Lanes removes 400tonnes of debris from flood-scheme tunnel in UK

It was “dirty work” for drainage engineers from Lanes Group in the UK when they recently removed 400tonnes of silt and debris from a culvert in northern England. Before sludge removal started, the 3m-wide concrete box culvert under the A38 on the outskirts of the city of Derby had been full almost to its roof. Lanes Group's East Midlands depot, based in Derby, desilted the culvert in a 17-day operation for North Midland Construction, working for Highways England, under its civil engineering framework.
March 28, 2017 Read time: 3 mins
Now you see it, now you don’t: 400tonnes of silt removed
It was “dirty work” for drainage engineers from Lanes Group in the UK when they recently removed 400tonnes of silt and debris from a culvert in northern England.

Before sludge removal started, the 3m-wide concrete box culvert under the A38 on the outskirts of the city of Derby had been full almost to its roof.

7891 Lanes Group's East Midlands depot, based in Derby, desilted the culvert in a 17-day operation for North Midland Construction, working for 8100 Highways England, under its civil engineering framework. Prevention of localised flooding is a key component of Highway England'sfi ve-year road maintenance programmes up to 2021.

Highways England commissioned the culvert clearance work to optimise flood resilience along the stretch of A38 next to Derby's 84-hectare Markeaton Park, the most popular municipal recreation area in the Derby vicinity.

The 60m-long culvert was built in 1977 to route a water course called Bramble Brook, which leads from a large lake in Markeaton Park, under the nearby A38 dual carriageway.

North Midland Construction Project Manager Paul Devine acknowledged that is was “hard and dirty” work. “Much of it had to be done by hand but their ‘confined space working’ health and safety measures were spot on.”

Samples of the in situ silt were first scientifically tested to assess potential toxicity. North Midland Construction built two temporary dams at the upstream and downstream ends of the culvert to retain the water flow during the works. Excess water was managed using 150mm water pumps.

A substantial amount of mobilisation work was also carried out to prepare the working area. This included site security, tree trimming and construction of a 100m temporary road to the culvert to allow safe access for Lanes vehicles and protect utility assets under soft ground. A scaffold platform was also built to gain safe access to the mouth of the culvert.

Lanes then deployed seven drainage engineers and excavation operatives at any one time on the project, along with a powerful Superflex wet-dry vacuumation tanker and a jetvac tanker. Up to four Lanes employees worked in the culvert shovelling and raking silt into the Superflex's vacuumation hose.

Next, the material was over-pumped to the jet-vac tanker and taken away for disposal at an authorised waste site. Members of the confined space working team wore wet suits, rescue kits, gas monitors and harnesses, allowing them to work continuously. Throughout the operation, a specialist two-person rescue team monitored conditions inside the tunnel and also weather conditions. A supervisor managed a tag board recording details of all operatives below ground.

For more information on companies in this article

Related Content

  • Isle of Wight road stability scheme ‘first’ at Niton’s Undercliff
    February 19, 2014
    John Peck Construction has been awarded the contract to carry out the first major road stability scheme at Niton’s Undercliff on the Isle of Wight, England’s largest island. This project is part of a major programme of special geotechnical schemes being delivered by Island Roads (made up of VINCI Concessions, Meridiam Infrastructure and Ringway) under the Highways PFI to maintain the highway at locations prone to ground movement.
  • Highways England starts moving on projects for the eastern region
    September 30, 2015
    Highways England has met suppliers and stakeholders to discuss how it will spend more than €2.7 billion to improve roads across the East of England region in the next six years. The work is part of the government’s Road Investment Strategy to triple levels of spending on England’s roads by the end of the decade. Plans include major improvements on the M11, A5 and M1, A1(M), A12, A14, A47 and A428. Roads minister Andrew Jones said the investment is the largest in a generation.
  • Auckland’s causeway project
    April 4, 2014
    When it is finished in early 2017, the causeway on Auckland’s North-western Motorway, State Highway 16, will have been raised 1.5m to stop flooding at extreme high tides. There will be four lanes city-bound and four/five lanes westbound with dedicated bus lanes in each direction, and the existing North-western cycleway that runs alongside it will be upgraded.
  • Power, stability and control with new Case 8 WX Series
    January 21, 2013
    Case Construction Equipment has unveiled the first three models in an improved range of wheeled excavators: the WX148, WX168 and WX188. The machine trio are said to benefit from the power and performance of a three-pump hydraulic system, with a dedicated swing pump, a new engine speed/working mode selection dial, a heavy-duty undercarriage and an improved operator’s cab. The revisions are also said by Case to result in improved operator comfort and ease of operation, excellent service accessibility and redu