Kwikform composite bridge formwork solution

Composite bridge specialist falsework, Paraslim, from RMD Kwikform is being used to construct a viaduct and rail over-bridge in Wales. Paraslim is supporting the £35 million (US$55.7 million) A487 Porthmadog, Minffordd and Tremadog Bypass constructed by a joint venture partnership of Balfour Beatty and Jones Bros Civil Engineering UK.
February 27, 2012 Read time: 3 mins
RMD Kwikform’s Paraslim composite bridge solution used on the Porthmadog bypass viaduct

Composite bridge specialist falsework, Paraslim, from RMD Kwikform is being used to construct a viaduct and rail over-bridge in Wales.

Paraslim is supporting the £35 million (US$55.7 million) A487 Porthmadog, Minffordd and Tremadog Bypass constructed by a joint venture partnership of 1146 Balfour Beatty and 3265 Jones Bros Civil Engineering UK.

The 5.3km, two-lane bypass has eight bridge structures in total with 20 culverts. Two of the eight bridges are constructed using steel girders with a composite deck cast using Paraslim. A further three are constructed using precast beams and the remaining three are RC box and through girder structures.

With the variation of bridge construction methods and the tight programme to deliver the project in just 18 months, the selection of products to support the construction of the steel beam composite bridges was critical to stay ahead of programme.

JV structural sub-agent Steven Jones, said: “With a project of this nature you are always considering four key elements when it comes to product selection. The first and most important is the safety of workers and the use of safe equipment solutions. This is our number one focus, which supports our company-wide Zero Harm initiative. The second is cost effectiveness and quality, with the third being whether a product is truly fit for purpose. The final consideration is reliability and performance, in other words looking back at whether a product or solution has a track record of performing well on other similar projects.

“Having gone through this process and being familiar with the use of Paraslim on composite bridge work we have carried out in the past, we selected 319 RMD Kwikform to supply the equipment.”

The equipment also offered a safe access platform, complete with Ultraguard edge protection.
“For this particular job, this allows operatives to walk safely above water and, in the case of the second bridge, to work above a live tourist railway line, to clad the structure in local stone,” said Jones.

“From an operational perspective, the tight site in North Wales, which is relatively remote in terms of major infrastructure, leads to limited access for large-scale deliveries. Interfacing with the customer service team at RMD Kwikform allowed us to take advantage of its branch network and ability to time deliveries to site on a just-in-time basis.”

While the larger viaduct was cast, the smaller Welsh Highland Railway composite under-bridge was constructed using a Paraslim to span both Welsh Highland Heritage Railway and Welsh Highland Railway tracks, two very important and landmark tourist attractions for the region.

With the A487 due to be open soon, visitors to the region will be able to benefit from what is currently at peak times a very congested route.

For more information on companies in this article

Related Content

  • New concrete testing technologies improve speed, safety and quality
    July 8, 2016
    Developments in data processing and management are revolutionising the way concrete strengths can be measured and used to improve efficiencies - Kristina Smith reports on two new technologies A new system that uses thermal imaging to measure the strength of sprayed concrete tunnel linings is being trialled for the first time in London. The brainchild of Dr Benoit Jones, managing director of Inbye Engineering, the technique could lead to improvements in safety, quality and – in the longer run – productivi
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.
  • First deck span completed for Mersey Gateway's north approach viaduct
    April 4, 2016
    The Mersey Gateway Project achieved another milestone as the first deck span for the elevated north approach viaduct was completed. Work started on site in May 2014 to build a six-lane toll bridge over the Mersey River between the towns of Runcorn and Widnes and opening is set for the autumn of 2017. As well as construction of the new bridge, works include the upgrading of 7km of highway to the north and south of the river - the main bridge is 2.2km long – and changing traffic flow so the majority of tra
  • Bridges in Sunderland and Poland are being slid into place
    February 6, 2017
    Sunderland sees a bridge slide into place and two bridges inch their way across a Polish highway Slowly but surely, a 2,500 tonne section of a new bridge deck was eased out from the banks of the River Wear near Sunderland in northern England. It now straddles the water, pointing towards the opposite bank which it will eventually reach after another sliding operation likely to take place next year. The project to build the New Wear Crossing is now halfway through with the first half of the steel deck b