Composite bridge specialist falsework, Paraslim, from RMD Kwikform is being used to construct a viaduct and rail over-bridge in Wales. Paraslim is supporting the £35 million (US$55.7 million) A487 Porthmadog, Minffordd and Tremadog Bypass constructed by a joint venture partnership of Balfour Beatty and Jones Bros Civil Engineering UK.
February 27, 2012 Read time: 3 mins
RMD Kwikform’s Paraslim composite bridge solution used on the Porthmadog bypass viaduct

Composite bridge specialist falsework, Paraslim, from RMD Kwikform is being used to construct a viaduct and rail over-bridge in Wales.

Paraslim is supporting the £35 million (US$55.7 million) A487 Porthmadog, Minffordd and Tremadog Bypass constructed by a joint venture partnership of 1146 Balfour Beatty and 3265 Jones Bros Civil Engineering UK.

The 5.3km, two-lane bypass has eight bridge structures in total with 20 culverts. Two of the eight bridges are constructed using steel girders with a composite deck cast using Paraslim. A further three are constructed using precast beams and the remaining three are RC box and through girder structures.

With the variation of bridge construction methods and the tight programme to deliver the project in just 18 months, the selection of products to support the construction of the steel beam composite bridges was critical to stay ahead of programme.

JV structural sub-agent Steven Jones, said: “With a project of this nature you are always considering four key elements when it comes to product selection. The first and most important is the safety of workers and the use of safe equipment solutions. This is our number one focus, which supports our company-wide Zero Harm initiative. The second is cost effectiveness and quality, with the third being whether a product is truly fit for purpose. The final consideration is reliability and performance, in other words looking back at whether a product or solution has a track record of performing well on other similar projects.

“Having gone through this process and being familiar with the use of Paraslim on composite bridge work we have carried out in the past, we selected 319 RMD Kwikform to supply the equipment.”

The equipment also offered a safe access platform, complete with Ultraguard edge protection.
“For this particular job, this allows operatives to walk safely above water and, in the case of the second bridge, to work above a live tourist railway line, to clad the structure in local stone,” said Jones.

“From an operational perspective, the tight site in North Wales, which is relatively remote in terms of major infrastructure, leads to limited access for large-scale deliveries. Interfacing with the customer service team at RMD Kwikform allowed us to take advantage of its branch network and ability to time deliveries to site on a just-in-time basis.”

While the larger viaduct was cast, the smaller Welsh Highland Railway composite under-bridge was constructed using a Paraslim to span both Welsh Highland Heritage Railway and Welsh Highland Railway tracks, two very important and landmark tourist attractions for the region.

With the A487 due to be open soon, visitors to the region will be able to benefit from what is currently at peak times a very congested route.

For more information on companies in this article

Related Content

  • Doka’s fine form
    June 18, 2012
    Doka’s SKE50 automatic climbing formwork are being used on two suspension towers for a new multi-lane cable-stayed bridge alongside an older viaduct in Zaporozhye, south-east Ukraine. On completion, this large-scale infrastructure project is set to massively reduce the traffic burden on the existing bridge and significantly improve the daily traffic situation at what is a major river crossing. The two separate roadway slabs are cable-stayed off twin H-shaped suspension towers 150metres high. Lead project co
  • Tanzania’s work on East Africa’s multi-national road project
    November 28, 2022
    Tanzania is kick-starting construction work on the missing link in East Africa's multinational road
  • Long-lasting surface repairs for Avonmouth Bridge
    July 9, 2012
    Two technologies combined to give a heavily used bridge a new surface that should last for years The Avonmouth Bridge carries the M5 motorway over the River Avon, and is a vital part of the road infrastructure in south-west England, linking the counties of Somerset, Devon and Cornwall to the rest of the country. Completed in 1973, it carries commuters to the city of Bristol, and to South Wales, along with holidaymakers. The 1.4km long steel box girder bridge comprising a 16,000m2 steel decked central span a
  • Doka rises to the challenge on Turkey’s Eyiste Viaduct
    June 4, 2019
    Formwork specialist Doka recently rose to the challenge on Turkey’s Eyiste Viadust, the country’s highest bridge with piers up to 155m tall. The Eyiste Viaduct will be part of a route between Central Anatolia and Turkey’s Mediterranean region, shortening travel time between the cities of Konya and Alanya. Cantilever forming travellers and Doka’s automatic climbing formwork Xclimb 60 were part of the construction solution. The viaduct is nearly 1.4km long and carried by two abutments and eight piers, stret