Pilosio and CMC Ravenna collaborate on Cornubia Interchange

The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange. The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal,
June 4, 2019 Read time: 4 mins
The Cornubia Boulevard Overpass is a 1.3km three-span, three-box, cast-in-situ concrete deck
The South African branch of the Italian construction company CMC di Ravenna again teamed up with formwork specialist Pilosio to take advantage of Pilosio's solutions. This time it was for construction of a new bridge in the city of Durban, a project named N2/Cornubia Interchange.


The overpass will streamline traffic by linking the Umhlanga industrial zone with the Cornubia new development area Tongat. Cornubia is a multibillion rand integrated settlement near Umhlanga, north of Durban, in KwaZulu Natal, South Africa. It incorporates industrial, commercial, residential and open spaces.

Material supplied by 7163 Pilosio included its MP shoring, MP heavy-duty walls, Maximix modular formwork for decks and MP stairway access.

Pilosio studied and provided to CMC a custom-made system from a previous project in which the two companies had collaborated. The idea was to use a tried and tested system and exploit their assets. Competitors had offered other solutions that required non-reusable wooden ribs.

The Cornubia Boulevard Overpass is a 1.3km three-span, three-box, cast-in-situ concrete deck. Construction had to take place without interrupting the traffic flow of the highway. This led to the construction of large portholes above the highway to allow for the pre-assembling of formworks panels, installing of the rebars and deck casting operations in a complete safety process.

Another complexity for construction was that the viaduct has a longitudinal slope of 2.4°, a transversal slope of the cross section plus a pre-camber casting deck.

MP Heavy-duty support system was provided for porthole support in order to overpass the highway: HD Walls of 19.2m long and 12.27m high spanning a clearance of 16m and with a total load capacity of 1,451kN.

The deck and the wings of the bridge were poured on a plywood surface installed on a grid of secondary timber beams and main steel walings (double UPN100 profiles) formwork. The deck of the bridge was installed over supporting truss beams 150cm high and made of HE340A and double L-shaped beams, coupled by vertical braces. Adjustable foot plates, placed between the steel walings of the bridge deck and the trusses, allowed pre-camber to the casting.

The steel trusses were supported by steel beams placed over MP Heavy Duty towers. In the horizontal plane, the trusses were stiffened with tube and fittings, both on the upper and lower cords of the trusses. The stresses in the steel elements of main beams and the nodal reactions were obtained from a 3D FEM dedicated model of the structure, carried out with SAP2000 software. All static checks were done by Pilosio engineers according to EN 1993 Standard.

The foot plate extraction had to guarantee the transversal sloping of the cross section plus the pre-camber that allows the casting to have a horizontal bottom deck after dismantling the falsework. The pre-camber was obtained from a 3D FEM model of the supporting structure.

Sloping viaduct


The gross longitudinal sloping of the bridge of 2.4° was obtained with the inclination of the main trusses. The steel trusses were fixed on the left support of the portal (bolt connection) and were free to move horizontally on the right support. In this way, the horizontal actions due to sloping were applied, all on the left support - MP Heavy Duty support tower.

The MP Heavy Duty tower base jacks were fixed to the ground and braced to the lateral MP standard platform. This mitigated a tipping risk. As an alternative, cables or a ballast could be used.

As a temporary support platform, an MP Pilosio multidirectional shoring system fitted perfectly with all the site requirements. The support platforms were obtained by connecting square or rectangular modules together. Height variation between 6.5-12.7m was easily covered, thanks to the flexibility of the MP system. Two casting phases were performed. The first phase was the pouring of the bottom deck and the second phase was the pouring of the lateral vertical walls and upper slab with lateral wings.

For the deck casting, the builder chose Maximix, a formwork system made of wooden beams, steel beams and plywood panels that covers large surfaces and complex shapes with high capacity and limited weight. The capacity can be adapted to the requirements by varying the distance of the beams. Pilosio engineers created the design for the wooden deck.

Finally, Pilosio gave on-site assistance with training for assembling Maximix panels and provided shop drawings for each module. Typical designs often require an interpretation for the workers on-site. There was daily assistance for any problems during the assembly and installation of the MP towers to remedy any discrepancies detected on-site with respect to the measurements made previously.

For more information on companies in this article

Related Content

  • Further new European pavers were launched at bauma 2013
    May 30, 2013
    Earlier this year several manufacturers announced new European asphalt pavers being launched at bauma 2013, but more surprises were in store at the show - Mike Woof writes. At the beginning of 2013 a number of manufacturers revealed new asphalt pavers being launched at the bauma 2013 exhibition. BOMAG, Caterpillar, Vögele and Volvo CE all announced new asphalt pavers in the shape of the BF900, AP300D, -3 Series units and new wheeled P-6870C respectively. These machines were at the show and all attracted con
  • Potain’s new tower crane for global markets
    May 16, 2018
    Potain is launching its first hydraulic topless luffing jib crane, following tests on site with select dealers in Thailand, Australia and New Zealand. It is the first topless luffing jib model from Potain and its novel hydraulic technology is said to make it easier to assemble and faster to operate. Featuring new technology, the crane is said to combine the advantages of Potain’s MCR luffing jib cranes and MCT topless cranes. The machine is said to be straightforward to assemble and disassemble the crane
  • Barrier system offers containment, noise reduction
    May 24, 2012
    Italian firm Marcegaglia has developed a new range of steel road safety barriers that is said to be versatile and cost effective. The units meet containment levels N2 to H4 and can be specified for different options in terms of working width levels (W). The line-up includes a dedicated system for motorcyclist protection designed to be fitted to all existing guardrails, a new P4 energy absorbing terminal system for barriers and a renewed range of steel New Jersey barriers, with optional integrated noise prot
  • Turkey’s new Marmara Highway project
    June 8, 2017
    By the end of 2018, a shiny new strip of asphalt will skirt around Turkey’s largest city, Istanbul, providing a new transport connection.