Linking Kenya and Uganda with a new road project

An upgraded road link will improve transport between Uganda and Kenya - Shem Oirere reports Rainfall patterns and type of soil in an agricultural rich area shared by the neighbouring East African countries of Kenya and Uganda was a key consideration in arriving at the decision to upgrade to bitumen standards 73km of the 118km Kapchorwa-Kitale road that links the two countries. Initially, Uganda had proposed to have the road between Kapchorwa and Suam on its border with Kenya re-gravelled and widened to a
May 10, 2018 Read time: 4 mins
An asphalt surface is being used for the Uganda-Kenya road link as this is more resilient with regard to the heavy rains in the area
An upgraded road link will improve transport between Uganda and Kenya - Shem Oirere reports


Rainfall patterns and type of soil in an agricultural rich area shared by the neighbouring East African countries of Kenya and Uganda was a key consideration in arriving at the decision to upgrade to bitumen standards 73km of the 118km Kapchorwa-Kitale road that links the two countries. Initially, Uganda had proposed to have the road between Kapchorwa and Suam on its border with Kenya re-gravelled and widened to address transport problems in the area that runs north of Mount Elgon National Park through Kapchorwa, Kween and Bukwa districts.

“Despite the periodic maintenance operations by Uganda National Road Agency (UNRA), the existing gravel road seriously deteriorates and becomes impassable whenever it rains due to black soils,” said Uganda’s State minister for planning David Bahati. The Ugandan Government sought parliament’s approval of a US$105.7 million loan from the 1586 African Development Bank (AfDB) for the road project last year.

AfDB last year approved $147.3 million and $103.7 million for Kenya and Uganda respectively which is equivalent to 89% and 88% of project financing for the countries. Kenya and Uganda are providing 11% and 12% of the project financing respectively.

Earlier, a brief on the project said widening and re-gravelling of the Kapchorwa-Suam stretch was not economically sustainable in terms of costs and the lifespan of the road. It also said the link “cannot effectively handle the predicted 15% annual traffic volume growth for the region with high economic potential.”

“Heavy rains ranging from 800mm to 1200mm which characterises the region will necessitate road re-gravelling every two years to maintain it in modest motorable condition,” the brief says.

“Re-gravelling will demand a frequent maintenance regime and high volumes of murram (gravel) which is not only scarce in the project area, but also whose acquisition poses the risk of environmental deterioration and landscape/visual blight,” it adds.

Uganda has opted for a Class II paved road that entails upgrading the gravel road to asphalt concrete surface with a base course and sub-base layers.

In addition, the preferred contractor for the Kapchorwa-Suam section, who is yet to be announced, will rely on a road design with improved geometric design of the existing alignment, drainage and safety conditions according to UNRA.

UNRA says the two-lane road will be 3.5m wide with boulder width of 1.5m and a parking lane and footpath on either side of 2.5m and 1.5m wide respectively.

If completed according to schedule and design, the road’s first maintenance will be in 2033. The road upgrading includes improved back benched and grassed embankment to mitigate the effects of possible slope failure and any likely landslides.

On the Kenyan side, 18km of the 45km earmarked for upgrading is currently of bitumen standard but in very poor condition, while the other 27km stretch is a flat and rolling gravel alignment crossing rivers Kaibei, Mubere and Suam that require an asphalt concrete surface for the first time.

5711 China State Construction Engineering Corporation has been picked by the 2639 Kenya National Highways Authority (KeNHA) as the preferred contractor for the Kenya side of the project. The firm will build a dual carriageway to address the congestion and heavy vehicle traffic. However, the upgraded road will follow the existing road corridor.

At Eldoret, the contractor will construction a 32km road bypass to divert traffic from the town’s A104 stretch, which is part of the Northern Corridor that links the port of Mombasa to Uganda, Rwanda, Burundi, South Sudan and eastern Democratic Republic of Congo. The bypass is a 7m-wide single carriageway with 2m-wide shoulders on either side. Three junctions, an overpass and a rail bridge are key features of the Eldoret bypass.

A trumpet junction will be built over A104 at Cheplaskei while a half clover one with a loop over C39 will be constructed at Kapsaret.

The contractor will also build an overpass running over the new bypass at Simat, a road-rail bridge on the existing railway line and a full clover junction with loops over A104 at Leseru.

At both Kapsaret and Leseru, the contractor will construct two truck parking lots close the interchanges.

The entire Kapchorwa-Kitale road project, although being implemented separately by Kenya and Uganda, is expected to be completed in 2021, reducing travel time by 50%.

According to the project brief the design of the upgraded road “will minimise accident risks by speed calming measures and appropriate and clear road signage.”

Part of the project includes refurbishment of dilapidated post-crash care centre and procurement of an ambulance and theatre equipment to boost the road safety emergency response whenever there is a road crash.

The Kapchorwa-Kitale project is considered vital in the integration of the East African economies under the East African Community.

Related Content

  • New Argentina highway construction work
    January 11, 2019
    Construction is underway for Argentina’s new Mendoza-San Juan Highway – Mauro Nogarin reports The rehabilitation and maintenance works of more than 3,300km of routes is now underway in Argentina. This followed on after the takeover of six new road corridors under the Public-Private Partnership (PPP) model, which took place in August 2018. The rehabilitation and maintenance works are being carried out prior to the start of the main projects, which will include the construction of highways. Building the
  • Challenges of NMT in Nairobi, Dar es Salaam
    September 13, 2016
    Developing safety for non-motorised transport in East Africa - Shem Oirere writes. Despite increasing national budgetary allocations for the road sector in recent years, governments in East Africa have made very low investments in non-motorised transport (NMT). This is despite the fact that both Kenya and Uganda have recently passed a policy on pedestrian and cycling safety. In Kenya, the County government of Nairobi, the country’s capital, has embraced a NMT policy, while in Uganda the government has passe
  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas
  • East Africa’s massive infrastructure development programme
    September 23, 2016
    A massive programme of infrastructure development is planned for East Africa that will help develop transport links and boost economic development. The projects will be implemented in Ethiopia, Kenya, South Sudan and Uganda. Roads and highways will be built and upgraded while new port facilities will be built. Also included in the programme will be an oil pipeline, rail links and fibre-optic cable installation. In all the Lamu Port-South Sudan-Ethiopia Transport (LAPSSET) Corridor project for East Africa wi