High speed bridge demolition minimises disruption

A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.
February 16, 2012 Read time: 3 mins
Atlas Copco hydraulic equipment performed reliably during a 30 hour project to remove an old road bridge in southern Germany
A high speed bridge demolition project has been carried out successfully in Germany. Speed was of the essence as the bridge spanned an important road link and had to be removed in a tight time frame, minimising disruption to traffic.

The job formed part of a project for a new layout of the junction of the roads B297 and B29 close to Lorch in southern Germany. FWA Fischer Weilheim Abbruch was brought in by the Stuttgart Regional Council to demolish the old bridge carrying the B297 over the B29. The two-bay bridge structure was made of reinforced concrete and weighed 3,000 tonnes. During demolition work, damage caused to the closed section of Federal road had to be avoided at all cost.

The demolition job turned out to be difficult because the bridge not only featured a longitudinal and transverse slope, but also had a curve at a 280m radius to the horizontal. Slightly offset and some 15m below the bridge, a passage for local residents' vehicles had to be always accessible for rescue vehicles during the entire demolition period.

The only way to carry out the job was for the demolition to be undertaken during a set period when the roads could be closed, to minimise disruption and maximise safety.

Work started with the full closure of the roads, the removal of the crash barriers and the protection of the Federal road B29 using an impact bed made of material for subsequent recycling. This was followed by the demolition of the bridge carried out by the fleet of 178 Caterpillar machines consisting of a wheeled excavator and five crawler excavators equipped with hydraulic breakers and CombiCutters.

For its attachments FWA 2777 Fischer Weilheim used 161 Atlas Copco tools; a total of five model HB3000, HB4200 and HB7000 heavy hydraulic breakers which were supported by four model CC3300U, CC3300S and CC6000U CombiCutters.

As the two HB3000 hammers were breaking down the 300mm thick deck slab from above, the two CC3300U and the CC6000U CombiCutters started to reduce the bridge caps. Then the bottom chords with a cross sectional area of 4m2 of concrete were demolished by the two HB4200 hydraulic breakers and the HB 7000. Once the longitudinal reinforcements were accessible, they were cut by the CC3300S into lengths suitable for removal.

Once the entire bridge bay had been demolished, the CC6000U CombiCutter used its force and its 1.4m wide jaw to demolish the bridge abutments. The use of this large CombiCutter allowed the demolishers from Weilheim to tear down without major effort the one metre wide and heavily reinforced wing walls of the abutment. Afterwards the 7tonne hydraulic breaker was used to reduce the abutment to the ground.

According to the contractor the availability of the hydraulic tools more than met requirements. All five hydraulic attachments worked non-stop for 30 hours without problems.

Once the demolition work was complete the concrete was recycled on site for use in other road construction projects.

For more information on companies in this article

Related Content

  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b
  • Asphalt milling optimised by 3D controls
    February 20, 2012
    3D machine controls can optimise milling efficiency, Mike Woof reports. More efficient milling and recycling operations can be carried out by using the latest 3D control systems on the market. At the last Trimble Dimensions event in Las Vegas, the advantages of 3D controls for milling operations proved a key topic. The use of 3D control systems can offer huge advantages in milling operations. This technology helps increase productivity as the milling machine will only remove what is required, which also hel
  • Toggenburger takes two Terex cranes to tackle a Swiss tandem lift
    August 21, 2015
    Two of the largest cranes in Switzerland recently were called upon to lift an 884tonne, 162m-long connecting bridge between two buildings at the Coop distribution centre in Schafisheim. “The individual bridge components had enormous gross weights of up to 275tonnes and required us to use working radii of up to 29m,” said Andre Huber, project manager at Toggenburger, the company that took on the task. To get the job done, Toggenburger rolled out its biggest machinery which also happen to be the two lar
  • Atlas Copco Combi Cutter becomes mobile shear
    January 6, 2017
    Atlas Copco is launching a new jaw variant that turns its CC 3300 Combi Cutter into a mobile shear. “Our aim is to be a leading manufacturer and solution provider for the demolition market. To round off our offerings in the silent demolition tools segment, we are introducing a mobile shear jaw for our CC 3300 Combi Cutter,” explains Wolfgang Hohn, product line manager, silent demolition tools.