Linking Kenya and Uganda with a new road project

An upgraded road link will improve transport between Uganda and Kenya - Shem Oirere reports Rainfall patterns and type of soil in an agricultural rich area shared by the neighbouring East African countries of Kenya and Uganda was a key consideration in arriving at the decision to upgrade to bitumen standards 73km of the 118km Kapchorwa-Kitale road that links the two countries. Initially, Uganda had proposed to have the road between Kapchorwa and Suam on its border with Kenya re-gravelled and widened to a
May 10, 2018 Read time: 4 mins
An asphalt surface is being used for the Uganda-Kenya road link as this is more resilient with regard to the heavy rains in the area
An upgraded road link will improve transport between Uganda and Kenya - Shem Oirere reports


Rainfall patterns and type of soil in an agricultural rich area shared by the neighbouring East African countries of Kenya and Uganda was a key consideration in arriving at the decision to upgrade to bitumen standards 73km of the 118km Kapchorwa-Kitale road that links the two countries. Initially, Uganda had proposed to have the road between Kapchorwa and Suam on its border with Kenya re-gravelled and widened to address transport problems in the area that runs north of Mount Elgon National Park through Kapchorwa, Kween and Bukwa districts.

“Despite the periodic maintenance operations by Uganda National Road Agency (UNRA), the existing gravel road seriously deteriorates and becomes impassable whenever it rains due to black soils,” said Uganda’s State minister for planning David Bahati. The Ugandan Government sought parliament’s approval of a US$105.7 million loan from the 1586 African Development Bank (AfDB) for the road project last year.

AfDB last year approved $147.3 million and $103.7 million for Kenya and Uganda respectively which is equivalent to 89% and 88% of project financing for the countries. Kenya and Uganda are providing 11% and 12% of the project financing respectively.

Earlier, a brief on the project said widening and re-gravelling of the Kapchorwa-Suam stretch was not economically sustainable in terms of costs and the lifespan of the road. It also said the link “cannot effectively handle the predicted 15% annual traffic volume growth for the region with high economic potential.”

“Heavy rains ranging from 800mm to 1200mm which characterises the region will necessitate road re-gravelling every two years to maintain it in modest motorable condition,” the brief says.

“Re-gravelling will demand a frequent maintenance regime and high volumes of murram (gravel) which is not only scarce in the project area, but also whose acquisition poses the risk of environmental deterioration and landscape/visual blight,” it adds.

Uganda has opted for a Class II paved road that entails upgrading the gravel road to asphalt concrete surface with a base course and sub-base layers.

In addition, the preferred contractor for the Kapchorwa-Suam section, who is yet to be announced, will rely on a road design with improved geometric design of the existing alignment, drainage and safety conditions according to UNRA.

UNRA says the two-lane road will be 3.5m wide with boulder width of 1.5m and a parking lane and footpath on either side of 2.5m and 1.5m wide respectively.

If completed according to schedule and design, the road’s first maintenance will be in 2033. The road upgrading includes improved back benched and grassed embankment to mitigate the effects of possible slope failure and any likely landslides.

On the Kenyan side, 18km of the 45km earmarked for upgrading is currently of bitumen standard but in very poor condition, while the other 27km stretch is a flat and rolling gravel alignment crossing rivers Kaibei, Mubere and Suam that require an asphalt concrete surface for the first time.

5711 China State Construction Engineering Corporation has been picked by the 2639 Kenya National Highways Authority (KeNHA) as the preferred contractor for the Kenya side of the project. The firm will build a dual carriageway to address the congestion and heavy vehicle traffic. However, the upgraded road will follow the existing road corridor.

At Eldoret, the contractor will construction a 32km road bypass to divert traffic from the town’s A104 stretch, which is part of the Northern Corridor that links the port of Mombasa to Uganda, Rwanda, Burundi, South Sudan and eastern Democratic Republic of Congo. The bypass is a 7m-wide single carriageway with 2m-wide shoulders on either side. Three junctions, an overpass and a rail bridge are key features of the Eldoret bypass.

A trumpet junction will be built over A104 at Cheplaskei while a half clover one with a loop over C39 will be constructed at Kapsaret.

The contractor will also build an overpass running over the new bypass at Simat, a road-rail bridge on the existing railway line and a full clover junction with loops over A104 at Leseru.

At both Kapsaret and Leseru, the contractor will construct two truck parking lots close the interchanges.

The entire Kapchorwa-Kitale road project, although being implemented separately by Kenya and Uganda, is expected to be completed in 2021, reducing travel time by 50%.

According to the project brief the design of the upgraded road “will minimise accident risks by speed calming measures and appropriate and clear road signage.”

Part of the project includes refurbishment of dilapidated post-crash care centre and procurement of an ambulance and theatre equipment to boost the road safety emergency response whenever there is a road crash.

The Kapchorwa-Kitale project is considered vital in the integration of the East African economies under the East African Community.

Related Content

  • Uganda’s new highway project revealed
    January 11, 2017
    Plans are being drawn up in Uganda for the upgrading of the Busega-Mpigi highway stretch. Funding worth US$151 million to help pay for the project is being sought from the African Development Bank (AfDB), which is being delivered in the shape of a loan. Busega lies on the eastern outskirts of capital Kampala and upgrading this 24km section of highway is necessary as it is suffers congestion at peak periods and is unable to cope with current traffic demands. Included in the work to improve this section of hi
  • Uganda’s capital Kampala needs road repairs
    March 8, 2021
    Uganda’s capital Kampala needs to repair its road network.
  • Uganda road projects funding sought
    February 6, 2017
    The Ugandan Government has unveiled plans to improve its road connections with its northern neighbour South Sudan. To fund the construction project, the Ugandan Government has been seeking a loan worth US$210 million from the Islamic Development Bank (IDB). The terms of the loan arrangements have yet to be revealed however. The aim of the project is to improve the road link running through Rwekunye, Apac, Lira and Acholibur. Better transport links form part of a much wider programme of integration between E
  • Plans in hand for Uganda’s key highway upgrade
    July 25, 2014
    In Uganda planning is underway for the upgrade of the Kampala-Jinja route. Preparations are being made for a new tolled highway connecting with capital Kampala. The upgrade will see the route being widened with four lanes for much of the length, six lanes on the approach to Kampala and up to eight lanes where vehicle densities will be heaviest to carry the capital’s traffic. The construction work is expected to cost some US$74 million and the new link will connect with the existing Kampala-Entebbe highway.