subway.

The highway, a dual-carriageway road constructed to bitumen standard in the 1970s, carries around 70,000 vehicles/day, with one of the highest road accident incidents on the Kenyan road network. Over the past five years for example, the road has recorded 700 road accidents, with 227 of them being described by the Ministry of Transport as "fatal". The upgrade is necessary to improve safety and reduce the current congestion problem.

Financing for the project, which was initially slated for completion in July 2011, has been provided by the African Development Bank (AfDB). The bank has provided 63% of the total project costs while the 1638 Kenya Government has provided the remaining 37% with assistance from the 2719 Chinese Government. "This project financed to the tune of $190 million is the largest single operation ever financed by the concessionary arm of the 1586 African Development Bank, the African Development Fund," said Gilbert Mbesherubusa, the bank's Director for Infrastructure. The project has set other trends too. Recently Kenya floated the first ever Infrastructure Bond Programme as a source of long term financing for infrastructure development in eastern Africa's largest economy. Last year's infrastructure bond raised $552 million with $17.5 million going to the Nairobi-Thika Highway project.

Related Content

  • Vietnam’s North-South Expressway sections
    March 24, 2025
    Key sections of Vietnam’s North-South Expressway are nearly complete.
  • Norway’s record breaking undersea road tunnel
    February 25, 2015
    The world's deepest road tunnel is currently in construction near Stavanger in Norway but is only the prelude to even larger projects - report and photographs by Adrian Greeman. Norway's convoluted coastline of fjords and high mountains is famously scenic but also a major problem for transport and connections. The country has long experience of constructing tunnels as a result. Now a series of tunnels underway, or in design, around the oil industry city of Stavanger will stretch its skills more than usual.
  • Georgia's East-West Highway
    February 17, 2012
    One of the most important priorities of the Government of Georgia is the construction and rehabilitation of the East-West Highway in accordance with international standards.
  • Korea strategy
    February 6, 2012
    South Korea is setting an ambitious transport and infrastructure budget for 2010. The country intends to invest US$52.51 billion on projects for new roads and highways, as well as rail and port developments.