New bridge to replace old

Neckarauer overpass, a railroad bridge adjacent to the plant of German paving equipment manufacturer Vögele, is one of Mannheim's main traffic arteries. Built in 1936, the overpass represents an important link into the city for commuters coming from the south of the Rhine-Neckar region being used by some 60,000 vehicles/day, together with several tram lines running every five minutes. Corrosion has caused heavy damage to the steel girder bridge, and recently a 30km/hour speed limit has been in place along w
July 24, 2012 Read time: 2 mins
The Vögele SUPER 800 placed some 80tonnes of asphalt mix for the bridge access areas

Neckarauer overpass, a railroad bridge adjacent to the plant of German paving equipment manufacturer 1194 Vögele, is one of Mannheim's main traffic arteries.

Built in 1936, the overpass represents an important link into the city for commuters coming from the south of the Rhine-Neckar region being used by some 60,000 vehicles/day, together with several tram lines running every five minutes.

Corrosion has caused heavy damage to the steel girder bridge, and recently a 30km/hour speed limit has been in place along with a ban on vehicles over 16tonnes.

Planning for a new bridge has been finalised, but an important objective is to keep the Neckarau overpass open to traffic during the period scheduled for building the new structure.

In mid-2007, construction work for a provisional bridge began next to the old one. Part of this bridge reaches into the land of 364 Wirtgen Group company Joseph Vögele.

Construction company Achatz, as a local partner of the contractors for the New Neckarau Overpass, was awarded the contract to build the access areas for the bridge, carrying out asphalt surfacing and installing the tramway tracks.

 For asphalt paving, the company used a Vögele SUPER 800 and placed some 80tonnes of asphalt mix for the wearing course. Combined with an AB 200 Extending Screed in TV version, the small paver was said to be the ideal candidate for the job.

For more information on companies in this article

Related Content

  • Olbia Airport upgrade work
    September 16, 2020
    Equipment from the Fayat Group has played an important role in the revamping of a busy airport on the Italian island of Sardinia
  • Race track construction in Japan
    March 13, 2024

    Road construction machines from the Wirtgen Group have been used to build a new race track in Japan. Four Vögele asphalt pavers worked on the project to build a demanding circuit in a mountainous area in Japan.

    Tight corners and uphill gradients of up to 19% are features of the private racing circuit. Three Vögele pavers, a SUPER 1800-3i, a SUPER 1803-3i and a SUPER 1900-2, paved almost 100,000m2 in four layers, while a MT 3000-3i offset material feeder was also used to ensure efficiency and quality.

  • More on the Newmarket Viaduct replacement
    June 15, 2012
    When it was completed in 1965 – just six years after the Auckland Harbour Bridge – the six-lane Newmarket Viaduct with its tall, slender piers was something of an engineering wonder, the first of its kind in the Southern Hemisphere. Forty years on it had become a much-maligned contributor to Auckland’s chronic traffic congestion, too weak seismically to withstand the heaviest loaded trucks let alone a severe earthquake, so narrow in the shoulders that any accident stopped traffic flow and made it difficult
  • A road challenge for Zimbabwe
    November 8, 2023
    Construction work is finally underway for a major new highway link in Zimbabwe after many years of false starts.