Pilosio and CMC Ravenna collaborate on Cornubia Interchange

The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange. The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal,
June 4, 2019 Read time: 4 mins
The Cornubia Boulevard Overpass is a 1.3km three-span, three-box, cast-in-situ concrete deck
The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange.


The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal, South Africa. It incorporates industrial, commercial, residential and open spaces.

Material supplied by 7163 Pilosio included its MP shoring, MP heavy-duty walls, Maximix modular formwork for decks and MP stairway access.

Pilosio studied and provided to CMC a custom-made system from a previous project in which the two companies had collaborated. The idea was to use a tried and tested system and exploit their assets. Competitors had offered other solutions that required non-reusable wooden ribs.

The Cornubia Boulevard Overpass is a 1.3km three-span, three-box, cast-in-situ concrete deck. Construction had to take place without interrupting the traffic flow of the highway. This led to the construction of large portholes above the highway to allow for the pre-assembling of formworks panels, installing of the rebars and deck casting operations in a complete safety process.

Another complexity for construction was that the viaduct has a longitudinal slope of 2.4°, a transversal slope of the cross section plus a pre-camber casting deck.

MP Heavy-duty support system was provided for porthole support in order to overpass the highway: HD Walls of 19.2m long and 12.27m high spanning a clearance of 16m and with a total load capacity of 1,451kN.

The deck and the wings of the bridge were poured on a plywood surface installed on a grid of secondary timber beams and main steel walings (double UPN100 profiles) formwork. The deck of the bridge was installed over supporting truss beams 150cm high and made of HE340A and double L-shaped beams, coupled by vertical braces. Adjustable foot plates, placed between the steel walings of the bridge deck and the trusses, allowed pre-camber to the casting.

The steel trusses were supported by steel beams placed over MP Heavy Duty towers. In the horizontal plane, the trusses were stiffened with tube and fittings, both on the upper and lower cords of the trusses. The stresses in the steel elements of main beams and the nodal reactions were obtained from a 3D FEM dedicated model of the structure, carried out with SAP2000 software. All static checks were done by Pilosio engineers according to EN 1993 Standard.

The foot plate extraction had to guarantee the transversal sloping of the cross section plus the pre-camber that allows the casting to have a horizontal bottom deck after dismantling the falsework. The pre-camber was obtained from a 3D FEM model of the supporting structure.

Sloping viaduct


The gross longitudinal sloping of the bridge of 2.4° was obtained with the inclination of the main trusses. The steel trusses were fixed on the left support of the portal (bolt connection) and were free to move horizontally on the right support. In this way, the horizontal actions due to sloping were applied, all on the left support - MP Heavy Duty support tower.

The MP Heavy Duty tower base jacks were fixed to the ground and braced to the lateral MP standard platform. This mitigated a tipping risk. As an alternative, cables or a ballast could be used.

As a temporary support platform, an MP Pilosio multidirectional shoring system fitted perfectly with all the site requirements. The support platforms were obtained by connecting square or rectangular modules together. Height variation between 6.5-12.7m was easily covered, thanks to the flexibility of the MP system. Two casting phases were performed. The first phase was the pouring of the bottom deck and the second phase was the pouring of the lateral vertical walls and upper slab with lateral wings.

For the deck casting, the builder chose Maximix, a formwork system made of wooden beams, steel beams and plywood panels that covers large surfaces and complex shapes with high capacity and limited weight. The capacity can be adapted to the requirements by varying the distance of the beams. Pilosio engineers created the design for the wooden deck.

Finally, Pilosio gave on-site assistance with training for assembling Maximix panels and provided shop drawings for each module. Typical designs often require an interpretation for the workers on-site. There was daily assistance for any problems during the assembly and installation of the MP towers to remedy any discrepancies detected on-site with respect to the measurements made previously.

For more information on companies in this article

Related Content

  • Geosynthetic drainage technology developments
    June 13, 2012
    An innovative solution to providing vital, low-impact surface water control for one of Britain’s largest local authority road schemes is said to have been recently achieved using Hydro International’s (HI) Hydro Vortex Drop Shaft  ow control technology. The new 7km bypass built by Costain at Church Village, near Pontypridd, South Wales, required careful planning to minimise its effect on the countryside and the local environment. Rhondda Cynon Taff Council needed to bypass Church Village to reduce traf c
  • Nigeria’s giant city Lagos to benefit from a new cable-stayed bridge
    September 19, 2012
    The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
  • Pilosio flies high with Flydeck
    January 17, 2023
    The Flydeck system from Pilosio simplifies and speeds up the assembly of suspended scaffolding and structures more safely.Importantly, because it is an under-bridge suspended system, there is no need to stop bridge traffic or close lanes. The system consists of 25cm or 45cm aluminium or steel lattice girders connected by patented pins and spring pins.
  • Brazil’s Serra do Cafezal Highway
    July 29, 2015
    Brazil's improved Mercosur route will boost capacity and cut travel time - Mauro Nogarin writes. The Régis Bittencourt Highway is one of the main access routes of the Mercosur traffic. It has a length of 400km and connects the main cities of São Paulo and Curitiba, which allows for products to enter from the southeast toward the rest of the southern part of Brazil and later transit to Argentina, Paraguay and Uruguay. Products also flow into Brazil from Mercosur through this major highway. The cost of the hi