Piling for a road project in tough conditions

Machines from Liebherr have been brought in to carry out a piling job in Colombia in tough conditions. The road network between Mosquera and Balsillas is being upgraded at a cost of some US$199.15 million. Mosquera lies on the outskirts of the capital, Bogotá, while Balsillas is to the south-west and close to the borders with Ecuador and Peru. Work started on the project to improve the 230km route in January 2016 and is expected to take until December 2021 to complete. One of the contractors involved in th
January 11, 2019 Read time: 3 mins
The LRB 355 is said to deliver high performance even under difficult conditions

Machines from Liebherr have been brought in to carry out a piling job in Colombia in tough conditions. The road network between Mosquera and Balsillas is being upgraded at a cost of some US$199.15 million. Mosquera lies on the outskirts of the capital, Bogotá, while Balsillas is to the south-west and close to the borders with Ecuador and Peru.

Work started on the project to improve the 230km route in January 2016 and is expected to take until December 2021 to complete. One of the contractors involved in the project, Mincivil, is utilising deep foundation equipment from 718 Liebherr to help stabilise the ground conditions, which can be challenging in some of the sections along the route.

The ground conditions can be extremely hard, but in spite of this, the LB 36 and LRB 355 rigs are being used to drill 57,000m of piles and are said to be working productively and dependably.

The aim of this construction project is to improve the infrastructure links for freight traffic between Tolima Department and Cundinamarca Department. The work also involves the construction of 16 bridges, which will help to deliver an improved road link between Tolima and Cundinamarca.

Mincivil is working on the project with another contractor, Topco. To install the piles for the bridges, Mincivil is using the LB 36 and LRB 355 deep foundation machines supplied by Liebherr. The two piling machines are being used for Kelly drilling and full displacement drilling, depending on the specific requirements of each location.

Piles with diameters of 1.5m have been driven to depths of 26m by the LB 36 rig, using the Kelly drilling method. Meanwhile, 600mm diameter piles have been driven to depths of 33m using the LRB 355 piling and drilling rig utilising full displacement drilling equipment. By the end of the piling portion of the contract, the Columbian company will have drilled a total of 57,000m.

The project is substantial and forms part of Colombia’s national road development programme, currently underway. A portion of the upgrade work has already been completed and while the LB 36 finished its work in December 2017, the LRB 355 will be operating until March 2019.

The deep foundation specialist, Mincivil, is located in Cundinamarca, Antioquia and Boyacá. Daniel Rodriguez is Foundation Unit business manager. He said that at a part of the job in Mosquera, nearly an hour by car from Bogotá, the soil conditions have proven hard and challenging due to the nearby mountains. Rodriguez explained, “These are difficult conditions and a real challenge for the machine.”

However, he added that the machines have proven both productive and dependable in the application.

For more information on companies in this article

Related Content

  • Paso de las Leña tunnel between Argentina and Chile
    December 22, 2016
    A new tunnel between Chile and Argentina will boost trade and transport between the two countries - Mauro Nogarin writes The international Tunnel Paso Las Leñas will stretch 11.5km at 2,050m above sea level through the Andes. Once complete, it will greatly improve the connectivity and integration between the Chilean O'Higgins region with the Argentine Mendoza region.
  • What lies beneath Down Under
    January 11, 2021
    The third and final construction stage on Sydney’s WestConnex project has begun, including the underground Rozelle Interchange – with a lot of help from Komatsu
  • GPS machine control paves the way for Turkish canal
    February 7, 2012
    GPS machine control for earthworks and concrete paving is helping to fast track construction of an irrigation canal in Turkey - Claire Symes reports. The Turkish economy is expected to flourish as a result of construction of a new irrigation channel currently underway in the east of the country. This canal is benefiting from the latest concrete paving and earthmoving technology and will bring with it prosperity to a deprived area of the country. But the project is already taking the lead in terms of Turkish
  • Customised mill cuts costs
    October 14, 2015
    A special customised cold planer has saved costs and time for a US contractor. In the US, New York State Highway 243 has benefited from an innovative use of novel milling technology. This 17.75km east–west state highway is located in the Southern Tier of New York and has been carrying traffic since the 1930 renumbering of state highways in the state. The NY 243 has been a utilitarian divided highway that begins at an intersection with NY 98 in the town of Freedom and proceeds south-eastward across mostly ru