Pilosio and CMC Ravenna collaborate on Cornubia Interchange

The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange. The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal,
June 4, 2019 Read time: 4 mins
The Cornubia Boulevard Overpass is a 1.3km three-span, three-box, cast-in-situ concrete deck
The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange.


The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal, South Africa. It incorporates industrial, commercial, residential and open spaces.

Material supplied by 7163 Pilosio included its MP shoring, MP heavy-duty walls, Maximix modular formwork for decks and MP stairway access.

Pilosio studied and provided to CMC a custom-made system from a previous project in which the two companies had collaborated. The idea was to use a tried and tested system and exploit their assets. Competitors had offered other solutions that required non-reusable wooden ribs.

The Cornubia Boulevard Overpass is a 1.3km three-span, three-box, cast-in-situ concrete deck. Construction had to take place without interrupting the traffic flow of the highway. This led to the construction of large portholes above the highway to allow for the pre-assembling of formworks panels, installing of the rebars and deck casting operations in a complete safety process.

Another complexity for construction was that the viaduct has a longitudinal slope of 2.4°, a transversal slope of the cross section plus a pre-camber casting deck.

MP Heavy-duty support system was provided for porthole support in order to overpass the highway: HD Walls of 19.2m long and 12.27m high spanning a clearance of 16m and with a total load capacity of 1,451kN.

The deck and the wings of the bridge were poured on a plywood surface installed on a grid of secondary timber beams and main steel walings (double UPN100 profiles) formwork. The deck of the bridge was installed over supporting truss beams 150cm high and made of HE340A and double L-shaped beams, coupled by vertical braces. Adjustable foot plates, placed between the steel walings of the bridge deck and the trusses, allowed pre-camber to the casting.

The steel trusses were supported by steel beams placed over MP Heavy Duty towers. In the horizontal plane, the trusses were stiffened with tube and fittings, both on the upper and lower cords of the trusses. The stresses in the steel elements of main beams and the nodal reactions were obtained from a 3D FEM dedicated model of the structure, carried out with SAP2000 software. All static checks were done by Pilosio engineers according to EN 1993 Standard.

The foot plate extraction had to guarantee the transversal sloping of the cross section plus the pre-camber that allows the casting to have a horizontal bottom deck after dismantling the falsework. The pre-camber was obtained from a 3D FEM model of the supporting structure.

Sloping viaduct


The gross longitudinal sloping of the bridge of 2.4° was obtained with the inclination of the main trusses. The steel trusses were fixed on the left support of the portal (bolt connection) and were free to move horizontally on the right support. In this way, the horizontal actions due to sloping were applied, all on the left support - MP Heavy Duty support tower.

The MP Heavy Duty tower base jacks were fixed to the ground and braced to the lateral MP standard platform. This mitigated a tipping risk. As an alternative, cables or a ballast could be used.

As a temporary support platform, an MP Pilosio multidirectional shoring system fitted perfectly with all the site requirements. The support platforms were obtained by connecting square or rectangular modules together. Height variation between 6.5-12.7m was easily covered, thanks to the flexibility of the MP system. Two casting phases were performed. The first phase was the pouring of the bottom deck and the second phase was the pouring of the lateral vertical walls and upper slab with lateral wings.

For the deck casting, the builder chose Maximix, a formwork system made of wooden beams, steel beams and plywood panels that covers large surfaces and complex shapes with high capacity and limited weight. The capacity can be adapted to the requirements by varying the distance of the beams. Pilosio engineers created the design for the wooden deck.

Finally, Pilosio gave on-site assistance with training for assembling Maximix panels and provided shop drawings for each module. Typical designs often require an interpretation for the workers on-site. There was daily assistance for any problems during the assembly and installation of the MP towers to remedy any discrepancies detected on-site with respect to the measurements made previously.

For more information on companies in this article

Related Content

  • HEXAGON LIVE - making the digital world become a reality
    June 3, 2015
    HEXAGON LIVE - the digital world becomes reality. Everyone in the construction and infrastructure maintenance sector faces the same great challenge - create reality with design through efficiency. But, as designs become more complex, how to gain efficiency is the real trick. These challenges are overcome only by people dedicated to solving problems. That puts them among the world’s innovators, said Ola Rollen, chief executive of technology information company Hexagon, during his welcoming keynote address to
  • Lighting innovations boosting brightness, cutting costs
    January 27, 2014
    CU Phosco’s new P850 LED main road lantern has just seen its first major deployment – between Junctions 16 and 17 of the A55, a strategic road which skirts the North Wales coastline – Jason Barnes reports The A55 is a grade-separated dual carriageway also known as the North Wales Expressway. Some 139km long, it originally ran from Chester to Bangor but was extended across the Isle of Anglesey into Holyhead Docks in 2001 under a project part-funded by the European Union.
  • Dutch road widening benefits from 3D software
    February 24, 2012
    Modern software is stretching traditional design boundaries on a motorway widening in the Netherlands, reports Adrian Greeman There was a time when civil engineering and aesthetics did not mix too well, especially on roads. The artistic ideas of an architect did not blend with the stringent requirements of structure. But modern three-dimensional modelling software is helping this change. Design notions that might have been overly complicated in the past are now attainable with hi-tech analysis tools.
  • Crane assembly for Tibet excavator
    February 9, 2017
    A tough machine assembly operation at extreme altitude has been carried out by two cranes from XCMG The cranes were used to assist in the assembly of a large excavator needed to assist in production at an extraction operation in Tibet. Located at an altitude of no less than 5,400m on the very remote Mila Mountain, the extraction sites was aiming at upgrading its operations and boosting productivity with the addition of a new 100tonne class excavator. The two cranes, an XCT100 model and a QAY300A machi